🧱 CFC 211.1Pathologies of reinforced concrete, diagnosis and strengtheningChapter 1 of 10 in the section

Concrete carbonation: mechanism, depth measurement and consequences

This chapter enables you to assess the progress of chemical neutralisation of concrete on existing structures. You will learn how to correctly perform the phenolphthalein colourimetric test on a fresh core sample, compare the measured depth with the actual concrete cover and model the progression of the front to determine the structural intervention window over twenty years.

Key takeaways

  • Carbon dioxide neutralises free lime and lowers the pH below nine.
  • The phenolphthalein colourimetric test is performed immediately on a freshly fractured concrete surface.
  • Steel depassivation begins as soon as the neutralisation front reaches the reinforcement.
  • The square-root-of-time law projects the progression of the front over the next two decades.

Neutralisation mechanism and measurement procedure using the colourimetric test

The cement matrix derives its initial basicity from the presence of calcium hydroxide resulting from the hydration of silicates. With an initial potential of hydrogen between 12.5 and 13.5, the concrete generates a microscopic film of stable oxides on the surface of the steel: this is the passivated state. On contact with ambient air, gaseous carbon dioxide penetrates through capillary porosity and reacts with free lime to precipitate as calcium carbonate. This transformation consumes the alkaline reserves and drops the pH below the critical threshold of 9, destroying the passivating layer.

Carbonation front
Physical and chemical demarcation line separating the neutralised peripheral zone with low pH from the internal concrete core that remains highly alkaline.

Reinforcement must be protected against corrosion throughout the intended service life by a dense concrete cover of sufficient thickness, suited to the environmental exposure classes.

norme SIA 262

Precise measurement of the front relies on applying a specific pH indicator: an aqueous-alcoholic solution containing 1% phenolphthalein. To obtain a usable value during a structural assessment campaign, the product must imperatively be applied to a sound surface, free of laitance or drilling slurry that would distort chemical equilibria.

  1. Sampling and splittingExtract a concrete core by diamond core drilling or detach a compact fragment using a mechanical chisel. Split the element to expose a rough cross-sectional fracture surface with no trace of cooling water.
  2. Dust removal and sprayingBlow away residual dust using dry compressed air. Spray a fine, uniform mist of phenolphthalein-based reagent onto the fracture immediately after mechanical splitting.
  3. Colourimetric reaction and readingObserve the distinct colour change. The uncarbonated zone instantly turns a bright magenta colour, while the carbonated zone remains colourless. Measure the minimum and maximum distance between the external edge and the coloured line using a calliper.

Kinetics of concrete cover breach and 20-year degradation forecast

The progression of neutralisation follows diffusional kinetics governed by the square-root-of-time law. If a 36-year-old structure has a stabilised front at 18 mm, its specific carbonation coefficient is established at 3 mm per square root of the year. This value depends directly on the compactness of the matrix, the internal relative humidity level and exposure to weathering.

Projection of the neutralisation front and risk of depassivation
Age of the structureObserved mean frontProjection at +10 yearsProjection at +20 yearsStructural impact
25 years10 mm12 mm13 mmPassivation maintained if concrete cover complies with standard SIA 262.
40 years22 mm25 mm27 mmCritical zone: secondary reinforcement loses its alkaline protection.
50 years35 mm38 mm41 mmTotal depassivation of load-bearing reinforcement, active corrosion initiated.

From the moment the carbonation front exceeds the depth of the reinforcement, depassivation occurs. In the combined presence of oxygen and moisture between 60% and 80%, the oxidation reaction starts. The formation of expansive ferric oxides, whose volume reaches three to six times that of the original steel, generates internal tensile stresses exceeding the tensile strength of the concrete.

Over a twenty-year horizon, the lack of remedial treatment inevitably leads to longitudinal cracking along the bars, followed by spalling of edges and complete delamination of concrete surfaces. Beyond aesthetic defects, the residual steel cross-section decreases and the steel-concrete bond deteriorates, calling into question the ultimate limit state of the load-bearing structure according to serviceability requirements.

Structural interpretation of the carbonation front according to standard SIA 262

Interpreting a neutralisation profile is not limited to recording a depth in millimetres on a freshly broken core sample. As part of structural assessment according to standard SIA 262, the direct challenge lies in the statistical comparison between the geometric position of load-bearing reinforcement and the progression of the carbonation front. When atmospheric carbon dioxide has neutralised the cement matrix beyond the nominal concrete cover, protective alkalinity disappears. The passive oxide film protecting the steel breaks down irreversibly as soon as the pH drops below the critical threshold of 9.

Carbonation front
Physical boundary separating sound, highly basic concrete (pH greater than 12.5) from the outer zone neutralised by the formation of calcium carbonate (pH less than 9), visualised by the absence of a magenta colour change during the phenolphthalein test.

On Swiss structures built before the 1980s, insufficient concrete cover is the primary aggravating factor. A neutralisation depth measured at 25 mm may seem moderate for a forty-year-old concrete, but it proves critical on a slab soffit where distribution bars were only spaced 15 to 20 mm from the formwork. The assessment must therefore cross-reference core drilling measurements with precise electromagnetic mapping of the actual reinforcement to identify areas where concrete cover has effectively been breached.

Depassivation stages and structural repercussions over 20 years
Relative position of the frontPassivation statePredictable corrosion kineticsImpact on load-bearing capacity (20 years)
Front more than 10 mm from the steelPassivation intactNone (incubation phase)No loss of cross-section expected
Front 0 to 5 mm awayImminent depassivationInitiation upon moisture penetrationRisk of localised edge spalling
Front having reached the reinforcementTotal depassivationActive according to wet-dry cyclesMeasurable reduction in effective cross-section
Front exceeding reinforcement by > 15 mmWidespread corrosionLongitudinal cracking and flakingLosses of reinforcement cross-section, delamination

Mechanical consequences of depassivation and strengthening strategy

Depassivation and the resulting corrosion do not merely cause aesthetic surface deterioration. The transformation of metallic iron into hydrated oxides generates a volumetric expansion of two to six times the initial volume of the steel. This internal pressure develops tensile stresses within the concrete cover that quickly exceed the characteristic tensile strength of the matrix, leading to longitudinal cracks running parallel to main reinforcing bars, followed by complete delamination of exposed surfaces.

At an advanced stage, the defect impairs the very integrity of the structure through three cumulative phenomena: the progressive reduction of the resistant cross-section of the steel bars, the loss of mechanical bond due to the failure of confinement between the ribs of deformed bars and the cement paste, and the risk of sudden spalling under service loads. When the assessment highlights a loss of effective cross-section in longitudinal bars or stirrups, routine maintenance works are no longer sufficient and structural strengthening becomes imperative.

  1. Survey of residual steel cross-sectionsLocalised mechanical exposure to measure the effective diameter of corroded bars using callipers and calculation of the cross-sectional loss compared with the original reinforcement drawings.
  2. Verification of ultimate limit statesRecalculation of the load-bearing capacity of the flexural or compressive element according to standard SIA 262, incorporating the residual geometry of the steels and the loss of bond.
  3. Selection of the structural strengthening methodApplication of bonded carbon-fibre-reinforced polymer strips to make up for tensile deficiencies, or installation of steel relief structures when the concrete cover no longer allows anchoring of composite reinforcements.
  4. Restoration of physico-chemical protectionApplication of a certified waterproofing coating or hydrophobic impregnation against CO2 diffusion, ensuring neutralisation of the phenomenon for the remaining service life.

Any contractor who identifies a neutralisation front passing through the reinforcement layer on a core sample taken during works must record the anomaly without delay in the site log. If structural defects compromise the overall stability of the element, the intervention of the civil engineering firm is required to validate the load path before any scabbing work or unloading of props. Good trade practice requires ruling out superficial patching that would seal active corrosion beneath an impermeable facing, postponing mechanical failure to the operating horizon of the next twenty years.

Conducting joint assessments and managing structural damage risks

When core drilling reveals a carbonation front that has breached the reinforcement layer, the state of depassivation and corrosion requires a rigorous assessment prior to any rehabilitation decision. The site foreman and the engineer perform a joint inspection on a freshly split core. The colourimetric test using phenolphthalein solution identifies the zone where the pH has dropped below the protective threshold of approximately 9, indicated by the absence of magenta colouring.

  1. Targeted exploratory exposureOpen an inspection pocket using a light chipping hammer in the area where the concrete cover is breached, avoiding notching of the load-bearing steels.
  2. Measurement of cross-sectional lossRemove mill scale and expansive oxides to measure the residual diameter of longitudinal bars and stirrups using callipers.
  3. Transmission of survey data to the engineerRecord the measured carbonation depths and residual cross-sections in order to recalculate load-bearing capacity according to standard SIA 262.

If static calculations show that the residual steel cross-section compromises the structural safety of the work, the engineer prescribes temporary relief propping. The contractor informs the client in writing when concealed defects substantially alter the scope of the works. Under art. 365 CO, the contractor must immediately notify the client if any circumstance jeopardises the correct or timely execution of the work, or bear the consequences thereof. Subsequent structural strengthening then utilises bonded carbon fibre strips or the addition of passive reinforcement completed by an infill pour calculated according to standard SIA 262.

Frequently asked questions

How should an absence of pink colouring after spraying phenolphthalein be interpreted?

The absence of a colour change indicates that the concrete pH has dropped below a value of approximately 9 to 9.2. Atmospheric carbon dioxide has neutralised the portlandite. When this colourless zone reaches the reinforcement, the passivation layer on the steel surface breaks down. From then on, in the presence of moisture and oxygen, the electrochemical corrosion process is initiated, leading to expansion and cracking of the concrete cover.

Why must the test be performed on a fresh fracture surface rather than on the sawn face of the core?

Sawing and rotary core drilling use water that washes uncarbonated cement dust from deeper layers. This highly alkaline slurry contaminates the surface and can turn a zone purple even though it is fully neutralised by carbon dioxide. Only a colourimetric test on a fresh core sample, mechanically split dry just before applying the reagent, guarantees an accurate reading of the penetration front.

At what margin between concrete cover and carbonation front should one be concerned for the next twenty years?

The rate of progression follows a law proportional to the square root of time. If the margin between the actual concrete cover and the measured front is less than 5 millimetres on a thirty-year-old structure, depassivation will occur in the short term. According to standard SIA 262, the absence of a sound margin exposes the reinforcement to a risk of active corrosion within twenty years, requiring preventive intervention.

What procedure should be adopted on a construction site when the front exceeds the reinforcement without visible concrete spalling?

The absence of surface spalling simply means that ambient moisture has not yet allowed fast expansive rust kinetics. Depassivation is nevertheless effective. The site foreman must report the situation to site management and carry out localised exploratory openings. If the diameter of the bars is intact, the engineer will design a surface protection or re-impregnation system to halt progression.

Texts and standards cited

  • SIA 262Standard for concrete structures: durability requirements, structural analysis and detailing of reinforcement.
  • CO art. 365Materials and site conditions: the contractor must immediately notify the client if any circumstance jeopardises the correct or timely execution of the work, or bear the consequences thereof (para. 3).