🧱 CFC 271Suspended ceilings: suspension, slab deflection and access hatchesChapter 7 of 10 in the section

Under-rafter ceiling: fixing to the roof structure, ventilation of the air gap and vapour barrier

This chapter details the installation of a plasterboard suspended ceiling under the rafters without impairing airtightness. You will learn how to set out a decoupled metal framework or one suspended by dedicated hangers, how to ensure absolute continuity of the vapour barrier membrane in accordance with SIA 180, and how to preserve the ventilation space under the roof.

Key takeaways

  • Any unsealed penetration of the vapour barrier creates a flow of warm air and destructive condensation.
  • The framework is fixed using suitable hangers that preserve the continuity of the vapour barrier.
  • SIA 180 requires strict airtightness, verified by bonded perimeter junctions.
  • The plasterer checks that a continuous ventilated air gap is present before the under-rafter area is closed in.

The physics of the under-rafter space: why penetrating the vapour barrier ruins the insulation

Under a pitched roof, warm air laden with interior moisture rises naturally towards the ridge by thermal draught. If the vapour barrier is perforated when metal hangers are plugged or screwed directly, water vapour penetrates massively into the thickness of the insulation by convection. On contact with the cold rafters or the sarking, this moisture reaches its dew point and condenses into liquid water. This phenomenon irreparably degrades the thermal performance of mineral or plant-based wools and, in the long run, causes the timber roof structure to rot.

The building envelope must have sufficient airtightness to prevent damage caused by moisture from convective condensation in the thermal insulation layers.

Norme SIA 180

In plastering and dry construction under CFC 271, the tradesperson often works after the carpenter has installed the insulation between the rafters. If the vapour-control or vapour barrier membrane is already in place, screwing the hangers of a suspended ceiling through it without dedicated sealing is a major construction defect. Even a 3.5 mm self-drilling screw creates a local leak capable of letting several tens of grams of water per square metre pass through each day during the heating season.

Furthermore, thermal insulation under the rafters must never come into contact with the sarking if the latter requires air circulation. Preserving a ventilated air gap of at least 20 to 40 mm under the battens or boarding is a matter of roof design, but the dry-construction plasterer is obliged to check that the lining does not push the insulation upwards, which would block the air inlets at the eaves or the outlets at the ridge. Under art. 365 para. 3 CO, if the contractor notices a circumstance that jeopardises proper execution of the work, they must immediately inform the client.

Compliant fixing systems: installation techniques without breaking the airtightness

To suspend a sloping ceiling without impairing the continuity of the airtight membrane, two main methods are accepted on the Swiss dry-construction market. The first consists of using composite or metal hangers with thermal break fitted with specific sealing end pieces. The second, particularly robust, relies on completely decoupling the framework by means of timber counter-battens or intermediate hangers sealed under the vapour barrier.

  1. Setting out rods or hangers on the roof structureFix the mechanical anchor brackets directly to the sides or underside of the rafters. If breakable hangers or threaded rods later pass through the membrane, their alignment must be accurate to the millimetre using a string line.
  2. Installing the insulation and the continuous membraneLay the vapour barrier with a minimum overlap of 100 mm between sheets. Thread the membrane onto the hangers provided for this purpose with minimal play to avoid any uncontrolled tearing.
  3. Local sealing of penetrationsApply an elastic adhesive sealing collar or a preformed EPDM washer to each hanger rod, pressed firmly against the clean, dust-free vapour barrier to restore airtightness.
  4. Clipping on the metal ceiling sectionsFit the CD 60/27 metal furrings onto the hanger heads protruding from the membrane, creating an interior service void without touching the airtight plane.
Comparison of under-rafter fixing solutions with regard to airtightness
Suspension systemAirtightness maintained (SIA 180)Integrated service voidInstallation complexity
Eyelet hanger threaded through with EPDM adhesive eyeletExcellent if carefully pressed onto a dry substrateYes, 30 to 60 mm void depending on the rodMedium, precise workmanship required at every penetration
Timber counter-battens screwed to hangers under the membraneVery good, membrane protected behind the battensYes, direct routing of electrical conduitsHigh, requires a double timber-and-metal structure
Bracket screwed directly through the membraneNon-compliant, recurring air leaks and condensationNo, board in direct contact with the insulationLow, method prohibited on a well-run construction site

To make work at height safe when erecting frameworks under the rafters, workstations must be arranged in accordance with the safety rules. Art. 17 OTConst requires measures to be taken so that workers are not endangered by falling objects or materials at workstations and walkways. The use of mobile scaffolding or lightweight height-adjustable platforms must replace improvised work on simple stepladders on an inclined surface.

Continuity of the airtight plane and compliance with SIA 180

SIA 180 requires strict airtightness of the thermal envelope in order to prevent vapour transfer by convection towards the roof structure and the insulation. Under the rafters, the main risk lies in the uncontrolled penetration of the vapour barrier by the ceiling fixings. When self-drilling screws or standard metal hangers perforate the film without an elastomer sealing device, the driving pressure difference pushes warm, humid interior air directly into the insulation. The water condenses there as soon as it reaches the dew point, ruining the thermal resistance of the mineral wool and causing rafters to rot.

The dry-construction fitter guarantees the integrity of the membrane by creating a service void below the vapour barrier or by using sealed suspension accessories covered by a technical approval. Two approaches make it possible to comply with SIA 180: fitting composite brackets with integrated sealing washers fixed to the sides of the rafters before the membrane is laid, or mechanically fixing clip-on hangers that trap the sheet without shearing it. In all cases, placing a butyl adhesive strip or a compressible sealing tape between the timber and the hanger support remains mandatory for any through-fixing.

Coordination with the carpenter and the plumber/roofing metalworker is decisive for maintaining the ventilated air gap located under the sarking. When installing semi-rigid insulation under the rafters, the plasterboard fitter must never push the insulation batt upwards so as to block the ventilation space under the battens. Even though ventilation under the tiles depends on the roofing trade, excessive compression of the insulation from the inside against the sarking membrane neutralises the outside air flow, trapping summer heat and promoting moisture build-up on the underside of the roof covering.

Erecting the metal framework and perimeter junctions

Mechanically erecting the framework under a timber roof structure calls for articulated fixings or acoustic hangers suited to the slope. The natural deformation of the roof timber due to moisture variations and climatic loads (snow and wind) requires the plasterboard lining to be decoupled from the load-bearing structure. CD 60 supporting rails and sections or equivalent studs are fixed at strict centres, limited to 400 mm for boards laid perpendicular to the rafters or 500 mm for double crossed frameworks.

Anchoring methods under a timber roof structure without damaging the vapour barrier
Fixing systemInstallation of the vapour barrierMain advantageCritical point on site
Intermediate threaded-rod hanger with sealing washerMembrane threaded onto the rod and locked by a sealant ringMillimetre adjustment of flatness under uneven raftersPrecise tightening of the washer without crushing or tearing the sheet
Timber counter-battens screwed onto a nailing sealing stripVapour barrier continuously clamped between rafter and counter-battenImmediate creation of a service void for cablesIncreased overall thickness and extra timber weight
Composite brackets with clip-on end piece, no perforationMembrane laid over the roof structure, brackets clipped on by pressureNo direct piercing of the membrane bodyRequires perfectly aligned rafters without warping
  1. Treatment of junctions at wall plates and gablesFold the vapour barrier sheet back with a deformation loop of at least 20 mm to absorb the deflection of the roof structure. Apply a continuous bead of solvent-free polyurethane or acrylic elastomer adhesive, 8 mm in diameter, onto the previously dust-free masonry, then press the membrane on without fully crushing the bead.
  2. Aligning and clipping the metal sectionsSet the flatness of the ceiling sections using a string line or rotary laser. Fit the metal furrings into the hanger heads, allowing a perimeter expansion gap of 5 mm against gable walls and main beam downstands.
  3. Fixing and screwing the under-rafter liningFit the lining starting from the bottom of the slope towards the ridge. Fix with plasterboard screws spaced at a maximum of 250 mm, making sure that the screw length never reaches the membrane located behind the service void.
  4. Perimeter decouplingPlace a foam decoupling strip or an adhesive slip tape at the junction between the rafters and the partitions or masonry, before the joints are treated with filler according to the required level of finish.

Handling perforations, interface disputes and remedial protocols

On a pitched-roof construction site, discovering a vapour barrier membrane that is perforated or pinched by a framework fixing is a critical defect that directly affects the durability of the roof structure. When the dry-construction plasterer finds a tear, an unsealed perforation around a fixing bracket or crushed insulation blocking the sarking air gap, the boarding work must be suspended. Under the general rules of the contract for work and services in the Code of Obligations (CO), the contractor immediately reports the defect in writing to the site management before the work is closed in. Closing up a lining over a damaged airtight barrier exposes the insulation to moistening by convection during the heating season, leading to mould and rapid rotting of the rafter timbers.

  • Stop fixing plasterboard as soon as a tear or a lifting adhesive strip appears on the rafters.
  • Apply a patch cut from the same membrane, overlapping the tear by at least fifty millimetres all round, bonded with an adhesive certified as meeting the airtightness requirements.
  • Treat the passages of rigid hangers with preformed sleeves or a durably flexible solvent-free elastomer sealant.
  • Record the intervention with photographs agreed by all parties, included in the site diary, before any finishing lining is installed.

The repair must always guarantee the perfect continuity required by SIA 180. If the damage results from work by another party, in particular when technical conduits not provided for in the installation void have been run through, the repair must be covered by a daywork order signed by the client's representative before the lining resumes. Keeping the ventilated air gap above the thermal insulation must also be rigorously checked: compressed insulation pushed towards the roofing battens blocks the rising air flow and causes condensation under the sarking.

Frequently asked questions

How do you repair a vapour barrier membrane torn while fitting the metal hangers?

The repair requires applying a patch of membrane of the same type as the vapour barrier in place. This patch must cover the slit by at least fifty millimetres on each side. It is sealed with an acrylic adhesive tape specific to interior airtightness. For complex through-penetrations, a solvent-free sealant is applied in a continuous bead, pressed without excessive smoothing, in order to guarantee lasting airtightness in accordance with SIA 180.

Why must a service void be provided between the vapour barrier and the plasterboard?

The service void created by the metal framework or the counter-battening makes it possible to incorporate electrical conduits, flush-mounting boxes and spotlights without ever perforating the vapour barrier membrane. This void protects the continuous airtight plane required by SIA 180 from later penetrations when the plasterboard is fixed. It thus prevents any convective infiltration of warm, humid air towards the roof structure and the thermal insulation under the rafters.

What should be done if the mineral wool blocks the ventilated air gap under the roof?

If the thermal insulation is pushed too deep between the rafters, it blocks the air gap needed to evacuate moisture under the roof covering. The dry-construction plasterer must suspend their work and send a written notice to the site management in accordance with the provisions of the Code of Obligations (CO). The carpenter or roofer must install stop battens or a rigid sarking to restore the required air circulation.

Who is responsible for a vapour barrier penetration made by another trade?

Each company is responsible for the integrity of the work it damages. When an electrician or plumber perforates the membrane laid by the plasterer to run cables, they must ensure airtightness with certified sleeves or formally ask the plasterer to carry out the repair. A plasterer who notices the perforation before fitting their suspended ceiling must raise written reservations so as not to incur liability for subsequent airtightness defects.

Texts and standards cited

  • SIA 180Thermal insulation, moisture protection and indoor climate in buildings