Key takeaways
- The base of the wall concentrates the maximum hydrostatic pressure and requires a continuous compressed seal.
- Escaping grout immediately creates gravel pockets through localised washing out of the mix.
- Cellular foam profiles or sealing strips compensate for flushness defects between formwork panels.
- Visual checking by light penetration before closing guarantees the absence of gaps beneath the panels.
Leakage mechanisms at the base of panels and associated edge defects
When pouring a wall, the column of fresh concrete exerts maximum hydrostatic pressure at the base of the formwork. If the contact between the formwork panel and the concrete substrate (raft or slab) has the slightest gap, the liquid, fine fraction of the mix is forced out under pressure. This phenomenon causes two major defects: the formation of an unwanted fin that must be trimmed off later and, more seriously, an edge gravel pocket on the exposed face of the wall.
- Edge gravel pocket
- Porous, unbound zone along the edge of a fair-faced surface, resulting from the washout or loss of fine elements and cement under the effect of pouring pressure through an open joint.
Grout loss leads to a lack of binder across the first few centimetres of the wall. Aggregates blocked against the reinforcement or the edge of the formwork are no longer coated, leaving the reinforcing steel bare or separated from the air by a fragile crust with no density. According to recognised good practice for reinforced concrete structures, porous concrete cover compromises the durability of the structure against carbonation.
| Defect location | Visible manifestation | Impact on the structure | Required remediation |
|---|---|---|---|
| Formwork base joint | Continuous fin and irregular shoulder | Geometric setting-out defect for partition walls | Mechanical scabbling and edge grinding |
| Wall base under pressure | Gravel pocket and exposed aggregates without paste | Loss of concrete cover and local mechanical weakness | Complete breakout, passivation, and micro-concrete |
| Vertical joint between panels | Vertical fin or stepped surface alignment | Visual defect and sharp edge | Flush sanding using a diamond disc |
| Tie rod hole | Powdery halo and localised cement loss | Risk of ingress through the spacer sleeve | Sealing plug and patch filling |
Sealing devices, profile installation, and pre-pour checks
To ensure tightness between formwork elements, the foreman has access to sealing profiles adapted to the flatness tolerances of the substrate. The irregularity of a rough slab requires the insertion of a compressible shape-memory profile. On steel panels, the original panel gasket must be inspected, cleaned of hardened grout residue, and replaced if it exhibits permanent compression set.
- Preparation of the floor seatingThoroughly clean the setting-out zone using compressed air or an industrial broom to remove sand grains, offcuts of tie wire, and dust likely to lift the formwork.
- Installation of the compressible stripApply a self-adhesive cellular foam set back 3 to 5 mm from the finished fair-faced surface. This setback prevents the seal from bulging inside the wall when tightening push-pull props.
- Locking formwork panel connectionsAssemble modular panels using alignment clamps or wedges specified by the manufacturer, observing the locking torque to ensure uniform compression of the edge seal.
- Dry-pack mortar packing at panel basesIn the event of a significant level discrepancy exceeding the foam thickness, lay a bead of non-shrink mortar or fix a sealed stop-end batten to the slab.
The contractor takes the necessary measures to execute the works in accordance with the drawings and recognised rules of technology, avoiding surface defects attributable to the equipment used.
norme SIA 118
Finally, the performance of the joints depends directly on the stability of the entire assembly under load. Under OTConst art. 17, measures must be taken so that workers are not endangered by the collapse of structural elements or falling materials. Correct tightening of tie rods and propping ballast ensures that seal compression is maintained throughout the concreting phase.
Treatment of discontinuities: panel joints and corner connections
The junction between two vertical formwork panels is the primary source of grout loss above the seating line. Under the hydrostatic thrust of fresh concrete, the slightest lack of tightness in assembly clamps or uneven compression of the profile seals integrated into the steel frame will push the formwork lips apart. This phenomenon immediately results in longitudinal fins on the struck concrete surface, followed by a local disruption of fine aggregates that weakens the cover to perimeter reinforcement.
| Joint location | Recommended sealing profile | Method of fixing | Risk in the event of failure |
|---|---|---|---|
| Vertical panel joint (panel to panel) | Cellular EPDM foam strip or integrated neoprene lip | Recessed into the original groove of the steel profile | Sharp protruding fin, linear gravel pockets |
| Panel junction on existing concrete kicker | Self-adhesive closed-cell polyethylene foam (form face) | Bonded to the bottom profile of the panel, trimmed flush | Leakage under pressure, bleeding, friable bottom edge |
| Internal or external corner junction | Chamfered corner profile with flexible sealing lip | Screwing at the bottom of the groove or clamping by corner profile | Stony shoulder, total loss of binder matrix |
| Wall stop-end and construction joint | Trapezoidal timber/elastomer profile fixed to perforated sheet | Through-nailing or screwing onto stop-end plywood | Full-depth edge gravel pocket, grout on starter bars |
For timber make-up pieces or connections to existing elements, tightness cannot rely solely on cutting accuracy. The application of a suitable compressible profile is required. If the gap exceeds permissible contact tolerances, the residual space is filled with a neutral silicone sealant or a waterproof sealing tape applied to the outer face of the plywood, so that concrete pressure presses the tape tight without tearing it or drawing it into the mass of the element.
Pre-pour inspection and prevention of edge gravel pockets
Grout loss inevitably leads to the formation of an edge gravel pocket. Deprived of their cement and fines matrix, gravel particles jam against corner reinforcement and the form lining without being coated. This defect impairs the local mechanical strength of the structure and exposes reinforcement directly to external aggressive agents, violating the minimum durability criteria specified for structural concrete.
- Visual inspection from inside the panel formworkBefore closing the second formwork face, check the seating seal contact along the blue setting-out line. Verify the absence of tie wire offcuts, rubble, or crushed plastic spacers beneath the sealing flap.
- Verification of mechanical tighteningSystematically check the tightening of every tie rod with its articulated nuts and verify complete locking of inter-panel alignment clamps. A poorly clamped panel will open by several millimetres during the first pour pass.
- Inspection under external glancing lightAfter closing and final tightening of the tie rods, check the ground contact line from outside the wall. Any visible daylight under the bottom transom requires additional external sealing before concreting is authorised.
- Recording and clearance of reservationsThe site foreman or site manager validates the tightness of the base and stop-ends on the pre-pour self-inspection checklist, certifying that grout integrity is ensured until striking.
Managing grout loss and repairing damaged edges
Grout loss observed during concreting indicates insufficient compression or displacement of the sealing profile under the lateral pressure of the concrete. At the base of the wall or along a panel joint, loss of paste causes local segregation: the cement matrix escapes, leaving aggregates jammed without binder. The direct result upon striking combines a rigid protruding fin with an underlying edge gravel pocket, compromising cover to reinforcement.
- Immediate action during pouringAs soon as a leak appears at the base joint, seal the exterior using a fast-setting bituminous mastic or a bevelled wooden wedge pressed against the footing. Do not vibrate the poker within 30 cm of the leak to avoid aggravating the expulsion of fines.
- Clearing and breakout immediately upon strikingRemove the fin using a bolster or a formworker's hammer while the concrete is green. Break out the edge gravel pocket back to sound, dense concrete, fully exposing the bars around their entire circumference if the reinforcement is uncovered.
- Cleaning and substrate preparationRemove dust from the area with compressed air, then wet the concrete to saturation without leaving standing water. The edges of the breakout must form a right angle with the fair face, without feathered bevels.
- Geometric reconstruction of the edgeSet up a clamping straightedge aligned with the existing face to reconstruct the joint backing. Fill the cavity by manually compacting a shrinkage-compensated structural repair mortar, then finish flush with the line of the original formwork.
Regarding construction site liabilities, the contractor remains the guarantor of the compliance of the finished work. Under CO, the contractor is liable for the good quality of the material supplied; if any circumstance compromises proper or punctual execution, they must notify the client. When edge segregation results from a warped formwork panel or poorly compressed foam tape, rectifying the defective structure remains entirely at the formworker's expense in accordance with standard SIA 118.
Frequently asked questions
How do you select the hardness of a sealing profile beneath a formwork panel?
On a rough slab or blinding concrete with surface irregularities of a few millimetres, opt for a thick, soft polyethylene or EPDM cellular foam. It compresses easily under the self-weight of the steel panel. On a concrete kicker perfectly screeded to level, a compact rubber profile or a denser self-adhesive seal guarantees consistent tightness without risking deflection under the pressure of fresh concrete.
Can canned expanding foam be used to seal the wall base?
Single-component canned polyurethane foam is strongly discouraged beneath formwork panels. Under hydrostatic pressure and the vibratory action of the poker, its fragile cellular structure bursts immediately, causing massive grout loss. In addition, polymerised residues adhere strongly to steel or film-faced timber formwork faces, requiring destructive mechanical scraping that damages the fair face during subsequent reuses.
What should be done if the foundation footing is out of level beneath the formwork panel?
If the level error exceeds 10 mm, simply installing a sealing profile is no longer sufficient. A mortar guide kicker must first be installed and screeded level along the wall layout line, or a timber batten fitted with a compressed foam strip must be nailed to the slab. The panel then bears against this rebate, preventing any liquid grout from escaping outward during the vibration of the reinforced concrete.
How should an edge fin be treated on a fair-faced surface intended to remain exposed?
On an as-struck fair-faced surface, the use of a rotary grinder is prohibited because it glazes the surface and leaves an indelible dark stain. The fin must be removed manually with a bolster or a rasp as soon as the panels are opened, while the concrete is green. Finish with light dry rubbing using a carborundum stone, parallel to the edge, to blend the texture without altering the surface skin.