Hydrodemolition: purge degraded concrete without damaging sound rebar

This chapter details the purging of degraded concrete by hydrodemolition on load-bearing structures in Romandy. You will learn how to adjust pressures to strip deteriorated paste without microcracking the sound substrate or deforming the reinforcement, whilst planning rubble containment, acoustic mitigation and the mandatory neutralisation of alkaline wash water.

Key takeaways

  • Water pressure selectively eliminates degraded concrete without generating microcracks in the sound matrix.
  • Reinforcing steel retains its full cross-section, cleaned of rust without any mechanical deformation or notching.
  • Impervious containment and acoustic screens protect personnel and the neighbourhood against high-velocity projections.
  • Highly basic hydrodemolition water requires rigorous settling and neutralisation with carbon dioxide.

Selective purging and preservation of load-bearing reinforcement

Hydrodemolition uses ultra-high-pressure water jets, commonly calibrated between 1000 and 2500 bar, to break down concrete via interstitial overpressure within the pore network. Unlike pneumatic breakers or jackhammers that propagate impact shocks and cause microcracks in the residual matrix, pressurised water exploits local mechanical weaknesses. The front of carbonated, delaminated or freeze-thaw-weakened concrete yields instantly under hydraulic thrust, whilst sound, dense and resistant concrete remains intact.

Selective hydraulic purging
Process of eliminating deteriorated concrete by injecting ultra-high-pressure water into the material's porosity, causing its localised breakout without damaging the underlying sound zones or the metal reinforcement.

The major structural advantage of this technique lies in the total preservation of the reinforcing steel. Longitudinal bars and stirrups suffer no impact stress, notching or destructive vibration likely to break their deep anchorage. The jet fully exposes the perimeter of the bars, removing non-adherent rust through cavitation and friction whilst leaving stripped steel ready to receive strengthening or reprofiling systems. Furthermore, the roughness of the sound concrete substrate obtained after work guarantees optimal mechanical adhesion for construction joints.

Technical comparison of structural purging methods
Technical criterionPneumatic / mechanical chisellingRobotic or manual hydrodemolition
Microcracking of substrateHigh (repeated shocks, aggregate debonding)None (pure hydraulic action, sound matrix preserved)
Reinforcement integrityRisk of notches, deformation and looseningPreserved steel, superficial derusting without work hardening
Rear clearance behind barsDifficult beneath dense layers, risk of spallingComplete and uniform around corroded sections
Bonding adhesionLow to medium (polished or fractured surface)Very high (washed aggregates, open roughness)

Nuisance control and process water neutralisation

The kinetic energy developed by the lance propels aggregate chips and concrete debris at ballistic velocities, posing an immediate danger to operatives and adjacent areas. In accordance with art. 17 OTConst, measures must be taken at workstations and passageways to ensure workers are not endangered by falling or flying objects and materials. The construction site must install impervious reinforced tarpaulins, timber hoardings or heavy rubber curtains fully confining the breakout zone.

The continuous operation of motor-pump units and jet expansion generate intense noise levels. Art. 36 OTConst specifies that if the noise exposure level cannot be reduced below the limit value by technical or organisational measures, suitable hearing protection must be worn. The contractor installs soundproof enclosures for high-pressure pumps, suspends sound-absorbing acoustic sheets along scaffolding and restricts working hours in urban environments according to cantonal directives on construction site noise control.

  1. Sludge capture and retentionInstallation of filter booms, coffer dams and dewatering pumps at the low point to collect all water laden with laitance and rubble without run-off onto natural ground.
  2. Mechanical settling of solidsRouting of effluents to baffled skips or a lamella clarifier to separate suspended solids and isolate compact mineral sludge.
  3. Hydrogen potential (pH) correctionAutomated injection of carbon dioxide gas into the liquid flow to neutralise the extreme basicity resulting from cement dissolution and bring the pH back between 6.5 and 9.0.
  4. Discharge monitoringContinuous measurement of turbidity and pH prior to discharge into the public sewer system or transport by tanker lorry to an approved wastewater treatment plant.

Substrate integrity inspection and mechanical clearance of reinforcement

Hydrodemolition separates degraded concrete from sound concrete through hydraulic fracturing within the material's porosity. Unlike heavy chiselling, which propagates microcracks into the residual sound matrix, the ultra-high-pressure water jet stops dead at zones of intact density. The site foreman must immediately inspect the resulting roughness, verify the absence of crushing impacts on quartz or hard limestone aggregates, and ensure complete annular clearance of corroded reinforcing bars.

To ensure flawless stress transfer and durably bond the steel-concrete interface during subsequent structural reprofiling, the passage of the high-pressure nozzle must systematically clear behind the reinforcement. Corroded steel sections are exposed around their entire circumference, with a uniform void allowing the repair material to mould intimately around the ribbed profile.

Substrate behaviour according to surface demolition technique
Structural criterionHigh-pressure hydrodemolitionPneumatic breaker chiselling
Microcracking of retained substrateAbsent (purely hydraulic breakout)Present (shock waves and internal delamination)
Integrity of retained reinforcementTotal (no mechanical impact or notch)High risk of impacts, twisting and debonding
Bond roughness profileIdeal (prominent, unfractured aggregates)Smoothed or fractured with residual powdery debris
Purge depth controlSelf-regulating according to actual porosityRough manual guidance dependent on the operator

Filtration, neutralisation and containment on remediation sites

Hydrodemolition wash water instantly becomes enriched with cement mineral fines and free lime, reaching alkalinity levels incompatible with direct discharge. The collection system must be hermetic: laden liquid must not infiltrate lower slab cracks or run off towards storm water drains. Neoprene containment booms, diaphragm dewatering pumps and mobile retention tanks must intercept all fluids as soon as they are projected.

  1. Capture and primary settlingGravity piping of laitance towards a buffer tank equipped with lamella separators to settle out the heavy sedimentary fraction.
  2. Fine mechanical filtrationPassing through basket strainers then multi-stage filter bags to extract suspended solids down to cantonal discharge thresholds.
  3. Continuous pH correctionAutomated injection of pressurised carbon dioxide into a mixing chamber to bring the pH back between 6.5 and 8.5 without generating aggressive salts.
  4. Disposal of slurry and purging sludgePackaging of dewatered sludge into watertight skips prior to transport via an approved waste disposal channel in accordance with the waste ordinance.

According to art. 36 OTConst, if the noise exposure level cannot be reduced below the limit value by technical or organisational measures, suitable hearing protection must be worn. Hydrodemolition generates considerable acoustic power linked to water expansion through rotating nozzles and bridge deck vibrations. Wearing dual hearing protection (moulded earplugs combined with earmuffs) is mandatory for the lance operator, as is the installation of sound-absorbing acoustic screens around the high-pressure unit to protect adjacent workstations.

Management of stripping contingencies and containment failures

On a structural refurbishment site, hydrodemolition may reveal defects far deeper than identified in the initial diagnosis. When the ultra-high-pressure lance pierces through a wall or exposes reinforcing bars corroded over more than a third of their cross-section, purging must be stopped. The loss of steel cross-section or excessive removal of compression concrete threatens the static equilibrium of the structure. The civil engineer must redefine the propping scheme without delay and recalculate the required supplementary reinforcement.

A contractor who finds that the actual condition of the substrate jeopardises the proper or timely execution of the work must inform the client pursuant to CO. This written notification protects the contractor against the consequences of unforeseen delays or over-depths. A joint inspection record formalises the concrete volumes purged beyond the base contract and validates the emergency shoring arrangement.

Monitoring impact pressures also avoids damaging sound bars. A jet that is too concentrated or incorrectly angled degrades steel-concrete adhesion in rear zones intended to remain bonded. If a bent bar vibrates under the jet or stirrups are sheared off by accidental overpressure, the area must be stabilised. According to art. 36 OTConst, the noise generated requires suitable hearing protection if the sound level cannot be lowered by technical measures. Heavy acoustic sheeting also minimises the risk of flying gravel chips.

  • Shut down the HP pump in the event of an unplanned breakthrough of the slab or wall.
  • Record the incident in writing for the site management, including an inventory of severed reinforcement.
  • Neutralise residual sludge with carbon dioxide prior to resuming any pumping.
  • Replace clogged geotextile filters to restore the recirculation flow rate.

Frequently asked questions

What should be done if the water jet breaks completely through a slab during hydrodemolition?

Immediately shut off the supply to the HP lance. Breakthrough signals through-thickness delamination or an area of totally degraded concrete not identified during diagnosis. Cordon off the lower area to prohibit all access under the slab, erect shoring towers to secure the weakened zone, then call the civil engineer to inspect the opening and design a soffit formwork with supplementary reinforcement.

What should be done if hydrodemolition slurry overflows towards a storm drain?

Stop high-pressure pumping immediately. Seal off the drain using an inflatable pipe plug or sandbags, then pump the standing liquid into the retention tank using an industrial vacuum. Measure the pH of the collected effluent: if any has entered the network, notify local wastewater services and treat the contaminated area.

What clearance tolerance must be maintained behind rebar during hydrodemolition?

Selective purging with a water jet must clear a minimum of 20 mm behind each corroded main reinforcing bar, or a value equal to the maximum aggregate size of the upcoming repair mortar. This clearance ensures flawless bonding without air pockets, whilst retaining substrate roughness without shock-induced microcracking.

Why is CO2 neutralisation preferred for treating process water?

Hydrodemolition water dissolves lime from cement, reaching a pH between 11 and 13. Injecting CO2 forms mild carbonic acid that lowers the pH to a neutral value between 7 and 8 without risking over-acidification of the medium, unlike strong acids such as hydrochloric acid which can corrode pipe networks and complicate disposal.

Texts and standards cited

  • COmaterials and ground: the contractor is liable for the good quality of materials supplied; if the material supplied by the client or the ground designated by the client is recognised as defective, or if any other circumstance jeopardises the proper or timely execution of the work, the contractor shall immediately inform the client, failing which the contractor shall bear the consequences (para. 3).
  • OTConst art. 36noise: if the noise exposure level cannot be reduced below the limit value by technical or organisational measures, suitable hearing protection must be worn.