🧱 CFC 211.1Slabs, floors and precast half-slabsChapter 4 of 10 in the section

Beam and block floor: centre-to-centre spacing, propping and compression slab

This chapter provides site benchmarks for setting beam centre-to-centre spacing without drift, arranging temporary propping beneath the ribs, and ensuring the minimum thickness of the compression slab. You will also master the reinforcement of perimeter ring beams to ensure structural monolithism without relying on rough tolerances.

Key takeaways

  • Beam centre-to-centre spacing requires rigorous wedging using gauge blocks before any final fastening.
  • Mid-span propping must bear beneath the ribs using stable and wedged bearer beams.
  • The thickness of the compression slab must never be reduced below the prescribed values.
  • The perimeter ring beam provides the mechanical connection between the ribbed floor and the load-bearing walls.

Adjust beam centre-to-centre spacing and secure mid-span propping

Precast ribbed floors are very unforgiving of installation deviations. Unlike a solid slab cast on continuous formwork, a prestressed or lattice girder beam relies on a strict geometry governed by the infill blocks, whether made of clay, concrete, or synthetic materials. A spacing that is just a few centimetres too wide causes the block bearing to slip off the bottom flange of the rib. Conversely, an over-tight spacing pinches the infill and misaligns the entire span.

  1. Positioning of gauge unitsLay a first beam along the bearing line, observing the minimum bearing depth on the load-bearing wall. Place two infill blocks at the ends and one in the centre to set the exact distance to the next beam without measuring each span with a tape measure.
  2. Installation of propping bearer beamsPlace timber bearers or steel beams perpendicular to the ribs, either before or immediately after craning, depending on the span. Telescopic props are adjusted to direct contact under the bottom flange, without forcing, so as not to arch the structure artificially.
  3. Interlocking the infill block layerInterlock the rows of blocks, working from one support towards the other. Any cracked, broken, or spalled unit is discarded to prevent localised collapse under the load of personnel or fresh concrete.
Checkpoints for beam installation and prop lines
Inspection stageStandard installation toleranceImmediate corrective action
Bearing depth on wallMinimum 50 mm (as per drawing)Recut or realign the bearing element
Centre-to-centre spacing between ribsMaximum deviation of 5 mmReposition using a rigid template
Level under propping bearer beamCamber of 2 to 3 mm maximumAdjust prop screw collar on a stable sole plate

Master the compression slab and reinforce edge connections

The compression slab forms the compression chord of the floor once the system has hardened. Making this layer too thin to compensate for a finished level or to save material invalidates the structural design assumptions provided by the civil engineering firm. In addition, the top distribution reinforcement loses its minimum concrete cover if the nominal thickness of the topping slab is not scrupulously maintained across the entire surface.

Edge tie
Continuous longitudinal and transverse reinforcement arranged along the floor perimeter, securing the heads of walls and anchoring the beams into the supports to prevent lateral displacement and stiffen the structure.

The perimeter ring beam must be shuttered and reinforced with mechanical continuity. Longitudinal reinforcement is threaded through the stirrups at the beam ends or beneath the edge top bars. Welded mesh laps for the compression slab must overlap by two full meshes to prevent shear cracks along the edge beams. Any visible deformation of the edge formwork under lateral pressure must be restrained with wedges and clamps screwed to the masonry supports.

The requirement for structural integrity is among the fundamental duties of the contractor. Art. 229 CP penalises anyone who, in directing or executing a construction or demolition, intentionally breaches the recognised rules of construction and knowingly endangers the life or physical integrity of persons. Negligence regarding the poured thickness or omission of an edge ring beam therefore directly engages the liability of site supervisory staff.

Pour coordination and performance under temporary loading

The precast rib and hollow-pot floor forms a structural assembly that is particularly vulnerable during its transitional phase. Before the in-situ concrete achieves its mechanical strength, the beam flanges and lines of props bear the full self-weight of the blocks, the fresh concrete, and the dynamic construction site live loads. Inadequate spacing of temporary supports or a concentrated point load will immediately cause shear microcracks at the web-flange junction or the collapse of infill blocks beneath the feet of workers.

Structural checks before and during concreting of the ribbed slab
Inspected elementCritical checkpointExecution toleranceImmediate corrective action
Mid-span prop linesTightness of wedges, plumbness of prop tubes, and locking of tripodsMaximum axial deviation of 20 mmPlumbing beneath stringer and re-wedging under zero load
Bearings on masonry or concrete wallPenetration depth of beam bottom flangesMinimum length of 50 mmInstallation of a base rail or support via end bracket/hanger
Crack-control meshPositioning in the upper third of the compression slabCover maintained to ± 5 mmInstallation of plastic or concrete spacers every 60 cm
Perimeter ring beamContinuity of anchor bars and lap lengths of steel reinforcementLap length prescribed by the structural engineerSplicing with tie wire or splice bars per formwork and reinforcement drawings

Concreting proceeds along the axis of the beams to balance pressure on the infill blocks and prevent any lateral buckling of the ribs. Special attention is paid to compaction in narrow ribs: the vibrating poker must not remain in prolonged contact with the prestressing steel or main beam reinforcement to avoid breaking the bond between steel and precast concrete. The foreman ensures that the pumping output does not cause local material accumulation exceeding the nominal gross slab thickness by more than 50 mm.

Striking, mechanical continuity and structural acceptance

Deferred load transfer
Structural process of gradually transferring bending stresses from temporary propping to the final composite section (precast bottom flange, cast-in-place rib, and hardened compression slab), conditional upon reaching the characteristic compressive strength of the in-situ concrete.

Dismantling of propping is systematically performed starting from mid-span towards the end supports. This sequence avoids transferring unintended cantilever loads onto adjacent beams. The tradesperson uses progressive decompression pins to release the load without dynamic shock. If an upper floor is to be formed and poured immediately afterwards, partial repropping without forcing residual deflection is installed to transfer construction site loads down to the foundations or to lower slabs that are already stabilised.

  1. Verification of structural curingCheck strength test reports or consult the responsible civil engineer before any lowering of prop screw jacks.
  2. Axial decompression of spansUnscrewing prop heads starting from the centre of the span, observing the behaviour of the compression slab under self-weight.
  3. Load transfer to curing propsRe-placement of safety props under stringers without excessive preloading if heavy storage or an upper-floor pour is scheduled.
  4. Visual inspection of soffit and bearing levelsThorough examination of the beam soffits, checking for any transverse cracks, and verifying the sound condition of edge connections.

The acceptance of the work for the structural shell involves checking residual deflections against the floor level laser reference datum. Overall execution tolerances are assessed according to recognised technical rules for reinforced concrete frameworks. The contractor records propping inspections, pour dates, and clearance of punch list items in the construction site journal before handing over the surface to the finishing work trades.

Management of structural non-conformities and propping adjustments

On a beam and block floor, geometric or mechanical anomalies are unforgiving. If a deviation in beam spacing is discovered before concreting, the placement of the blocks becomes unstable. If the offset exceeds the manufacturer tolerances, forcing the element or laying it with insufficient bearing is prohibited: the beam must be lifted and realigned using a gauge rod before placing the reinforcement mesh.

  1. Abnormal deflection of the propping bearerIf a level drop appears during erection, stop loading. Check the wedging of prop bases on stabilised ground and retighten the screw jacks without imposing excessive upward camber that would shear the bottom flanges of prestressed beams.
  2. Deficit in compression slab thicknessA pour level that is too low reduces the lever arm and load capacity. Never skim or patch retrospectively dry. Inform the civil engineer to assess structural strengthening or bonded reprofiling in accordance with their formal instructions.
  3. Displacement of perimeter ring beam reinforcementEdge bars and continuity top steel pushed against the formwork must be repositioned immediately on their spacers to ensure the prescribed cover and tying of the slab.

Frequently asked questions

How should one react if an infill block breaks under foot traffic during reinforcement installation?

Access to the weakened area must be barred immediately. Replace the damaged block from the working platform below or lay temporary load-spreading planks supported exclusively on the adjacent beams. Never pour concrete into a cracked block without first sealing it, as this unnecessarily increases floor self-weight and alters the prescribed geometry of the compression slab.

What should be done when a beam has insufficient bearing on the load-bearing wall?

The minimum bearing length defined on the layout drawing must be scrupulously observed. If the masonry is out of square, reducing the seat below the required value, pouring as is is strictly forbidden. A propping rail must be placed tight against the load-bearing wall to provide a secure temporary support, and the civil engineer must be consulted to design a remedial detail using fishplates or a reinforced pocket.

Can a deficit in slab thickness be compensated for with a subsequent finishing screed?

No. The in-situ compression slab resists bending compression stresses and ensures the monolithic connection of the beam-block assembly. A floating screed or unbonded bedding mortar poured after setting contributes nothing to the structural performance of the work. A deficit in thickness directly affects the overall load-bearing capacity calculated by the civil engineer and requires validation through their structural calculations.

When can intermediate mid-span props be removed?

The striking of props is carried out only when the mechanical strength of the slab concrete reaches the value specified by the engineering firm. According to standard SIA 118, striking and unpropping operations must be conducted methodically from the support towards the centre to prevent sudden load transfers. Any premature removal without formal approval from the site management is strictly precluded.

Texts and standards cited

  • COmaterials and ground: the contractor is liable for the sound quality of the materials he supplies; if material supplied by the client or ground designated by him is found to be defective, or if any other circumstance compromises the proper or timely execution of the work, the contractor immediately informs the client, under penalty of bearing the consequences (para. 3).
  • CPbreach of the recognised rules of construction: whoever, in directing or executing a construction or demolition, intentionally breaches the recognised rules of construction and knowingly endangers the life or physical integrity of persons is liable to a custodial sentence not exceeding five years or a monetary penalty; in the case of negligence, not exceeding three years or a monetary penalty.
  • norme SIA 118General conditions for construction work