🧱 CFC 271Fire protection and acoustics of dry constructionChapter 6 of 10 in the section

Decoupling the edges: resilient strip, tightening of the tracks and flanking transmission

By the end of this chapter, you will know how to size and install the resilient strip correctly under the perimeter profiles of a dry-lining partition. You will master the tightening torque of the fasteners so as to compress the material without destroying it, thereby ensuring the acoustic insulation required by standard SIA 181 against flanking transmission through the bare structure.

Key takeaways

  • The resilient strip decouples the track from the bare slab to stop structural flanking transmission.
  • Over-tightening destroys the porosity of the material and creates a rigid acoustic bridge that is highly detrimental.
  • The profile must receive a strip that overhangs across its full width, including vertical sides and top.
  • Standard SIA 181 penalises any direct contact between the metal framing and the structural work immediately.

Flanking transmission and the acoustic role of the strip under the track

In dry construction, lightweight walls never work in isolation. Airborne sound waves striking a lining set the galvanised steel profile framing vibrating. If the floor or ceiling track is fixed directly against the reinforced concrete without any break in impedance, this vibration passes instantly into the adjacent slab or wall. Sound does not only pass through the partition: it bypasses the separating element via the slabs and cross walls. This flanking transmission through the structure ruins the overall acoustic performance of the building, even if the plasterboard linings and the mineral wool inside are correctly sized.

Flanking transmission (flanking noise)
Transmission of acoustic energy from one room to another via the building elements adjacent to the separating wall, notably bare slabs, façades and load-bearing walls.

Applying standard SIA 181 requires strict control of the noise level perceived between adjacent dwellings or offices. To meet the minimum or enhanced requirements of this standard, placing a resilient strip at the base and edges of the partition is the first line of defence. The resilient strip acts as a mechanical damping spring. It breaks the rigid steel-to-concrete contact, preventing the load-bearing structures from being set into resonance through the network of secondary framing. Omitting this decoupling or using an unsuitable material exposes the contractor to a major non-conformity during on-site acoustic acceptance measurements.

Acoustic decoupling does not concern only the bare floor before the floating screeds are poured. The vertical sides rising against pillars, façade walls or internal masonry, as well as the top track under the upper slab, require exactly the same treatment. A single residual rigid connection per track cancels the benefit of the insulation inside the framing.

Installation, permissible compression and tightening management

To ensure its lasting elastic function, the resilient material must be chosen according to its density and its crushing behaviour. Commonly used are strips of closed-cell cross-linked polyethylene foam, bituminous acoustic felts or dense elastomer rubber strips. The nominal thickness under the uncompressed track generally varies between 3 mm and 5 mm. The width of the strip must be strictly equal to, or slightly greater than, the flange of the metal track, for example 50 mm, 75 mm or 100 mm. The strip must cover the entire bearing face to prevent any point contact between the sheet metal and the roughness of the slab.

Behaviour of decoupling materials under load
Type of resilient stripThickness at restTarget compression rateConsequence of excessive crushing
Cross-linked polyethylene foam3 to 5 mm25% to 35%Closing of cavities, loss of elasticity, structure-borne acoustic bridge
Dense EPDM elastomer4 to 6 mm15% to 25%Stiffening under pre-stress, direct transmission of vibrations
Heavy impregnated felt5 mm30% to 40%Premature creep, loss of thickness, failure of the perimeter joint
  1. Thorough cleaning of the substrateRemove concrete laitance, plaster debris and gravel with an industrial vacuum cleaner. A rough surface perforates the strip under the pressure of the track.
  2. Bonding the resilient stripApply the self-adhesive strip to the back of the metal profile before fitting, without stretching the foam, to preserve its native density.
  3. Drilling and suitable pluggingDrill the slab through the track. Use hammer-in screws or synthetic plugs with sealing washers, spaced at 60 cm to 80 cm maximum.
  4. Adjusting the mechanical tighteningScrew in while checking the reduction in thickness of the strip. Stop screwing as soon as the compression reaches one third of the initial thickness.

Finally, the fixing of the plasterboard to the framing must respect this physical break. The boards must never touch the bare floor or the adjacent walls: an air gap of 5 mm to 10 mm is left at the foot of the board by means of fitting spacers. This perimeter joint is then sealed with a flexible acrylic sealant or a resilient elastic joint before the finishing work. If the lining were to rest directly on the concrete slab, the decoupling of the bottom track would become totally ineffective, feeding the sound wave back into the load-bearing structure of the building.

Vertical edges and head connection: perimeter continuity and decoupling

Flanking transmission of sound is not limited to the bottom flange. Edge studs pressed against masonry or concrete walls, like the guide profiles fixed at the head under the bare floor, are direct transmission paths for structure-borne vibrations. The insulation requirements against airborne and impact noise set out in standard SIA 181 call for a continuous perimeter seal. If a vertical stud touches the masonry directly, or if the top profile is jammed against the slab without a flexible interlayer, acoustic energy propagates into the load-bearing structure by mechanical bridging, degrading the sound insulation values measured on the finished work.

The adhesive resilient strip applied under the back of the perimeter metal profiles fulfils two distinct functions: filling the micro-irregularities of the structural work to prevent air leaks and breaking the rigid steel-to-concrete connection. On off-form concrete or smoothed render, a 3 to 5 mm closed-cell polyethylene foam strip is generally enough to follow the substrate. With terracotta brick masonry with hollow joints or an uneven concrete wall, additional sealing with a bead of acrylic sealant at the edge is essential to neutralise any air passage under the perimeter profile.

  1. Preparing and cleaning the edge substrateDust the bearing area with a brush or industrial vacuum cleaner on the walls and under the bare slab. Remove laitance runs or mortar splashes with a flat chisel to obtain a continuous seating plane with no protruding hard point.
  2. Bonding the resilient strip to the side studsBond the polyethylene foam or elastomer strip over the full width of the rear flange of the vertical stud. Make sure the strip slightly overhangs on each side to prevent any contact of the boards with the adjacent wall.
  3. Fixing and mechanical anchoring without excessive perforationPlug the side profile into the masonry with hammer-in plugs or concrete screws suited to the substrate, at a spacing of 60 to 80 cm maximum. Adjust the screwing stroke to compress the foam by about one third of its initial thickness.
  4. Fitting the linings with a perimeter setbackScrew the plasterboard to the framing leaving a clear gap of 3 to 5 mm from the side wall and the ceiling. Never bring the lining into rigid abutment against the masonry or the bare slab.

Treating the bases and sealing: eliminating acoustic bridges at the edges

The interface between the bottom track and the floor is the zone most sensitive to impact noise and structure-borne transmission. Where a partition is erected on the bare slab before the floating screed is laid by the flooring contractor, the resilient strip under the bottom track provides the initial decoupling, while the screed will be poured against the linings on either side with perimeter edge strips interposed. If the partition is erected on a flowing screed that has already been laid, the tightening of the track must in no case crack the screed or compress the resilient strip beyond its elastic limit, which would nullify the acoustic attenuation sought.

Resilient sealing materials under profiles and installation characteristics
Resilient materialTypical thicknessTarget compression rateMain use on site
Cross-linked polyethylene foam (PE)3 to 5 mmAbout 30% of the thicknessRegular substrates at head, sides and bottom flange on smooth screed
Impregnated or bituminous felt strip4 to 6 mmAbout 25% of the thicknessWorks with high acoustic requirements and rough substrates
Dense elastomer (EPDM or rubber)5 to 10 mm15 to 20% of the thicknessHeavy double framing, dividing partitions between dwellings
Double bead of acrylic sealantDiameter 6 to 8 mmControlled crushing under trackIrregularities in structural work and fire-rated acoustic walls

When screwing on the linings, the fasteners must never pass through the bottom track to anchor into the concrete slab. Self-drilling screws remain confined to the metal framing and stop at least 10 mm above the finished floor. At the head of the partition under a concrete floor liable to deflect under load, fixing the boards to the top track must be avoided if a telescopic track or sliding connection has been specified in the execution details. Visual checking of the strip compression and the total absence of hard contact between board and structure guarantee that the sound insulation complies with the directives of standard SIA 181.

Acoustic non-conformities at the edges: diagnosis, remedial work and dispute management

On a plastering site, a sound insulation defect linked to the edges is often detected only after the finishes have been installed or during acoustic acceptance measurements in accordance with standard SIA 181. An insufficient raw insulation value between two adjoining rooms almost always betrays flanking transmission through the structure. The recurring causes in the field are well known: total crushing of the resilient strip by pneumatic plugging or excessive screwing creating a rigid bridge, the plain omission of the strip at the base of the profile on a bare slab, or a board screw passing through the track to anchor into the adjacent concrete.

  1. Locating the acoustic bridgeVisually check the partition bases before the screeds are poured, or inspect the perimeter of the framing with a site stethoscope to locate direct contact points with the slabs and solid walls.
  2. Curative decoupling of fastenersWhere a plug has perforated and crushed the foam beyond its permissible compression, unscrew the fastener, insert a flexible insulating washer under the head or redo an intermediate anchor with a controlled tightening torque.
  3. Cutting the rigid contact at the foot of the liningIf the plasterboard lining abuts the slab without the required clearance, cut a clean horizontal groove ten millimetres deep with an oscillating saw, then inject a durable flexible acrylic sealant.
  4. Raising or lining a defective edgeWhere the absence of a strip under the perimeter profile is proven over a long length without the possibility of dismantling the build-up, the only corrective measure is to add a decoupled counter-partition or a sealed hollow perimeter joint on the opposite side.

In the event of a challenge by site management, the dry-construction plasterer relies on the written duty to notify drawn up during the preparation of the substrates: a slab with unevenness exceeding the tolerances of standard SIA 414 prevents uniform compression of the strip without prior shimming. Recording these reservations protects the company before any contradictory acoustic measurement.

Frequently asked questions

How can you tell on site that a resilient strip is over-compressed under a track?

The check is carried out before the plasterboard is fixed. A cellular foam or elastomer strip must retain a residual thickness of between fifty and seventy per cent of its nominal thickness. If the material flows completely out from under the flange of the profile or is totally crushed under the plug washer, the tightening torque is excessive and transmits impact vibrations and airborne noise directly to the bare slab.

What should you do if the concrete slab has hollows that prevent the strip from sealing the base of the partition?

When the substrate exceeds the flatness tolerances, a simple resilient strip no longer fills the gaps. First report the defective condition of the substrate to site management. To guarantee the requirements of standard SIA 181, first apply a continuous bead of elastomer acoustic sealant under the seating of the profile or fit a resilient strip of increased thickness, thus avoiding the air leaks that degrade the sound reduction index.

Can the floor track be fixed directly with steel nails fired from a powder-actuated tool?

This practice is prohibited for partitions subject to the acoustic requirements of standard SIA 181. The violent impact of the shot pulverises the cellular structure of the resilient strip at the point of impact and presses the steel against the concrete with no residual elasticity. Drilling with hammer-in plugs or direct screw fixing for concrete is imperative, with the depth stop set so as to compress the strip without crushing it.

Is the resilient strip under the track enough to decouple the whole separating partition?

No, it only ensures the decoupling of the metal framing. To eliminate flanking transmission through the structure completely, the plasterboard lining must be fixed with a clearance of at least five millimetres from the bare floor, the ceiling and the side walls. This edge space is then closed with a flexible backing rod and a non-yellowing acoustic sealant before the skirting boards are fitted.

Texts and standards cited