Skip to content
Website
🧱 CFC 271Drywall partitions: framing, linings and performanceChapter 6 of 10 in the section

Letting services through: stud perforations, back boxes and making good the lining

On the construction site, coordination with electrical and plumbing installers determines the strength and insulation of lightweight partitions. This chapter details the geometric limits for holes in metal studs, the mandatory acoustic treatment of flush-mounted boxes and the method for making good plasterboard linings, in order to guarantee the mechanical stability and acoustic performance of the work.

Key takeaways

  • The flanges of studs must never be cut, as this destroys their resistance to buckling.
  • Holes in the web remain limited in diameter and centred within the permitted neutral zones.
  • Two opposite electrical boxes must be offset by at least three hundred millimetres to preserve acoustic performance.
  • Any penetration through the lining requires complete filling with reinforced plaster to restore the mass.

Perforating metal sections without destroying the mechanical strength of the framing

The metal framing of a drywall partition ensures the stability and overall mechanical strength of the work against impacts from use, internal wind and air pressures. The vertical studs, made of galvanised sheet steel six tenths of a millimetre thick, derive all their stiffness from cold roll-forming and from the geometric continuity of their flanges. When an electrical or plumbing installer cuts a flange with shears or notches the framing with an angle grinder to route conduits, the section instantly loses its moment of inertia. The partition then becomes prone to localised buckling, premature cracking of the joints under load and noticeable deformation when doors are slammed.

To allow cables and pipes to run horizontally, SIA 242 and the manufacturers' guidelines require the use of the original perforations or of strictly calibrated holes in the web of the stud. Industrial sections have prepunched H-shaped openings every sixty centimetres along their height. If these openings do not match the routing of the services, manual drilling is tolerated at the exact centre of the web. Use a nibbler or a suitable circular punch, and avoid abrasive discs, whose heat destroys the zinc coating and initiates tearing of the sheet steel.

Drilling limits in the web of metal sections
Web width (mm)Maximum diameter (mm)Minimum distance to edge (mm)Minimum spacing between holes (mm)
502512500
753515500
1005020500

When a bundle of conduits exceeds the permissible diameter for a single section, the constructive solution is to form a reinforced opening before the electricians start work. The vertical stud is doubled with a twin section back to back, fixed together with self-drilling screws every thirty centimetres, or horizontal trimmers made of tracks are inserted to transfer the loads to the neighbouring studs. The plasterer refuses to fit the linings as long as the framing includes studs weakened by non-compliant cuts made on the construction site.

Treating back-to-back electrical boxes and ensuring a sealed making good

The insertion of flush-mounted electrical boxes is the leading cause of measured acoustic degradation in finished lightweight partitions. Cutting the plasterboard to house sockets or switches locally removes the surface mass of the lining and creates a direct air path through the internal cavity. If two boxes are placed face to face in the same bay of the framing, the sound insulation of the wall drops by several decibels. This weakness ruins the mass-spring-mass principle and prevents the contractual sound insulation values specified according to SIA 242 from being achieved.

To guarantee sound insulation between two adjoining rooms, the boxes located on either side of the partition must be offset horizontally by at least three hundred millimetres, or occupy separate stud bays. The plasterer checks that the mineral wool insulation remains continuous between the linings, without excessive settling or gaps. In separating partitions requiring high acoustic performance or certified fire resistance, standard boxes must be protected by a rear cover made of plasterboard or replaced by special acoustic boxes fitted with intumescent pads and soundproof elastomer seals.

  1. Cutting and chamferingNeatly cut out the outline of the opening with a plasterboard hand saw, then bevel the edges of the board at forty-five degrees to mechanically key the filling plaster.
  2. Fitting framing reinforcementsFor openings wider than one hundred millimetres, insert a dry timber batten or an offcut of metal track into the cavity, then screw it firmly from the sound face of the lining.
  3. Filling to restore massCompletely fill the annular void around the conduits with plaster of Paris or a heavy filler, compacting the material to restore the mass and eliminate any through air gap.
  4. Reinforcement and finishingEmbed a microperforated reinforcing tape in the fresh jointing compound, then press and smooth with a wide knife to leave a flat surface ready for the painter.

Decisions on the construction site: refusing uncontrolled cuts by the services trades

The metal framing of a drywall partition ensures mechanical strength under horizontal load and the flatness of the finished lining. When the electrical or plumbing installer works after the vertical studs have been aligned, there is often a temptation to cut the sections in order to pass bundled ICTA conduits, drain pipes or distribution manifolds. For the drywall plasterer, any weakening of the metal section that was not planned when the order was placed is a major non-conformity liable to void the stiffness guarantees and the acoustic or fire-protection test reports.

Studs made of galvanised sheet steel derive their moment of inertia from the C-shape of their flanges and returns. Notching a flange to let a supply pipe through immediately destroys the section's resistance to buckling. Any hole outside the factory-punched knock-outs must be strictly confined to the central web, within the middle third of the partition height, using a deburred circular punch or a nibbler. The angle grinder is strictly forbidden for this work, as the heat destroys the protective zinc and creates tear initiation points leading to failure.

Managing holes and service crossings in the metal framing
Situation encountered on the construction siteConsequence for the workPlasterer's decision / Corrective measure
Flange or return of the stud cut with shears or grinderImmediate loss of mechanical stiffness and risk of cracking under loadFlat refusal. Replace the stud or splice with a reinforcing CW section fixed over the full height.
Circular hole in the web outside the knock-outs (diameter less than 35 mm)Inertia preserved if the hole is centred in the web and located in the middle thirdTolerated without reinforcement, provided the opening is protected by a cable grommet to prevent the conduits from being cut through.
Bundle of conduits forcing the stud out of plumbLining out of flush, joints out of flush and visible bulgeDismantling of the bundle required. Routing spread over several knock-outs or offset brackets fixed.
Large-diameter opening (more than half the web)Loss of transverse resistance and localised saggingForm a horizontal framing trimmer with reinforced sections or double the studs as paired twin sections.

Filling, decoupling and continuity of the linings

Once the conduits have been threaded and the flush-mounted boxes fixed by the electrician, the plasterer closes the second face of the partition. This stage demands absolute rigour regarding the continuity of the acoustic and thermal insulation inside the cavity. The glass or rock wool must be cut neatly around the conduits and boxes, never packed or compressed, to avoid creating acoustic bridges between the two linings in accordance with the principles of SIA 181. Any gap in the insulation at a bank of sockets sharply degrades airborne sound insulation.

The plasterboard must be cut to house the boxes using a hole saw of the exact diameter of the fitting. An oversized or irregular hole weakens the mechanical hold of the box and compromises airtightness. If inspection openings or chases have been cut into the linings afterwards by the installers, the making good must be carried out according to the rules of SIA 242 on plastering and drywall work. No simple plaster stuffing without mechanical reinforcement is tolerated.

  1. Cleaning and chamfering the openingRemove dust from the cut area. Chamfer the sharp edges of the paper and plaster at 45 degrees using a rough-cut plane to promote adhesion of the filling compound over the full thickness of the board.
  2. Fitting battens or back splicesFor rectangular cut-outs exceeding ten centimetres, slide pieces of section or timber battens behind the existing board. Screw them through the intact lining to form a rigid backing.
  3. Inserting a fitted lining pieceCut a piece of board of the same type and thickness as the existing one. Screw this piece firmly to the rear support, sinking the screw heads slightly without puncturing the paper.
  4. Sealing and filling with compoundFill the perimeter gap with a quick-setting jointing compound. Where acoustic or fire-stopping requirements apply, inject a bead of flexible acrylic sealant or intumescent compound around the conduit penetrations.
  5. Reinforcement and smoothing to the agreed finish levelApply a paper or microperforated glass-fibre reinforcing tape embedded in the jointing compound. After drying, apply the finishing coat and sand finely to blend the repaired area into the general plane of the partition according to SIA 242.

The treatment of penetrations through partitions with acoustic or fire-compartmentation requirements leaves no room for approximation. The drywall plasterer makes sure that the conduits passing through are sealed over the full depth of the board with tested and approved products. The final surface finish, whether executed to the usual quality level Q2 or the high-quality level Q3, must make the repair completely invisible in raking light before the work is handed over to the painters.

Execution disputes: procedure for repairing a cut framing

On interior fit-out construction sites, discovering a metal stud cut with an angle grinder by an electrical or plumbing installer means an immediate technical stop. When the flange or return of a vertical section has been notched to force through a conduit or a manifold, the piece loses all of its mechanical inertia. The drywall plasterer must never close the second lining over a weakened framing: under the effect of air pressure differences, door slamming or simply the service load, the partition will flex, causing systematic cracking of the finished joints.

As soon as the non-conformity is found, the foreman reports the damage to site management by a formal notice in the construction site diary. Technical repair is required before any making good. If only the web has an unauthorised perforation too close to an end, fitting a galvanised sheet steel splice riveted on both sides may be sufficient. If, on the other hand, a flange has been severed, the element must be replaced or doubled over its full height with a new stud fixed back to back by structural screwing.

Where flush-mounted boxes are installed directly opposite each other without offset, the plasterer requires the offending fitting to be removed or installs a specific acoustic cover behind the box, made of dense plasterboard and heavy acrylic sealant. Once the conformity of the framing and insulation has been restored, the lining is made good according to the rules of SIA 242: clean squaring of the board, chamfering of the butt edges, fitting of a framing reinforcement under the joint if the opening exceeds the tolerances, then taping and careful coating.

Frequently asked questions

What minimum distance must be maintained between two holes in a metal stud?

The accepted rule requires each perforation to be spaced at least three times the diameter of the largest opening, with a minimum of 300 mm centre to centre along the web of the section. Every hole must remain centred in the web, more than 50 mm from the top and bottom ends. Cutting into the flanges or flange returns is strictly prohibited, as it destroys the strength of the framing.

How should electrical boxes placed face to face in an acoustic partition be treated?

Installing boxes directly opposite each other creates a major sound bridge that ruins the sound reduction index of the wall. SIA 242 recommends a horizontal offset of at least 600 mm centre to centre between the boxes of opposite linings. If this arrangement proves impossible on the plans, the tradesman must encapsulate the back of each box in a sound-damping enclosure built from dense plasterboard and sealed with acoustic sealant.

What should be done when an electrician has enlarged a factory-punched hole with shears?

A deformed or sheared knock-out has sharp edges that threaten the cables and weaken the metal stud. The plasterer's team leader must reject the work and require an insulating plastic protective grommet to be fitted on the metal edge. If the cut extends onto the flange or weakens the bend zone of the steel, the element must be reinforced with a nested section screwed on both sides.

How should a plasterboard with an oversized hole around a technical panel be repaired?

A gap of more than 10 mm around the box cannot be filled with compound alone. A clean square must be cut out of the lining as far as the adjacent studs, metal support cross-pieces screwed to the framing inserted, a fitted piece of board fixed according to SIA 242, then the joints filled with setting compound reinforced with jointing tape. The final flatness must meet the agreed quality level.

Texts and standards cited

  • norme SIA 118General conditions for the execution of construction work
  • norme SIA 242Plastering, rendering, drywall construction

In the same section