Key takeaways
- The actual strength of the concrete governs any placement of heavy pallets on a recent slab.
- The site installation plan establishes the authorized storage areas directly above supports.
- Placing spreader timbers under pallets prevents punching shear and early cracking.
- The civil engineer must approve in writing any point load exceeding the nominal imposed load.
Actual concrete strength and permissible loading schedule
Placing a masonry pallet weighing over one tonne in the middle of a freshly poured span causes irreversible deformations. Even if the concrete appears hardened on the surface, its flexural tensile strength and modulus of elasticity develop much more slowly than its compressive strength. Premature loading creates through microcracks that reduce element stiffness, increase long-term creep deflection, and degrade reinforcement corrosion protection, in direct contradiction with the serviceability requirements of standard SIA 262.
| Concrete age | Target relative strength | Permitted operations | Storage restrictions |
|---|---|---|---|
| 3 days | Low fraction of fck | Light foot traffic | No pallet or skip placement |
| 7 days | Partial stiffness gain | Setting out and light propping | Storage limited to wall heads |
| 14 days | Intermediate strength | Erection of lightweight walls | Storage subject to engineer sign-off |
| 28 days | Nominal strength fck | Design service loads | Strict adherence to imposed loads |
Construction site organisation demands rigorous foresight. Under art. 3 OTConst, work must be planned so that the risk of occupational accidents, occupational illnesses, or damage to health is as low as possible. Placing uncontrolled loads on an unstable structure compromises the safety of crews circulating below. The criminal liability of supervisory personnel remains governed by art. 229 CP, which penalises breaches of the recognised rules of the trade endangering the life or physical integrity of persons.
Mass distribution and spatial organisation according to the installation plan
The location of a temporary load determines the bending moments sustained by the slab. Materials delivered by tower crane, such as sand-lime bricks, clay blocks, dry mortar, or reinforcing steel, must never be set down at the geometric centre of spans. The site installation plan precisely identifies access strips and temporary storage areas, which must strictly be located along load-bearing walls or directly above reinforced concrete columns.
- Locating bearing areasIdentify on the execution drawings the exact vertical projection of the lower-level load-bearing walls and columns in order to align storage directly onto these rigid axes.
- Placing spreader padsLay timber balks with a minimum cross-section of 80x120 mm beneath the pallet bearers to widen the footprint and neutralise local punching of green concrete.
- Checking reshoringMaintain the drying props beneath in accordance with the structural phasing plan without ever releasing the screw jacks prior to formal sign-off from the representative.
- Visual check against overloadingProhibit stacking pallets on the slab and check for any local deflection or unevenness before the crane operator fully releases the load.
The site foreman must refuse any departure requested by finishing work subcontractors wishing to stock their work areas prematurely. Before any placement of heavy materials outside the zones designated on the formwork drawing, a brief calculation note signed by the structural civil engineer must confirm technical feasibility. This precaution protects the bare element from premature through-cracking that would compromise the slab's air and water tightness.
Transmission of actions and propping management under green slabs
Prematurely depositing a pallet of bricks or formwork panels on a reinforced concrete slab does not only load the direct bearing section: the action spreads vertically through the network of props down to the ground or lower storeys. According to standard SIA 262, the structure must be able to withstand construction loads without suffering detrimental residual deformations or premature cracking that would degrade the durability of the structure through early depassivation of reinforcing steel.
| Configuration beneath the loaded slab | Path of the point load | Primary structural risk | On-site execution requirement |
|---|---|---|---|
| Full unreleased propping | Almost direct transfer to lower floors and ground | Cumulative overloading of underlying slabs | Verify the load-bearing capacity of lower receiving storeys |
| Stripped slab then reshored with clearance | Local bending of the green slab before prop contact | Shear cracking and onset of punching shear | Snug prop heads firmly into place without forcing with the jack |
| Free slab without relief props | Fully carried by the green concrete in pure bending | Irreversible deflection and through microcracks | Prohibit any heavy storage prior to civil engineer approval |
Placing a concentrated load at the centre of a span generates a positive bending moment far exceeding the design working load specified in the calculation notes. When the flexural tensile strength of the green concrete is exceeded, cracks open on the soffit. These cracks never fully close after removal of the materials, compromising air tightness and exposing passive reinforcement to aggressive agents.
Spreader arrangements and sign-off protocols before cranage
Transporting pallets from the unloading area to temporary storage zones demands strict discipline between the plant operator and the site foreman. The application of OTConst requires measures to be taken at workstations and traffic routes to prevent workers from being endangered by the collapse of building components or falling materials. Preparing the receiving surfaces therefore requires suitable equipment to prevent punching shear from pallet bearers.
- Inspection of installation plan and pouring recordCheck the pouring date and time recorded in the site journal. Calculate the effective age of the concrete taking into account average ambient temperatures recorded under shelter.
- Installation of load-spreading deckingPosition timber planks with a minimum cross-section of 80 × 160 mm or steel beams perpendicular to the main reinforcement to spread the self-weight of the pallet over a wider area.
- Alignment over vertical load-bearing elementsDeposit heavy items exclusively directly in line with concrete load-bearing walls or above girders, avoiding crawl space zones or parapet cantilevers.
- Visual check of soffits and safety propsInspect the soffit of the slab immediately after placement to identify any initiation of cracking or settlement of steel prop heads.
Any deliberate breach of handling instructions and allowable loads directly involves the chain of command. Under art. 229 CP, anyone who breaches the recognised rules of the trade in directing or executing a construction project and thereby endangers the life or physical integrity of persons faces criminal sanctions. Rigorous coordination between the crane operator and the ground crew prevents stacks overturning or sudden settlement of formwork during tower crane lifting operations.
Managing accidental overloading and assessing early cracking
The unplanned set-down of a formwork pack or a pallet of bricks in the middle of an unreshored span demands an immediate response from site supervision. When the load-bearing element is still green, the risk is not limited to instantaneous failure: the concrete undergoes irreversible plastic deformation and premature crack opening that compromises durability regarding reinforcement according to standard SIA 262.
- Load relief and making safeCarefully remove the load using the crane, without dragging it across the deck. If direct lifting is impossible, install emergency propping beneath the slab from the floor below, snugged up with the jack without over-forcing to prevent destructive reverse jacking.
- Formal joint condition surveyInspect the soffit and the top surface. Measure crack widths using a graduated crack microscope and record the residual deflection relative to the initial propping level. Map the crack pattern: transverse flexural cracking at mid-span or onset of shear cracking near supports.
- Formal notice to the representativeUnder CO, if any circumstance compromises the proper or punctual completion of the work, the contractor shall inform the client. Forward the geometric survey and crack width measurements without delay to the structural civil engineer.
Strict compliance with the recognised rules of the trade is mandatory on load-bearing structures. Breaches of the recognised rules of the trade are covered by art. 229 CP, which penalises anyone who endangers the life or physical integrity of persons by breaching these rules. Corrective measures approved by the engineer then cover maintaining reshoring props longer, potential pressure injection to restore corrosion protection of the steel according to standard SIA 262, or recalculation of ultimate load-bearing capacity.
Frequently asked questions
Can temporary storage of a pallet be authorized if placed directly against a concrete wall?
Yes, but only with the agreement of the site management. Slab strips located along a wall or directly over a column primarily act in direct shear and do not undergo maximum mid-span bending moments. However, it is essential to verify on the formwork drawing that the slab has no concealed openings or service penetrations weakening this direct support prior to any placement.
How should authorized storage areas for secondary trades be marked out?
The site foreman must mark out on the floor, using marking paint or heavy-duty tape, the exact perimeter defined on the site installation plan. Each designated zone must receive a sign clearly indicating the allowable imposed load in kilograms per square metre and the maximum stacking height. This visual information holds subcontractors accountable and prevents unapproved placement across open spans during crane deliveries.
Must props systematically be kept beneath a slab loaded with materials?
As soon as the expected construction site load exceeds the nominal design imposed load, or if the concrete has not reached its specified characteristic strength, a load-transfer propping system must remain under tension. These uprights must not be loosened and forced back up, but maintained snugly in place under inspection to transfer vertical loads to the lower storeys without damaging the curing structure.
What residual crack width requires structural intervention according to standard SIA 262?
For internal elements not exposed to moisture, the nominal crack width limit defined by standard SIA 262 is generally set between two and four tenths of a millimetre, depending on durability requirements. If an accidental overload causes wider cracks, the civil engineer must assess the risk of premature corrosion of the passive reinforcement and prescribe bridging or resin sealing to ensure the required durability.
Texts and standards cited
- COmaterials and ground: the contractor is liable for the good quality of materials supplied; if the material supplied by the client or the ground designated by the client is found defective, or if any other circumstance compromises the proper or punctual completion of the work, the contractor shall immediately inform the client, under penalty of bearing the consequences (para. 3).
- CP art. 229breach of the recognised rules of the trade: anyone who, when directing or executing a construction or demolition, intentionally breaches the recognised rules of the trade and knowingly endangers the life or physical integrity of persons faces a custodial sentence not exceeding five years or a monetary penalty; in the case of negligence, up to three years or a monetary penalty.
- norme SIA 262Concrete and reinforced concrete structures: design, execution, and durability of load-bearing structures