🧱 CFC 211.1Reinforcement: bending, laps and placementChapter 10 of 10 in the section

Storing steel on the construction site: identification, packing and protection

This chapter provides you with the method for receiving, sorting and storing reinforcing steel on the construction site. You will know how to check the match between bending schedules and fabrication tags, organise a storage area kept clear of the ground and maintain batch traceability right up to the final reinforcement of the structure.

Key takeaways

  • Check each bundle tag against the delivery note and the bending schedule.
  • Systematically isolate the reinforcement from the natural ground using timber battens or ground beams.
  • Sort fabricated bars and mesh by structural element to prevent diameter mix-ups.
  • Protect steels from contamination by mud, formwork release agents and standing earthwork water.

Receiving the delivery note and checking the fabrication tags

As soon as the lorry arrives from the reinforcement plant, the gang leader or site foreman takes charge of the delivery note. This contractual document is the starting point for material traceability required by standard SIA 262. It details the steel designation, bar marks, nominal diameters, steel grades as well as cutting lengths and shapes. Checking is not limited to signing the receipt for the driver; it requires physically ticking off each bundle unloaded.

Each bundle of fabricated reinforcement, each pack of straight bars or each stack of welded mesh bears at least one tear-proof metal or synthetic identification tag. This tag indicates the bar mark corresponding to the reinforcement drawing approved for construction, the diameter, the number of pieces and the production batch. If a pack arrives without a tag or with an illegible mark, the unloading of that specific batch must be suspended or the bundle immediately quarantined to avoid any subsequent confusion.

Systematic checks to be carried out during reinforcement unloading
Checked itemReference documentVisual verification point
Steel grade and conformityMill delivery noteRib pattern markings and compliant mill test certificate
Bar mark identificationEngineer's bending scheduleBar mark and quantity of pieces on each tag
Fabrication geometryReinforcement construction drawingsStirrup shape, leg lengths, bending angles
Surface condition of the batchRequirements of standard SIA 262Absence of flaky rust, grease, oil or mud

Once checked and signed, the delivery note is kept in the site office in the technical file for the structure. It serves to prove the steel's origin in the event of an inspection by site management or the civil engineer prior to concreting. Under art. 365 CO, the contractor is liable for the good quality of the material they provide. Maintaining this documentary traceability protects the contractor against disputes regarding the mechanical tolerances of the bars delivered.

Setting up the storage area, packing off the ground and protecting the bars

The steel storage area must be defined from the site installation plan onwards, within immediate reach of the tower crane without oversailing worker walkways or obstructing emergency access routes. The ground must be levelled, compacted and have a slight fall to prevent rainwater accumulation. Reinforcement must never be placed directly on the ground or in the mud at the bottom of an excavation.

Packing off the ground is carried out using timber baulks, softwood battens or concrete ground beams arranged in parallel. The minimum ground clearance must allow ventilation beneath the bundles and prevent mud splashes during wet weather. Timber packing must be spaced at regular intervals, generally every two to three metres, to prevent deflection of small-diameter bars and sagging of prefabricated cages.

  • Physically segregate storage zones by construction phase: foundation slab, basement walls, upper-floor slabs.
  • Keep bundle tags tied to the wire ties until final placement in the formwork.
  • Maintain a walkway of at least 80 centimetres between each storage bay for slinging work.
  • Sheet bundles exposed to splashes of laitance, form release agents or winter road spray.

The surface of the steel must remain clean to ensure proper bond with the cement matrix. While a light coating of non-flaky surface rust is acceptable under trade practice, deposits of grease, bitumen residues or crusts of earth must be cleaned off before reinforcement placement. For mechanical handling of bundles by crane, the construction work ordinance requires ensuring that workers are not put at risk during the handling of heavy materials.

Steel traceability and filing of bending schedules on site

On a reinforced concrete construction site, mixing up a batch of reinforcement is unforgiving. Installing 12 mm diameter bars instead of 14 mm or substituting one steel grade for another compromises the resistance of the structure. The rigorous organisation of traceability begins as soon as the delivery note is signed off upon unloading of the delivery lorry.

Each bundle delivered by the bending plant bears a weather-resistant tag. This tag indicates the order number, the schedule mark, the steel grade, the diameter and the number of fabricated pieces. The gang leader or site foreman must never authorise the untying of a bundle without first checking the perfect match between the physical tag, the delivery note and the civil engineer's reinforcement drawings.

Administrative management in the site office is an integral part of quality control. Methodical filing of documents ensures the chain of justification in the event of an audit or inspection by site management.

  • Immediate filing of the duplicate delivery note in the reinforcement binder, sorted by pour stage and by level.
  • Systematic stapling of a sample tag to the engineer's bending schedule as soon as a bundle is completely consumed.
  • Ticking off on the placement drawing as rebars are incorporated into the formwork to avoid duplicate placements.
  • Retaining all delivery notes on the construction site until acceptance of the work within the meaning of the Code of Obligations (CO).

Physical segregation of diameters and preservation of surface condition

The storage area must be compartmentalised to eliminate mixing of diameters. Two ribbed bars of neighbouring diameters, such as 16 mm and 18 mm, look virtually identical to the naked eye during hurried placement in formwork. Rigorous physical sorting remains the only safeguard against steel cross-section errors.

Direct contact between bars and soil or standing water causes detrimental deterioration of the steel. Clay and mud adhering to the ribs destroy the steel-to-concrete bond required by standard SIA 262. Packing off the ground on dry timber battens or concrete sleepers is an absolute rule, as is the use of breathable tarpaulins during adverse weather or on winter construction sites exposed to de-icing salts.

Organisation matrix for reinforcement storage racks
Storage zoneStored itemsIdentification devicePacking precautions
Straight bar rack12 m or 14 m lengths (diameters 10 to 32 mm)Painted sign at the head of the bay with diameterTimber cross-members every 2.00 m to prevent sagging
Stirrups and links rackStandard shapes for beams and columnsOriginal plastic tag left attached to the bundleStorage on pallets raised 15 cm off the ground
Welded mesh zoneStandard sheets and edge stripsMetal identification plate stating the sheet typeFlat storage on aligned battens, slight fall for water drainage
Special steels zonePunching shear reinforcement, continuity pull-out boxesLaminated routing slip stapled to each crateStorage under covered shelter or watertight ventilated sheeting

During crane handling, chain slings risk tearing off hanging tags. The banksman or machine operator must check that identification remains intact when setting down opened bundles in temporary racks. If a tag is lost, the bundle must be measured with a vernier calliper before any manual re-tagging by the site foreman.

For safety during movement around the storage area, falling objects or tripping over protruding bars must be prevented. The employer applies OTConst art. 17 so that traffic routes and workstations remain free from any danger of collapsing materials or personal snagging.

Handling storage non-conformities and traceability disputes

On a structural work construction site, a break in reinforcement traceability poses a direct structural risk. When a bundle arrives without an identification tag, has a soaked illegible tag or has been unloaded directly into the mud without packing off the ground, the site foreman must refuse to incorporate these steels into the reinforcement of the structure. Untraced B500B or B500A steel cannot be installed on guesswork based solely on visual estimation of the diameter.

  1. Immediate quarantine of the disputed batchPhysically barrier off the doubtful pack of bars or mesh using barrier tape. Mark the batch with red spray paint stating "Blocked" and move the bundle away from the active reinforcement zone to prevent any unintended installation by steel fixers.
  2. Joint check against the scheduleCross-reference the fabricator's delivery note with the civil engineer's bending schedule. Check the number of bars, steel grade, developed lengths and measure actual diameters using a vernier calliper across the ribs and core.
  3. Written notification to the supplierUnder art. 365 CO, if the material supplied or any circumstance compromises the proper execution of the work, the contractor informs the client or their representative. Draft a written complaint without delay, accompanied by photographs of the untagged or contaminated bundle.
  4. Adjudication and re-qualificationRequire the issue of a certified duplicate tag by the reinforcement plant or the return of the batch for reconditioning. If the bars are contaminated with hydrocarbons or clayey soil, order high-pressure cleaning before any placement in the formwork.

The delivery note kept in the site binder serves as legally enforceable supporting evidence during acceptance of reinforcement by site management. In the event of a later dispute regarding the steel grade of a wall or slab, the absence of this document leaves the contractor bearing the cost of non-destructive testing or destructive core sampling for laboratory analysis.

Frequently asked questions

What should be done if a bundle of cut-and-bent bars has lost its tag?

Isolate the bundle immediately to prohibit its use on slabs or walls. Measure the core diameter with a vernier calliper, count the pieces and record the fabrication dimensions. Compare these dimensions with the bending schedule prepared by the civil engineer. If doubt persists or there is no formal match, contact the rebar supplier to re-issue a compliant official tag before any placement in the formwork.

How should reinforcement stored directly on muddy ground be dealt with?

Standard SIA 262 requires a surface condition that guarantees perfect bond with the concrete. Lift the batch using the crane, install timber battens to maintain a minimum ground clearance of 10 centimetres, then wash the steel with a high-pressure cleaner to remove all traces of soil or dried clay. If oil contamination persists, the contaminated bars must be degreased or simply rejected.

Why keep reinforcement delivery notes until the end of the construction site?

The retained delivery note forms the legal and technical link between the mill test certificate, the engineer's bending schedule and the completed structure. During reinforcement acceptance or in the event of a subsequent structural dispute, this document certifies the conformity of the B500B grade delivered. The contractor thus proves that they have fulfilled their material inspection duties in accordance with the rules of the art.

Can offcuts of neighbouring diameters be mixed in the same rack?

No, this practice must be strictly prohibited on the construction site. Confusing a 12 mm and a 14 mm diameter, which is difficult for steel fixers to detect by eye in the rush of a pour, causes a steel cross-section deficit detrimental to the load-bearing safety of the structure. Offcuts must be sorted into labelled racks or cleared to the metal recycling skip according to the site foreman's instructions.

Texts and standards cited

  • CO art. 365material and ground: the contractor is liable for the good quality of the material they provide; if the material provided by the client or the ground designated by them is found to be defective, or if any other circumstance compromises the proper or prompt execution of the work, they must inform the client immediately, on pain of bearing the consequences (para. 3)
  • norme SIA 262requirements relating to passive steel reinforcement for concrete structures, including surface condition, bond and dimensional conformity