Shear walls, columns and vertical elements: the execution standard
Aimed at gang leaders, site foremen and site managers, this section covers the rigorous execution of vertical reinforced concrete structures in accordance with standards SIA 262 and SIA 260. From millimetre-accurate setting out to controlling the hydrostatic pressure of fresh concrete, through to confining column reinforcement and finishing fair-faced concrete, it details the practical methods to ensure structural stability and guarantee flawless geometry.
- 10chapters
- 22 000words
- 6sections in the training course
- 60chapters in total
Key values to remember 4
100 cm
Minimum height of the top rail of perimeter edge protection above the working surface
15 cm
Minimum height of the toeboard on formwork working platforms
47 cm
Maximum clear spacing between horizontal members of edge protection
2 m
Unprotected fall height requiring the installation of perimeter edge protection
Technical scope and operational limits
The construction of vertical elements forms the load-bearing framework of any building. This section focuses exclusively on the execution engineering and formwork framework aspects required for pouring shear walls, load-bearing cross walls, columns and stair cores. It covers load transfer according to standard SIA 260, the mechanical resistance of wall formwork panels, push-pull propping kinematics and the rigorous positioning of passive reinforcement in accordance with standard SIA 262.
Emphasis is placed on the temporary phase, often the most critical for the safety of the structure. Masonry crews must master lateral pressures exerted on formwork faces, secure the base of formwork panels to prevent any uplift and coordinate the millimetre-accurate installation of cast-in inserts prior to concreting.
Logical order of progression and execution path
Executing a vertical storey follows a strict operational sequence that allows no improvisation. Each step directly conditions the success of the next and ensures the structural conformity of the structural work.
- 1. Setting out and heavy formworkThe cycle begins with setting out gridlines and checking starter kickers ([A4-01]). The team then sizes its formwork system and adjusts the pour rate to contain the lateral pressure of the fresh concrete ([A4-02]).
- 2. Isolated elements and bracingConstructing columns requires extreme care regarding link confinement and base cleaning ([A4-03]). Load-bearing cross walls are then poured, strictly respecting the integrity of seismic shear zones ([A4-04]).
- 3. Basement waterproofing and architectural concreteIn substructures, earth-retaining walls incorporate watertight joint systems and waterstops ([A4-05]). For internal walls or exposed façades, tie-rod and joint layout takes over to ensure aesthetic appearance ([A4-06]).
- 4. Cast-in items, access and parapetsAnchor channels and inserts are fixed before closing the formwork ([A4-07]). Work on the construction site continues with setting out in-situ stair flights ([A4-08]), integrating precast elements ([A4-09]) and finishes with the geometric casting of roof parapets ([A4-10]).
📘 Chapters in this section 10
Setting out and marking a concrete wall: transferring grid lines before shuttering
Prevent cumulative axis deviations by locking in the setting-out of kickers before erecting formwork panels.
Walls, columns and vertical elementsPouring height and fresh concrete pressure: what formwork can take
Calculate the exact pour rate to prevent formwork bursting under hydrostatic pressure.
Walls, columns and vertical elementsReinforced concrete column: links, slenderness and column base care
Ensure buckling resistance by tightening top ties and meticulously preparing the base.
Walls, columns and vertical elementsShear wall and bracing: why we do not core this one
Identify walls providing overall stability to prohibit any unapproved destructive core drilling.
Walls, columns and vertical elementsBasement wall cast against the ground: base construction joint, waterstop and trade sequencing
Install waterstops without folds to waterproof the buried slab-wall construction joint.
Walls, columns and vertical elementsFair-faced concrete: layout, uniform shade and protection until delivery
Align tie holes and plan panel layouts to deliver a flawless architectural finish.
Walls, columns and vertical elementsCast-in inserts and anchor channels: positioning for subsequent trades
Secure Halfen channels and threaded inserts to prevent any rejection during façade installation.
Walls, columns and vertical elementsIn-situ cast concrete stairs: riser shuttering, going and constant rise
Master Blondel's rule by shuttering regular steps with perfectly consistent nosings and risers.
Walls, columns and vertical elementsPrecast element: receipt on delivery, installation shimming and grouting
Check levelling shims and non-shrink grouting mortar to stabilise columns and twin walls.
Walls, columns and vertical elementsParapet and capping: height, fall geometry and upstand block-out
Adjust the clear height and drip groove of the parapet to ensure compliant waterproofing upstands.