🧱 CFC 211.1Formwork: wall forms, form liners and surface finish qualityChapter 6 of 10 in the section

Climbing formwork: lifting a high-rise wall in pours

This chapter provides the technical benchmarks to organise and successfully lift climbing formwork on a high-rise wall. You will learn how to position suspension shoes, check the required mechanical strength of the hardened concrete before striking, sequence the hoisting phases, and record the essential inspections for each new pour.

Key takeaways

  • Climbing anchor cones must be secured perpendicular to the formwork panels and fully tied to the reinforcement.
  • The minimum concrete strength specified by the formwork manufacturer governs the hoisting of the platform.
  • The lifting cycle requires a strict sequence: striking, cleaning, shifting brackets, and steel fixing.
  • Systematic torque checks on the climbing shoes ensure load transfer for the next pour.

Climbing anchors and minimum concrete strength for climbing

The operation of climbing formwork relies entirely on transferring vertical loads and overturning moments into the previously cast wall. Loads are transmitted through suspension shoes secured to high-tensile threaded rods screwed into anchor cones embedded in the previous pour. The positioning accuracy of these inserts is the most critical aspect of the operation: any out-of-plumb or misalignment prevents correct bracket locking and generates abnormal shear stresses.

Climbing shoe
Steel bracket secured to the hardened concrete wall by a tie bolt screwed into an embedded cone, designed to support the dead load of the climbing platform and the pressure of fresh concrete.

To ensure anchor integrity, the anchor cone must be tied directly to the shear reinforcement specified on the civil engineer's working drawings. This reinforcement, made of links or loops, prevents the risk of concrete cone pull-out failure. Any direct contact between the anchor tie and a main rebar must be avoided to allow free rotation of the bolt during torquing.

Hoisting the formwork assembly—whether crane-guided or assisted by self-climbing hydraulic rams—cannot begin without formal confirmation that the concrete of the latest pour has reached its minimum allowable compressive strength. This threshold value, usually specified in the formwork supplier's structural calculations, is typically between 10 and 14 megapascals for a rail-guided platform. Measurement is carried out using calibrated rebound hammer tests or by crushing test cubes/cylinders cured under the same environmental conditions as the structure.

Lifting cycle sequence and inspections before each pour

Managing a high-rise wall using climbing formwork requires rigorous cyclic organisation to maintain pace without compromising structural geometry or personnel safety. A typical pour ranges from 2.50 to over 4 metres in height. Each rotation stage relies on dedicated teams for striking, shifting brackets, and fixing reinforcement.

  1. Retracting formwork panels and cleaningLoosen the formwork tie rods, retract the panels on the mobile carriage integrated into the bracket, then clean and oil the form faces immediately.
  2. Installing new climbing shoesUncover the anchor inserts from the latest pour, fit the climbing cones, and secure the suspension shoes to the specified torque.
  3. Vertical shifting of the assemblyUnscrew the lower anchors, hoist the platform and its panels to the upper level, then engage the safety catches onto the shoes.
  4. Reinforcement and geometric adjustmentErect the wall reinforcement, roll forward the panels to the set-out line, check plumb using a heavy plumb-bob or theodolite, and secure the tie rods.

Before approving concrete placement, the site foreman carries out a systematic inspection logged on a tracking sheet. He verifies the absence of residual deflection in load-bearing profiles, the mechanical locking of the shoes, the torque tightening of the anchors with a torque wrench, and the cleanliness of the formwork base at the construction joint. Recognised engineering rules also require checking the proper function of fall-prevention devices on every platform level.

Stage inspection checkpoints before casting the pour
Inspected componentVerification criterionCorrective action
Climbing shoeTorque compliant with the technical data sheetImmediate re-tightening with a torque wrench
Panels and roll-back carriagesRetract-stop locking pins engaged in the closed positionFull engagement and safety pin insertion
Construction jointLaitance removed and substrate wettedHigh-pressure jetting and vacuuming of debris
Wall face verticalityAlignment within project tolerancesAdjustment using base jacks and push-pull props

The overall organisation of workstations must prevent any incident during shifting. According to art. 17 OTConst, measures must be taken at workstations and passageways to ensure workers are not endangered by the collapse of building components or falling objects and materials. The area directly below the climbing formwork must be strictly cordoned off throughout the shifting operation.

Bracket transfer kinematics and platform securing

Vertical shifting of the support brackets is the critical phase of guided climbing formwork. Unlike traditional suspended systems, guide shoes maintain a continuous connection between the steel bracket and the anchor cast into the hardened wall. This kinematic arrangement prevents any outward tilting of the travelling unit during lifting under wind gusts or accidental unbalance.

  1. Striking the form face and locking in the retracted positionUnscrew the through-ties of the panel. Roll back the formwork unit using the roll-back carriages or rack-and-pinion jacks integrated into the main deck until a clear working space of 60 to 80 cm is cleared for face cleaning and fixing reinforcement for the next pour. Lock the mechanical roll-back stops.
  2. Fitting upper guide shoes and torquing climbing conesScrew the new suspension cone into the socket embedded during the previous concrete pour. Position the receiving shoe, engage the base plate, and apply the preload torque specified by the manufacturer using a torque wrench. Check level alignment with the laser datum of the pour.
  3. Unloading lower supports and initiating liftingDismantle the anti-lift devices on the lower shoes. Connect the self-climbing cylinders or the crane to the designated lifting points. Transfer the total load of the unit to the upper shoes via locking pawls or hardened locking pins.
  4. Deck planking coverage and closing access openingsAs soon as the unit lands in its final position, engage the mechanical stop catches and lock the safety pins. Lower trapdoors immediately and unfold the hinged sealing flaps between the main platform and the concrete to eliminate any gaps.

Climbing equipment forms a connected unit of three to four platform levels. The upper platform accommodates workers for guiding the concrete skip and vibrating. The main platform supports formwork retraction and steel fixing adjustments. The lower suspended platforms provide direct access to earlier anchor points for cone removal and grouting anchor recesses.

Managing wind loads, geometric adjustment, and team coordination

At high elevations, wind exposure generates substantial horizontal loads and suction effects on the outer wall faces. These forces are transferred entirely to the climbing shoes and suspension cones. Continuous-rail self-climbing systems maintain stability in higher winds (typically 70 km/h), but fine-tuning vertical alignment requires calm weather to prevent profiles from binding.

Geometric and mechanical checkpoints prior to closing the pour
Inspected itemVerification methodCompliance criterion
Upper anchor shoeCalibrated torque wrenchTorque compliant with manufacturer's data sheet
Verticality of load-bearing profilesCentreline plumb-bob or optical levelPlumb within system alignment tolerances (± 2 mm)
Concrete bearing platesVisual inspection and feeler gaugeFull contact with no air gaps or localized crushing of laitance
Ladder trapdoors and sealing flapsManual checkFully closed, auto-latched, and free of drop gaps
Micrometric adjusting screwsTravel check with steel ruleThreads greased, clean, with spare travel for batter adjustment

Vertical alignment is adjusted using mechanical base jacks located at the foot of the bracket uprights. These threaded spindles allow panel batter to be corrected before installing tie rods. On architectural walls or large lift shafts, coordination between two chargehands is required: one sights with a theodolite or vertical laser plummer from the starter slab, while the other turns the spindles until cumulative deviations are eliminated.

Site organisation requires strict coordination between crane operators and formwork carpenters. Art. 17 OTConst requires that measures be taken at workstations and passageways to ensure workers are not endangered by the collapse of building components or falling objects and materials. During the lifting or hoisting of a climbing panel, the area directly beneath on the ground must be cordoned off and prohibited to all finishing trades.

Managing lifting anomalies and stoppage procedures

On climbing formwork, any mechanical or geometric fault requires the immediate stoppage of shifting operations. When sliding panels or raising brackets, a shoe binding in its guide rail or a seizing anchor rod indicates misalignment or deflection under load. The site foreman logs the stoppage, releases pressure from the hydraulic power pack or slackens the crane slings, and bans all access beneath the suspended platform. The crew verifies the integrity of the kinematics before any resumption of movement.

Partial spalling or cone pull-out of the concrete around an anchor cone constitutes a critical structural non-conformance. If a cone displays abnormal play while torquing the shoe bolt, the load-bearing capacity of the anchor point is compromised. The project's civil engineer must be consulted to define a remediation plan: drilling replacement chemical anchors according to an approved detail, or installing a spreader beam bearing on lower, hardened levels. Loading a bracket whose primary anchor shows radial cracking or slippage is out of the question.

When the out-of-plumb deviation measured by theodolite or heavy plumb-bob exceeds the wall setting-out tolerance, adjustments are made before closing the rear formwork face. Correction is done millimetre by millimetre using the base jacks and push-pull props on the support frames. Any attempt to force alignment by crane pull on a locked bracket irreversibly damages the vertical guide rails and distorts the levels of the upper working platforms.

Frequently asked questions

What should be done if the concrete strength is insufficient on the morning scheduled for climbing?

Lifting the formwork remains strictly prohibited until the compressive strength required by structural calculations is confirmed. The chargehand postpones shifting the brackets and leaves the panels loosened but secured. A new set of rebound hammer tests or site-cured cylinder crushes is conducted a few hours later, adjusting the daily cycle accordingly.

How should one respond to sudden wind exceeding the speed limit during shifting?

As soon as the anemometer reaches the threshold value set by the manufacturer, the operation is halted immediately. If the formwork is being lifted by crane, the unit is lowered back onto its lower anchor shoe or locked onto the guide rail. Platforms are cleared of loose materials, and all mechanical travel locks are engaged.

How should an anchor cone clogged with laitance or damaged be treated?

A shoe bolt must never be forced, as this risks cross-threading or introducing parasitic stresses. The internal thread must be cleaned with a wire brush and blown out with compressed air. If the thread is stripped or distorted, the anchor is condemned, and the engineer defines the installation of a through-tie or an equivalent chemical anchor.

Why does a step or offset occur between two successive wall pours?

This offset often results from inadequate tightening of the lower sealing flap or deformation of the climbing shoe under the pressure of the previous pour. To correct the next pour, the crew compensates for the angle using the frame adjusting jacks, thoroughly cleans the construction joint, and applies a compressed foam gasket to prevent leakage.

Texts and standards cited

  • OTConst art. 17protection against the collapse of building components or falling objects and materials: at workstations and passageways, measures must be taken so that workers are not endangered.