Key takeaways
- Selective removal separates recyclable plasterboard from fibrous insulation destined for controlled inert landfills.
- Sorting on the construction site meets federal requirements and reduces the cost of waste disposal.
- Clean unscrewing of the boards avoids crushing and preserves the purity of the recyclable gypsum.
- Airtight bagging of mineral wool at source protects the fitters' respiratory tracts.
Selective removal of the boards to recover the gypsum and comply with the OLED
On an interior refurbishment construction site in French-speaking Switzerland, brutal demolition with a sledgehammer or pick is a major technical and economic mistake. Mixing plasterboard sheets, the metal framing and the insulation produces a skip of mixed commercial waste or mixed materials, charged at the highest rate by the sorting centres. By contrast, well-planned selective removal makes it possible to separate pure fractions that can be recovered directly. The Ordinance on the Avoidance and Disposal of Waste sets a strict framework for managing construction sites: according to art. 17 OLED, construction waste is sorted on the construction site by separating the recoverable fractions from the other waste streams. Plasterboard is among the materials covered by these material recovery obligations.
To preserve the purity of the material, dismantling follows the reverse order of installation. The team first locates and disconnects all fittings fixed to the surface, then removes the visible sealing strips and finishing profiles. Rather than breaking the board over the studs, the most productive method is to locate the screws with a flat neodymium magnet, then remove them with a screwdriver fitted with a magnetic bit. If the plaster conceals the screw heads too firmly, score around the fixings with a utility knife or cut the board along the framing with a special plasterboard hand saw. Whole boards or large pieces are then stacked flat on a pallet or loaded directly into containers reserved for clean plasterboard.
Removing mineral wool: dust protection and packaging
Unlike plasterboard, which benefits from a closed industrial recycling channel, mineral wool insulation (glass wool or rock wool) from deconstruction has no economically viable material recovery route in Switzerland. These fibrous materials are destined for controlled landfill. Accidentally mixing tufts of mineral wool into a plasterboard skip leads to the recycler flatly refusing the load or moving it into a heavily penalised tariff category. The two streams must be strictly kept apart from the moment the first face of the partition is opened.
Opening an existing dry-lining partition systematically releases large quantities of plaster dust and mineral microfibres that irritate the skin, eyes and respiratory system. Dismantling requires suitable collective and individual protective measures, in accordance with art. 33 OTConst, which requires that hazardous substances be extracted, filtered or diluted by artificial ventilation and that respiratory protective equipment be worn if the technical measures are insufficient. Using a mobile air extractor fitted with absolute filters, or light dampening by spraying, prevents fibres from becoming airborne again in the ambient air of the construction site.
- Mandatory personal protective equipment: FFP3 filtering respirator, close-fitting nitrile or polyurethane work gloves, sealed goggles and a disposable coverall with elasticated cuffs.
- Remove the insulation batts by hand, as complete panels, without tearing or jerking, directly from the metal stud.
- Bag immediately in transparent tear-resistant bags, compacted moderately without pulverising the material.
- Seal airtight with reinforced tying before any transfer out of the work area to the outdoor storage area.
| Criterion | Plasterboard (facings) | Mineral wool (insulation) | Metal framing (C-Stud/U-Track) |
|---|---|---|---|
| Status under the OLED | Mandatory recoverable waste | Non-recoverable combustible/inert waste | Recoverable scrap metal |
| Final destination | New gypsum manufacturing plant | Controlled landfill (type B/E) | Steelworks / metal recovery |
| Packaging on the construction site | Strapped pallet or dedicated plasterboard skip | Airtight sealed bags | Tied bundles or scrap-metal skip |
| Hygiene constraint | Respirable gypsum dust | Irritant mineral fibres / dust | Sharp edges of light sheet metal |
Once the insulation has been removed and bagged, the remaining metal framing comes apart quickly. The vertical studs are unclipped or unscrewed from the floor and ceiling tracks. The remaining screws are removed to avoid puncture risks during manual handling. The galvanised steel profiles form a third clean stream, bought back or taken back by metal recyclers without excessive charges. By organising the removal station around these three separate channels from the first square metre demolished, the site manager reduces the logistical load, ensures compliance with environmental standards and often halves the skip processing cost compared with undifferentiated disposal.
Methodical removal of the metal framing and sorting of secondary components
Once the plasterboard facings and the mineral wool batts have been removed and sent to their respective channels, the metal structure remains exposed. Dismantling this skeleton requires a rigorous method for two reasons: to avoid any damage to the surrounding substrates (floor screed, concrete slabs, adjacent suspended ceilings) and to guarantee a clean steel stream, free of any polluting material, that can be recovered directly by scrap dealers in French-speaking Switzerland.
- Dismantling the vertical studsRelease the vertical profiles that are clipped or crimped into the tracks. If self-drilling screws were used to fix the studs to the tracks or to door-frame reinforcements, always unscrew them with a clutch screwdriver. Avoid wrenching the studs out with a crowbar, which would twist the profiles and complicate stacking them efficiently for transport.
- Removing reinforcements and door-frame supportsUnscrew the heavier-gauge reinforced profiles (transom studs or reinforced profiles for doors). Immediately separate the angle brackets at floor and ceiling. Solid timber or solid steel pieces used as load reinforcement must be separated from the thin galvanised sheet.
- Removing the horizontal tracks and separating the resilient stripsUnscrew or cut the mechanical fixings connecting the guide tracks to the floor and ceiling. Peel off the acoustic sealing strip made of polyethylene foam or felt applied under the web of the track: this strip counts as residual combustible waste and must on no account contaminate the scrap-metal skip.
Organising OLED waste streams and the financial benefit of selective removal
The Ordinance on the Avoidance and Disposal of Waste (OLED) requires demolition materials and recoverable fractions to be sorted on the construction site once the volume of waste exceeds the regulatory thresholds. Throwing all the elements of a dry-lining partition (plasterboard sheets, glass or rock mineral wool, galvanised sheet profiles) into an ordinary skip for mixed construction waste is the worst option technically and financially. The heterogeneous density of this mixture is penalised, and sorting centres charge a prohibitive processing cost per tonne to deal with a complex sorting reject.
| Demolition fraction | Regulatory destination | Acceptance criteria | Financial impact |
|---|---|---|---|
| Clean plasterboard | Gypsum recycling plant | Foreign matter below 1 %, no mineral wool, timber or plastic | Very low intake cost, up to three times lower than mixed waste |
| Mineral wool (glass / rock) | Suitable controlled landfill (type B) | Airtight packaging mandatory in dedicated bags or closed big bags | Charged by volume or by tonne depending on the landfill, neutral treatment if not soiled |
| Galvanised steel framing | Scrap dealer / metal recovery | Clean sheet metal, free of polyethylene foam strips, composite screws and plaster | Buy-back credit or free drop-off depending on the steel price |
| Mixed construction waste (DMC) | Industrial sorting centre / thermal plant | Any unsorted material, mixture of gypsum, insulation and metals | Maximum rate per tonne with sorting penalties and processing surcharges |
For the team leader, the logistics on the construction site are organised as a forward station: three separate containers are set up from the dismantling phase. The boards are stacked on pallets and then strapped, or placed in a skip reserved for gypsum. The mineral wool is bagged airtight as work progresses in the work areas to prevent fibres from dispersing into the atmosphere, in accordance with occupational health protection rules. The tracks and studs are grouped into bundles tied with wire, or placed in a compact scrap-metal bin.
Handling unforeseen events and non-conformities during deconstruction
On a refurbishment construction site, dismantling a dry-lining partition holds hazards that threaten the profitability of the operation and the safety of the team. The appearance of a suspect material when the facing is opened is the first critical risk. If reinforcement tapes, old patching or sealants reveal doubtful fibres not listed in the pre-works survey, the team leader stops work in the area. In accordance with the directives of the Ordinance on Construction Work, the sector is cordoned off to prevent any harmful dust from becoming airborne again, and the site management is alerted so that formal analytical samples can be ordered.
Hidden moisture or mould in the framing also complicates disposal under the OLED. Plasterboard that has suffered prolonged water ingress loses its mechanical cohesion and develops fungal spores. These degraded materials cannot enter the industrial regrinding channels for manufacturing new boards. They must be isolated, bagged airtight to avoid contaminating the ambient air, and then sent to an incineration or controlled landfill channel, separate from the stream of clean recoverable gypsum.
- Contaminated plasterboard skip: tag the skip immediately and have the pieces of glass wool and metal profiles removed by hand, using suitable gloves, before the haulier arrives.
- Suspected unforeseen pollutant: stop the stripping, seal off access to the room, clean the area with an industrial vacuum cleaner with absolute filtration and record the incident in the site diary.
- Premature filling of containers: methodically compact whole plasterboard sheets on strapped pallets to relieve the main skip and keep access routes clear.
- Logistics extra cost: to readjust the waste item of the quote in case of unforeseen volume, consult the orders of magnitude at /soumissions/.
Frequently asked questions
Can moisture-resistant plasterboard be recycled in the same way as standard boards?
Yes, boards impregnated for damp rooms are accepted by plasterboard recycling plants in French-speaking Switzerland. The silicone incorporated in the gypsum core does not prevent industrial regrinding or reintegration into the manufacture of new plasterboard. However, sorting must absolutely exclude facings covered with ceramic tiles, cement tile adhesive or thick bituminous waterproofing membranes, which make the product unfit for material recovery.
Why can used mineral wool not be recycled with gypsum?
Glass or rock wool consists of man-made mineral fibres and insoluble organic binders. If these fibres get mixed into the ground gypsum, they impair the hydraulic setting of the calcined plaster and create major structural defects in the new boards. The OLED requires mineral insulation to be placed in a dedicated skip, sent to landfills for inert materials or stabilised residues, completely separate from recoverable waste.
What should be done with the bent metal profiles and screws removed from the partitions?
The galvanised sheet-steel framing is a secondary raw material of high market value. The studs and tracks must be cleared of any stuck-on plaster, cut into manageable lengths and then placed in the construction site scrap-metal skip. Screws picked up from the floor with a magnet go into the same metal bin. This systematic sorting reduces the weight of the paid skips and generates a credit from metal recyclers.
How can mineral wool dust be limited when dismantling a partition?
Mineral wool must be removed without violent tearing or jerking. The fitters fold the insulation panels over on themselves and immediately slide them into thick transparent polyethylene bags, sealed airtight in the work area. Forced mechanical ventilation and the use of professional vacuum cleaners fitted with fine-dust filters protect the staff's respiratory tracts, in addition to the mandatory wearing of the FFP3 personal respiratory mask.
Texts and standards cited
- OLEDRequirements on sorting construction waste, separating recoverable materials and limiting mixing
- OTConstGeneral safety rules during dismantling, protective measures against harmful dust and management of pollutants