Precast element: receipt on delivery, installation shimming and grouting

On the construction site, a precast concrete element arrives finished and tolerates no adjustments to concrete cover. You will be able to organise joint inspection upon unloading, adjust elevation on rigid shims, brace the component with dimensioned push-pull props, and inject the non-shrink grout without leaving voids beneath the bed or in the ducts.

Key takeaways

  • Lorry inspection checks starter bars, lifting anchors, and tolerances.
  • The bearing rests on non-deformable shims adjusted with a laser level before final placement.
  • Temporary stability is ensured by double push-pull propping mechanically anchored into the slab.
  • The non-shrink grout completely fills the ducts and the void beneath the element.

Receiving the precast element on the lorry and setting installation shims

As soon as the lorry arrives on the raft foundation or working slab, the site foreman inspects the precast component before unloading. This joint inspection makes it possible to detect concrete spalling, possible cracking around lifting inserts, superficial corrosion of starter bars, or deformation of connecting reinforcement. The delivery note and the marks painted on the component are systematically checked against the civil engineer's installation drawings. According to art. 365 CO, if the material supplied by the client is found to be defective, or if any other circumstance jeopardises the regular or prompt performance of the work, the contractor immediately informs the client. In the event of geometric non-conformity or a crushed grouting duct, immediate reporting avoids handling an unusable element.

  • Absolute agreement of the element's identification mark with the assembly drawing and the current phase.
  • Condition of lifting anchors or cast-in threaded sockets: clean threads, absence of hardened laitance, and compliant geometric alignment.
  • Presence and straightness of starter rebars intended for corrugated ducts or structural keyways.
  • Verification of manufacturing dimensions: wall height, column cross-section, blockouts for shear keys, and rebate depths.

Preparation of the bearing surface determines the plumb precision of the finished element. Chalk-line marking establishes the setting out of both wall faces or column corners. Installation shims are then positioned directly beneath the bearing areas specified by the engineer. The tradesperson uses exclusively machined steel shims or certified high-strength plastic shims to take up loads without creep. Timber shims or haphazard stacks that crush under the self-weight of the concrete are strictly prohibited. The thickness of the bedding layer is set between 15 and 30 millimetres according to the detail drawing to allow a consistent flow of grouting mortar.

Selection criteria and arrangement of installation shims under vertical precast elements
Element typeShim materialRequired positioningPrimary role
Square or rectangular columnSteel plates or non-deformable hard plasticAt the 4 corners or 2 parallel stripsLevel setting and transfer of self-weight
Solid load-bearing wallCalibrated stackable flat shimsBeneath stiffener axes, 30 cm from edgesElevation maintenance and joint gap opening
Twin-wall or double wallNarrow high-density bearing shimsUnder each concrete shell, spaced per calculation notesLoad transfer before core concreting

Ensuring temporary stability and executing pressure grouting

As soon as the precast element leaves the lorry and is lowered onto its bearing shims, it constitutes an unstable structure. The crane operator never releases the lifting slings before the component is completely secured with push-pull props. Art. 17 OTConst requires that measures be taken at workstations and traffic routes so that workers are not endangered by the collapse of construction elements or falling objects. Temporary propping withstands not only the weight of the element during the adjustment phase, but also wind loads calculated for the geographic area of the construction site.

  1. Fixing push-pull propsAttach props to the sockets provided in the precast element and anchor them to the ground in the hardened concrete slab using appropriate concrete screw anchors or anchor bolts, never relying on simple mobile ballast.
  2. Plumb adjustmentAdjust the verticality of the element using the millimetric adjustment collar on the props, checked on two orthogonal faces with a heavy plumb bob or a long spirit level.
  3. Perimeter formwork of the bearing jointInstall tight formwork around the base joint, fitted with chamfers to facilitate product entry and air release vents on the face opposite injection.
  4. Injection or pouring of non-shrink mortarInject high-strength fluid mortar into the feed pipes of the corrugated ducts until it flows out continuously through the upper vents, then fill the space beneath the bed.

The bearing and grouting mortar ensures mechanical continuity between the precast element and the underlying slab. This formulated factory product exhibits zero volume shrinkage and develops rapid compressive strength. Prior to injection, the concrete base is cleaned with compressed air to clear grinding dust and saturated with water without leaving standing puddles. For columns with through-anchor ducts, the grout is introduced from the bottom to drive air upward; no air bubbles must remain trapped around the tie bars, which would otherwise compromise the structural anchorage.

Geometric survey of setting out and starter bar management

As soon as lifting operations are complete, the site foreman performs setting out and verticality checks before the bearing mortar begins to set. The vertical precast element, whether a solid wall, a lift shaft, or a column, must align strictly with the lines marked on the ground by the surveyor. Grid lines are checked against reference chalk lines or painted markings on the bare slab, verifying the alignment of reference faces rather than chamfered edges.

The position of starter bars protruding from the floor slab below determines the ultimate strength of the structural joint. When corrugated ducts or blockout boxes at the base of the element receive these rebars, no mechanical forcing with a sledgehammer may be tolerated to correct misalignment. Arbitrary bending would reduce the effective cross-section of the steel and risk spalling the precast concrete cover during final lowering.

Common installation tolerances according to standard SIA 414 and points of attention
Geometric parameterStandard permissible deviationConsequence on assemblyCorrective action on the construction site
Axis alignment at base± 5 mmOffsetting of the load on the lower storeyPry bar nudging before tightening props
Verticality / out-of-plumb± H/1000 (max. 5 mm)Parasitic load in upper connectionsFine adjustment using push-pull prop screws
Top-of-wall / column level± 5 mmBearing defect for incoming slabs or pre-slabsPrior adjustment of shim thickness
Starter bar alignment± 10 mm in the duct axisRebar binding against duct wallGentle straightening with a rebar bender before positioning

Keying, pressure grouting, and releasing temporary supports

The final structural integration of the element relies on perfect keying of the lower joint and filling of rebar pockets. To ensure the transfer of axial loads and shear forces in accordance with the formwork drawings, the space between the underside of the element and the substrate must be completely filled. A non-shrink mortar, formulated to achieve adequate fluidity without bleeding, is introduced either by gravity beneath tight formwork or injected with a mortar pump via lower inlet tubes.

Pressure injection proceeds from the lowest point toward the vents located at the highest point of the pockets. As soon as the grout flows out with equal density and without visible air bubbles through the opposite vent, the opening is plugged with a conical stopper or a shut-off valve. This procedure eliminates any risk of voids beneath the precast element, ensuring continuous bearing of the concrete foot on the pad foundation or slab head.

Temporary stability provided by push-pull props must not be removed until the bearing mortar has effectively hardened. Furthermore, art. 17 OTConst imposes measures to protect workers against the collapse of construction elements at workstations and access routes. Bracing props remain under tension until the grout reaches the minimum compressive strength specified by the civil engineer, generally verified using site-cured test specimens crushed on-site or manufacturer product charts.

The site manager coordinates prop removal following a strict sequence. Fixing anchors secured in the slab and into the element are unscrewed only when the grout has set and the upper floor connections are capable of taking wind loads. In accordance with art. 365 CO, if the contractor notes that reinforcement is missing or that an anchor in the existing structure shows a compromised defect, they immediately inform the client to agree upon structural remediation measures.

Managing precast non-conformities and installation contingencies

On a structural construction site, the arrival of a non-compliant precast element requires a methodical response prior to any unloading or forced installation attempt. When a component shows spalling at edges, damaged lifting inserts, or starter bar positions incompatible with overlapping reinforcement, the site foreman must immediately record these findings on the delivery note and notify site management.

  • Geometric clash of injection ducts: check the actual centre-to-centre spacing of starter bars before fully setting down the component.
  • Unevenness beneath the element: adjust the thickness of high-density rigid shims without stacking more than three shims per bearing point.
  • Grout refusal or leakage: seal the base formwork with quick-setting mastic or thixotropic mortar before resuming injection.

The employer applies measures tailored to the prevailing conditions in accordance with LAA to prevent accidents, which entails prohibiting crane release if temporary stability via push-pull props is not securely anchored. In the event of a major manufacturing defect rendering the component unfit, refusing receipt on the lorry protects the company from unplanned rework costs.

If pressure grouting emerges from a vent without completely filling the duct or the bed, the joint is incomplete. The affected area must be cleared before full set or core drilling must be scheduled and approved by the structural engineer to determine targeted purging and reinjection.

Frequently asked questions

Can a precast column be placed directly on timber shims?

No, the use of timber shims is prohibited under vertical precast elements. Wood deforms under the self-weight of the component and absorbs mixing water from the grouting mortar, creating voids beneath the bearing surface. Only non-deformable high-density synthetic shims or flat steel shims, dimensioned to support the full weight before the grouting joint hardens, are permitted.

What should be done if starter bars from the raft do not fit into the precast wall ducts?

Starter bars must never be ground down or cut on the construction site without written instructions from the engineering office. If there is a slight offset, cold straightening using a bending pipe may be permitted within specified rebar diameters and minimum bend radii. If the discrepancy is too large, the component must remain suspended or be set down on the ground pending a technical solution from the engineer.

When can crane rigging be released after lowering a precast wall?

Unhooking lifting tackle occurs only after push-pull props are fully tightened to the slab and to the precast element. Temporary stability must be completely assured against wind loads and accidental impacts. The team verifies alignment, plumbness, and the tightening of mechanical anchors in the supporting slab before slacking the crane slings.

When can push-pull props supporting a precast element be struck?

Push-pull props remain in place until the grouting or keying mortar has reached the compressive strength specified by the civil engineer. This timeframe typically ranges from 24 to 72 hours depending on ambient temperature and the type of grout used. Premature removal exposes the structure to overturning movement and cracking in the newly injected bearing joint.

Texts and standards cited

  • LAAgeneral prevention rules: to prevent occupational accidents and diseases, the employer must take all measures that experience has shown to be necessary, that are applicable according to the state of the art, and that are adapted to the given conditions; workers assist the employer (notably by using personal protective equipment).