Slabs, floors and floor plates: execution reference framework
Intended for team leaders, site foremen and structural work site managers, this section details the execution of floors and floor plates according to standards SIA 262 and SIA 260. It guides the assembly of propping, punching shear transfer, deflection management and structural connections, ensuring team safety and structural stability.
- 10chapters
- 22 000words
- 6sections in the training course
- 60chapters in total
Key values to remember 4
2 m
Fall height requiring edge edge protection guardrails along slab edges
100 cm
Minimum height of the top guardrail above the walking surface
47 cm
Maximum vertical clear distance between horizontal guardrail rails
15 cm
Minimum height of the toeboard fixed along the floor edge
Technical scope and trade boundaries
The construction of floors and slabs forms the primary horizontal framework of a reinforced concrete building according to standard SIA 260. This technical dossier deals exclusively with mechanical behaviour, formwork, reinforcement and structural assembly of horizontal elements. It covers in-situ solid slabs, job-site or precast floor plates with their top concrete topping, ribbed floors as well as complex cantilevers subjected to severe thermal and static stresses.
The site foreman must maintain strict vigilance over the transfer of forces during concreting. The installation of precast elements requires millimetric verification of bearing surfaces and precise marking of propping lines. Any deviation from formwork and reinforcement drawings directly compromises the compliance of the finished structure with serviceability limit states and ultimate limit states.
Methodical floor execution workflow
To organise slab works without risking structural defects, reviewing execution documents must follow the chronological order of site loads. Installation starts with bearing the precast units and their temporary support, continues with connection reinforcement, and finishes with strict monitoring of striking and temporary loads.
- Installation and continuity of floor platesModules A3-01 and A3-02 detail the adjustment of falsework ledgers, minimum bearing depths on walls, and the installation of shear reinforcement to ensure composite slab monolithism.
- In-situ pouring and lightweight floorsGuides A3-03 and A3-04 cover mid-span reinforcement of solid slabs, adherence to span directions, and the execution of hollow-block floors to limit structural dead load.
- Critical zones and deformationsChapters A3-05 and A3-06 address the risk of punching failure at columns using links or shear stud rails, as well as formwork camber adjustments required by standard SIA 262.
- Geometric specifics and surface finishesFactsheets A3-07 to A3-10 analyse opening trimming reinforcement, installation of balcony thermal break cages, power floating, and strict curing times prior to pallet storage on young slabs.
📘 Chapters in this section 10
Laying precast floor slabs: bearing length, temporary propping and laying sequence
Ensure stability during lifting and comply with the minimum bearing depth required on your supports.
Slabs, floors and precast half-slabsGrouting of floor plates: tie reinforcement and continuity between panels
Achieve structural monolithism of your floor using code-compliant shear reinforcement.
Slabs, floors and precast half-slabsIn-situ cast solid slab: thickness, span and span direction
Optimise formwork depths and master the exact orientation of main load-bearing spans.
Slabs, floors and precast half-slabsBeam and block floor: centre-to-centre spacing, propping and compression slab
Reduce dead loads while securing centre-to-centre spacing and slab pouring.
Slabs, floors and precast half-slabsPunching shear in a slab on column: identify and correctly install specific reinforcement
Eliminate the risk of brittle shear failure around columns using engineered reinforcement.
Slabs, floors and precast half-slabsSlab deflection: precamber during execution and measurement after striking formwork
Anticipate deflection under load and adjust your formwork to the required tolerances.
Slabs, floors and precast half-slabsStair and lift openings: trimmers, edge reinforcement and tolerances
Secure stair and lift openings using strictly reinforced trimmers.
Slabs, floors and precast half-slabsCantilever balcony: structural thermal break, installation orientation, and top reinforcement mesh
Prevent any thermal or structural defect by precisely aligning your balcony thermal breaks.
Slabs, floors and precast half-slabsSlab surfacing: power floating, trowelling and finish level to declare
Attain expected flatness through power floating tailored to the target finish class.
Slabs, floors and precast half-slabsLoading green slabs: material storage and critical limits
Prevent early cracking by planning temporary storage loads on green concrete.