Shear walls, columns and vertical elements: the execution standard

Aimed at gang leaders, site foremen and site managers, this section covers the rigorous execution of vertical reinforced concrete structures in accordance with standards SIA 262 and SIA 260. From millimetre-accurate setting out to controlling the hydrostatic pressure of fresh concrete, through to confining column reinforcement and finishing fair-faced concrete, it details the practical methods to ensure structural stability and guarantee flawless geometry.

  • 10chapters
  • 22 000words
  • 6sections in the training course
  • 60chapters in total

Key values to remember 4

OTConst art. 22

100 cm

Minimum height of the top rail of perimeter edge protection above the working surface

OTConst art. 22

15 cm

Minimum height of the toeboard on formwork working platforms

OTConst art. 22

47 cm

Maximum clear spacing between horizontal members of edge protection

OTConst art. 23

2 m

Unprotected fall height requiring the installation of perimeter edge protection

Technical scope and operational limits

The construction of vertical elements forms the load-bearing framework of any building. This section focuses exclusively on the execution engineering and formwork framework aspects required for pouring shear walls, load-bearing cross walls, columns and stair cores. It covers load transfer according to standard SIA 260, the mechanical resistance of wall formwork panels, push-pull propping kinematics and the rigorous positioning of passive reinforcement in accordance with standard SIA 262.

Emphasis is placed on the temporary phase, often the most critical for the safety of the structure. Masonry crews must master lateral pressures exerted on formwork faces, secure the base of formwork panels to prevent any uplift and coordinate the millimetre-accurate installation of cast-in inserts prior to concreting.

Logical order of progression and execution path

Executing a vertical storey follows a strict operational sequence that allows no improvisation. Each step directly conditions the success of the next and ensures the structural conformity of the structural work.

  1. 1. Setting out and heavy formworkThe cycle begins with setting out gridlines and checking starter kickers ([A4-01]). The team then sizes its formwork system and adjusts the pour rate to contain the lateral pressure of the fresh concrete ([A4-02]).
  2. 2. Isolated elements and bracingConstructing columns requires extreme care regarding link confinement and base cleaning ([A4-03]). Load-bearing cross walls are then poured, strictly respecting the integrity of seismic shear zones ([A4-04]).
  3. 3. Basement waterproofing and architectural concreteIn substructures, earth-retaining walls incorporate watertight joint systems and waterstops ([A4-05]). For internal walls or exposed façades, tie-rod and joint layout takes over to ensure aesthetic appearance ([A4-06]).
  4. 4. Cast-in items, access and parapetsAnchor channels and inserts are fixed before closing the formwork ([A4-07]). Work on the construction site continues with setting out in-situ stair flights ([A4-08]), integrating precast elements ([A4-09]) and finishes with the geometric casting of roof parapets ([A4-10]).

📘 Chapters in this section 10

Walls, columns and vertical elements

Setting out and marking a concrete wall: transferring grid lines before shuttering

Prevent cumulative axis deviations by locking in the setting-out of kickers before erecting formwork panels.

Walls, columns and vertical elements

Pouring height and fresh concrete pressure: what formwork can take

Calculate the exact pour rate to prevent formwork bursting under hydrostatic pressure.

Walls, columns and vertical elements

Reinforced concrete column: links, slenderness and column base care

Ensure buckling resistance by tightening top ties and meticulously preparing the base.

Walls, columns and vertical elements

Shear wall and bracing: why we do not core this one

Identify walls providing overall stability to prohibit any unapproved destructive core drilling.

Walls, columns and vertical elements

Basement wall cast against the ground: base construction joint, waterstop and trade sequencing

Install waterstops without folds to waterproof the buried slab-wall construction joint.

Walls, columns and vertical elements

Fair-faced concrete: layout, uniform shade and protection until delivery

Align tie holes and plan panel layouts to deliver a flawless architectural finish.

Walls, columns and vertical elements

Cast-in inserts and anchor channels: positioning for subsequent trades

Secure Halfen channels and threaded inserts to prevent any rejection during façade installation.

Walls, columns and vertical elements

In-situ cast concrete stairs: riser shuttering, going and constant rise

Master Blondel's rule by shuttering regular steps with perfectly consistent nosings and risers.

Walls, columns and vertical elements

Precast element: receipt on delivery, installation shimming and grouting

Check levelling shims and non-shrink grouting mortar to stabilise columns and twin walls.

Walls, columns and vertical elements

Parapet and capping: height, fall geometry and upstand block-out

Adjust the clear height and drip groove of the parapet to ensure compliant waterproofing upstands.