Key takeaways
- The poured slab transfers its self-weight and live loads to the lower propped levels.
- The number of re-shored slabs depends on the bending calculation drawn up by the civil engineer.
- Props are always released from the centre of the span towards the supports.
- Any modification to the propping system strictly requires prior written validation from the civil engineering consultancy.
Determine the number of propped storeys and distribute the fresh concrete load
When an upper slab is poured, the fresh concrete has no load-bearing capacity of its own. The entirety of its density, the weight of the formwork, and the construction live loads are carried entirely by the vertical props. These elements transfer the forces to the slab immediately below. If the latter has not reached its design final strength or if its residual capacity is insufficient to carry twice its self-weight, the force must be distributed across several underlying levels by means of a methodical re-shoring system.
- Re-shoring
- Operation consisting in loosening the initial propping to allow the slab to deflect under its self-weight, then repositioning props snug without forcing, in order to take up only the superimposed loads brought by the levels above.
| Construction site configuration | Level immediately below (N-1) | Underlying level (N-2) | Load transferred to foundations or raft foundation |
|---|---|---|---|
| 1 single propping level | 100% of upper self-weight + dynamic loads | 0% (free slab) | Taken up directly by slab N-1 |
| 2 levels propped continuously (without decompression) | Up to 60% of the cumulative total load | Up to 40% of the cumulative total load | Rigid transfer without activating bending |
| Re-shoring after decompression (good building practice) | Self-weight N-1 autonomous + share of distributed load | Self-weight N-2 autonomous + remainder of load | Progressive activation of slab inertia |
In standard building practice in Romandy, two levels generally remain propped: level N receiving the direct pour, and level N-1 kept supported by drying props or re-shored. In structures with large spans or flat slabs without column heads, the civil engineer may specify partial retention of level N-2 to limit long-term deflection.
Apply the progressive striking sequence under the engineer's written decision
Partial formwork striking and the reinstatement of props are carried out according to a strict phasing defined in the formwork and falsework drawings. The slab must be brought to bear its self-weight symmetrically to prevent unsymmetrical stresses or uncalculated shear force transfers.
- Verification of prerequisites and written authorisationEnsure receipt of the site inspection report or written confirmation from the civil engineering consultancy authorising the start of striking manoeuvres for the level concerned.
- Loosening from the centre of the span towards the supportsRelease the prop screw jacks starting from mid-span towards the load-bearing walls and columns. This direction of removal allows the slab to take its natural deflected shape without locking parasitic forces onto the supports.
- Formwork removal and equipment recoveryLower the drop heads, remove the primary beams, secondary beams, and formwork panels while observing safety instructions.
- Immediate installation of re-shoring propsInstall the re-shoring props strictly aligned vertically with those of the floor below to avoid subjecting the slab to localised bending moments.
- Bringing into contact without forcingTighten the prop shafts only until snug contact under the concrete. The prop must not lift the slab or introduce reverse pre-stressing.
propping and shoring must withstand foreseeable loads and forces, be built in accordance with recognised technical rules, and be dimensioned taking additional loads (vehicles, machinery, deposits) into account.
art. 77 OTConst
Under no circumstances may the contractor unilaterally modify the equipment rotation schedule. If the program requires faster striking to pour the next level, the civil engineer must recalculate the load path and formalise agreement through a dated, signed document in the construction site diary. Responsibility for the mechanical strength of the structure directly follows under art. 229 CP, which penalises breaches of the recognised rules of construction endangering life or physical integrity.
Load redistribution mechanism and verification of force transfers
The transmission of loads when pouring an upper level does not occur by simple static addition. As soon as drying or re-shoring props are tightened, the relative elastic deformations of the hardened slabs and the compressibility of the propping system create a complex vertical structural link. Each floor slab takes up a fraction of the total load proportional to its instantaneous stiffness at that moment. A young slab, whose modulus of elasticity has not reached its nominal value, deflects more and transfers a disproportionate share of the fresh concrete weight to the underlying level. If the phasing fails to control this path, the intermediate lower slab experiences a shear peak and bending moments exceeding the service live loads intended in the final structural design.
The load accumulation phenomenon imposes absolute rigour in the vertical stacking of uprights. Transferred loads must transit purely axially through consecutive slabs without subjecting the concrete to local bending or premature punching shear. Offsetting the axis of a re-shoring prop relative to the one located on the floor below generates parasitic shear in a slab zone not designed for this concentrated point load.
| Level considered | State of the structure | Mechanical function of propping | Indicative cumulative load transfer |
|---|---|---|---|
| Level N (pour) | Liquid to plastic concrete during vibration | Full formwork carrying self-weight and concreting live loads | 100% of the load transferred to prop heads beneath the formwork lining |
| Level N-1 (young slab) | Partially struck, re-shored without forced pre-stressing | Intermediate drying props preventing exceeding allowable limit deflection | Carrying 40 to 60% of the weight of level N according to gained modulus of elasticity |
| Level N-2 (hardened slab) | Floor slab having reached at least 21 to 28 days of maturity | Safety props taking up remaining bending forces | Absorption of remaining load (40 to 60%) transferred directly to foundations |
| Level N-3 (substructure) | Stabilised structure, raft foundation or slab over basement | Complete removal of props after verified stabilised deflection | Zero force originating from the upper concreting phase |
Execution specifications and formalisation of prop release
Releasing a set of props is never improvised on the visual observation of surface concrete hardness alone. Art. 77 OTConst provides that propping and shoring must withstand foreseeable loads and forces, be built in accordance with recognised technical rules, and be dimensioned taking additional loads into account. The construction manager and the site foreman ensure that the written schedule and calculation notes provided by the structural engineering consultancy explicitly incorporate construction loads, such as temporary storage of formwork pallets, wall forms, or concrete skips on recently released slabs.
- Verification of required strengthsCheck crushing test reports of specimens stored on the construction site or use concrete maturity curves to validate the minimum strength class specified by the civil engineer.
- Engineer's written sign-offReceipt of the formal document authorising unpropping of the lowest level in the rotation cycle, specifying areas approved for storage and spans that must remain relieved.
- Progressive decompression of prop shaftsReleasing wedges or quarter-turn loosening of adjusting screws, strictly proceeding from mid-span towards vertical supports to accompany the natural loading of the slab.
- Dismantling and visual inspection of soffitRemoval of steel props, removal of material, and immediate inspection of the concrete soffit to detect any early microcracking or abnormal deflection.
Any deviation from the official phasing places heavy liability on site supervisory staff. In the event of a serious failure to comply with structural provisions generating structural risk, art. 229 CP punishes anyone who, while directing or executing construction or demolition work, intentionally breaches recognised rules of construction and knowingly endangers the life or physical integrity of persons with a custodial sentence not exceeding five years or a monetary penalty. Strict compliance between the equipment rotation plan and the written decision of the site management guarantees worker safety and the long-term integrity of the structural work.
Management of loading anomalies and emergency measures during the striking cycle
On structural work construction sites, failure to follow the de-tensioning chronology or premature concreting on the level above creates direct overloads on immature slabs. If abnormal deflection, severe binding of jack pins, or ceiling crazing occurs, the crew must immediately halt striking operations. In accordance with art. 77 OTConst, propping must withstand foreseeable loads and forces, be built in accordance with recognised technical rules, and be dimensioned taking additional loads into account. The uncontrolled transfer of the fresh concrete mass onto a single intermediate slab creates a risk of sudden structural collapse.
- Halt of placing and securing the zoneImmediately stop the skip or concrete pump on the upper floor. Evacuate workers present beneath the level concerned and install physical barriers prohibiting all access.
- Freeze on decompression operationsProhibit any prop loosening or removal of secondary bearers on the two lower levels. Components under high stress must not be forced with a formwork hammer.
- Installation of emergency props without excessive preloadingPosition supplementary steel props beneath the deflected span, adjusted snug under the slab soffit without creating destructive mechanical camber.
- Formal notice to site management and engineerSend a quantified visual report including recorded crack widths and estimated deflection relative to the floor datum line.
The site foreman then strictly applies the written decision of the civil engineer before any restart of the cycle. The engineer recalculates the redistribution of load transfers and specifies either extended retention of re-shoring over three levels or the installation of steel distribution beams. Any improvised manoeuvre to correct residual deflection by jacking constitutes a serious fault liable to compromise punching shear reinforcement around column heads. The re-loading protocol resumes only after signature of the technical site instruction.
Frequently asked questions
What should be done if a prop refuses to lower when unscrewing the collar?
Never strike the collar or the shaft with a sledgehammer, which risks causing sudden buckling under load. The binding force indicates an abnormal load transfer from the floor above. Stop the operation, check adjacent levels, install two relief props adjusted snug in the immediate vicinity, then inform the site foreman to review the propping phasing with the structural engineer.
Can reinforcement pallets be stored on a newly re-shored slab?
No. Re-shoring is designed only to balance the self-weight of the structure and the construction loads of concreting above according to the calculation note. Concentrated storage of reinforcement bundles generates point loads not incorporated in the load redistribution model. Any heavy material storage on a fresh slab requires prior written validation from the civil engineer specifying the exact permitted area.
How should one react to radial microcracks appearing around a column after striking?
The appearance of radiating cracks around a column head indicates an excessive concentration of shear or punching stresses. Immediately halt the striking of adjacent spans. Reinstall a perimeter of safety props with timber packing beneath the critical zone without forcing the screw jacks. Immediately draw up a written report for the site management and await structural assessment before any further stage.
Why is it forbidden to tighten a re-shoring prop under load?
The re-shoring prop must be placed snug against the concrete soffit, without mechanical preloading. If the operative forces the screw jack, they impose an upward reverse shear force not accounted for by the slab reinforcement, locally lifting the concrete off its natural supports. This artificial lifting dangerously alters support lines and prematurely cracks the top face of the slab.
Texts and standards cited
- OTConst art. 77requirements concerning propping and shoring: they must withstand foreseeable loads and forces, be built in accordance with recognised technical rules, and be dimensioned taking additional loads (vehicles, machinery, deposits) into account.
- CP art. 229breach of the recognised rules of construction: anyone who, while directing or executing a construction or demolition work, intentionally breaches the recognised rules of construction and knowingly endangers the life or physical integrity of persons is liable to a custodial sentence not exceeding five years or a monetary penalty; in the case of negligence, not exceeding three years or a monetary penalty.