🧱 CFC 271Fire protection and acoustics of dry constructionChapter 2 of 10 in the section

Closing the head: fire-resistant junction with the slab, packing and fire-resistant sealant

By the end of this chapter, you will be able to size and install a movable fire-resistant partition head beneath a concrete slab, incorporate the class RF1 mineral wool packing and apply the intumescent sealant. You will also master the mandatory visual inspection procedure before the facings and cover strips are fitted.

Key takeaways

  • The head junction absorbs structural deflections while ensuring tightness against hot gases.
  • A two-centimetre air gap destroys the overall fire performance of the wall.
  • The packing is carried out exclusively with compressed stone wool classified VKF RF1.
  • The visual inspection of continuity must be validated before the plasterboard is fixed.

Designing the upper connection to allow for the foreseeable deformation of the structural work

In a reinforced concrete building, floors deflect under service loads and delayed shrinkage. The connection between the top of a lightweight partition and the underside of the slab can therefore never be rigid. If the top track is restrained directly against the concrete without a calculated gap, the load transfer crushes the vertical sections, buckles the studs and cracks the plasterboard facings. Conversely, leaving a free gap without fire-resistant treatment turns the top of the wall into a thermal chimney: in the event of a fire, two centimetres left unsealed are enough to spread toxic gases and hot smoke to the neighbouring compartment within minutes.

Fire-resistant sliding head
Decoupled connection device consisting of a U-section with long flanges fixed beneath the slab, in which the vertical studs slide freely with an expansion gap, the void being sealed with fire-resistant materials.

The sliding head system is based on a track mechanically fixed to the ceiling at a fixing spacing suited to the type of concrete. The studs of the metal framing are cut shorter than the clear height beneath the slab, leaving a gap corresponding to the maximum theoretical deflection provided by the civil engineering office. The screws fixing the boards must under no circumstances pass through the flange of the top section: they stop on the vertical stud, below the sliding line. Any screw connection joining the board to the head track blocks the sliding mechanism and nullifies the mechanical decoupling function.

The fire resistance requirement imposed by the fire protection regulations of the Association of Cantonal Fire Insurers (VKF/AEAI) requires the assembly to maintain its fire-resistant function (EI 30, EI 60 or EI 90) for the entire regulatory duration, including when the slab has reached its maximum deformation under thermal action. The rules of the trade oblige the contractor to carry out an installation strictly in accordance with the test reports of the dry construction system manufacturers. Art. 364 CO requires the contractor to carry out the work with care, which implies strict compliance with the fire approvals issued for the complete system.

Installing the RF1 materials and recording the acceptance of the sealing

The expansion gap is sealed using building materials of reaction-to-fire group RF1, that is, without contribution to fire. Standard glass wool is prohibited in this specific detail because its melting temperature is too low, around 600 °C, which is far exceeded in the early phases of the standard fire curve. Only rock wool with a melting point above 1000 °C and a minimum density suited to the board supplier's test report is used, generally between 40 and 80 kg/m³.

  1. Cleaning the concreteRemove dust from the underside of the slab with a hard brush or an industrial vacuum cleaner to remove residues of formwork laitance and release oil that would prevent the sealants from bonding.
  2. Setting out the packingCut the RF1 rock wool into strips with a minimum oversize of 10 to 15% relative to the thickness of the cavity, so as to obtain lasting mechanical compression once inserted.
  3. Inserting the mineral woolCompress the wool between the top of the boards and the concrete using a flat spatula, without packing it so tightly that it blocks the travel of the sliding partition head.
  4. Applying the fire-resistant sealantApply a regular bead of intumescent acrylic sealant or elastomeric fire-resistant coating along the entire length of the gap, observing the joint depth recommended by the VKF/AEAI certificate.
  5. Fitting the protective cover stripsFix the added facing strips or finishing angles only to the support designated by the approved technical detail.

Deliberate or negligent omission of the head packing endangers public safety by nullifying the compartmentation of the building. In the event of personal injury linked to the spread of smoke through a poorly closed wall head, the criminal liability of the site manager or of the installer may be pursued under art. 229 CP if the recognised rules of building practice have been breached.

Permissible components for the head junction of a fire-resistant partition
Detail elementVKF/AEAI RF1-compliant materialActual fire behaviourCritical installation point
Flexible sealing materialCertified intumescent sealantExpands under heat and seals the gapObserve the minimum application thickness
Bulk packingRock wool (density ≥ 40 kg/m³)Maintains thermal insulation without meltingCompress without blocking the travel of the track
Decoupling stripRF1 mineral felt stripCloses the section-to-concrete interfacePosition before plugging the U-track
Thickness build-up claddingReinforced plasterboard stripProtects the sliding track from direct flameFix to one element only to allow sliding

Installing the sliding profile and RF1 rock wool packing

A fire-resistant separating partition tolerates no discontinuity at the head. Two centimetres left empty between the top track and the underside of the concrete are enough to turn the junction into a chimney within the first minutes of a fire: toxic smoke and pressurised hot gases pass through the faulty joint, bypass the facing and ignite the adjacent compartment well before the mechanical resistance of the structure is affected. To maintain the gas tightness and thermal insulation criteria required by the VKF/AEAI fire protection regulations, the head connection must absorb the differential movements of the structural work while forming an impassable barrier.

Managing the slab deflection requires a sliding head. The dry-construction installer fixes to the ceiling a U-section with long flanges, sized to allow vertical movement without constraining the vertical framing. The metal C-studs are cut shorter with a clear gap corresponding to the foreseeable deformation provided by the civil engineer. They slide freely inside the top track without any fixing by self-drilling screw or crimping. The void thus created to absorb the sagging of the slab must be completely filled with a mineral blanket able to withstand extreme temperatures without melting or shrinking.

  1. Fitting the sealing strip under the profileLay a non-combustible mineral resilient strip or a continuous fire-resistant sealant under the head section before its mechanical anchoring into the reinforced concrete slab.
  2. Trimming and guiding the studsCut the metal studs with a net clearance of 15 to 25 mm from the bottom of the top profile to guarantee freedom of vertical sliding.
  3. Sealing by mechanical packingInsert strips of compact stone wool classified RF1, cut with a minimum oversize of 10 mm to ensure continuous and permanent lateral compression.
  4. Fitting the facings with clearancesStop the plasterboard or reinforced boards below the ceiling at a distance equivalent to the theoretical deflection, avoiding any screw in the head track.
Components of the sliding head junction of a fire-resistant partition
Junction elementMaterial and classificationFunctional roleCompliance criterion
U-shaped head sectionRF1 galvanised steel sheetGuiding the framing and holding the blanketUpper flanges of at least 40 to 60 mm depending on the deflection
Intermediate packingRaw RF1 stone wool (high density)Thermal barrier and flame retardantCompressed fully without settling under gases
Base resilient stripNon-combustible RF1 mineral or ceramic fibreAcoustic break and surface tightnessContinuity of support under the sheet without interruption
Upper reinforcement stripRF1 special fire-rated plasterboardLateral protection of the telescopic trackOverlap in accordance with the approval certificate

Tightness by fire-resistant sealant and inspection procedure before closing

The mineral wool packing provides thermal insulation but is not sufficient to guarantee complete tightness against cold pyrolysis gases. A complementary sealing with a flexible elastomeric joint or fire-resistant acrylic sealant must edge the upper perimeter of the partition. Applied between the upper edge of the facings and the underside of the slab, this sealant must have sufficient elasticity to absorb the building's deformation cycles while reacting by intumescence under the direct action of heat. The bead swells, blocks the gap and permanently stops the spread of smoke and flames.

Once the second facing is screwed on, the head junction becomes completely invisible. This structural concealment makes any defect undetectable by the site management or by the fire protection expert without costly destructive testing. The dry-construction plasterer foreman must introduce a systematic visual inspection, recorded jointly on the construction site before the second face of the partition is completed. This record guarantees that the entire length has received its non-combustible sealing in accordance with the manufacturers' test reports.

  • Checking the continuity of the RF1 stone wool packing over the full thickness of the internal void of the framing.
  • Checking the total absence of fixed connections by screws or rivets between the vertical studs and the top U-section.
  • Measuring the residual gap between the top of the facing boards and the raw concrete to verify compliance with the expansion travel.
  • Recording the application depth and adhesion of the fire-resistant sealing sealant on a dust-free concrete substrate.
  • Systematic photographs of the open partition heads for filing in the as-built records.

This formal validation step is a precondition for issuing the fire compliance certificate that the contractor hands over at the acceptance of the work. In dry construction, the fire performance of a separating element EI 30 to EI 90 depends not only on the composition of the boards, but on the rigour applied to this top joint. Methodical rigour during self-inspection protects the company against later disputes and guarantees the real safety of the building's occupants.

Handling non-conformities at the partition head and reworking the sealing

On the construction site, the absence of sealing or a defective packing at the head of a fire-resistant partition is a major non-conformity that voids the entire fire resistance rating aimed for. Two centimetres left unpacked or an unsuitable sealant are enough to spread hot smoke and toxic gases to adjoining compartments within minutes. When the defect is found late, in particular after the facing has been closed or during an inspection by the site management, complete rework of the detail is required before any acceptance of the work in accordance with standard SIA 118.

  1. Methodical removal and exposing of the headCleanly saw the plasterboard facing over a strip of 150 to 200 mm below the underside of the concrete slab. Remove the offcuts and vacuum the plaster dust to free direct access to the sliding U-profile and to the deformation space provided for the deflection of the structural work.
  2. Clearing out and redoing the RF1 packingRemove combustible or non-certified materials. Insert fully strips of rock mineral wool classified VKF/AEAI RF1, with a minimum density of 40 kg/m³. Compress the blanket by at least 25 to 30% in the void to ensure mechanical tightness in the event of slab movement.
  3. Applying the fire-resistant sealantFit a suitable backing cord if required by the manufacturer's test report, then extrude a VKF/AEAI-approved intumescent or elastomeric fire-resistant sealant. Smooth the joint with a knife, ensuring a minimum thickness in accordance with the compliance certificate, without discontinuity or air bubbles.
  4. Reinstating the facing and recordRefit a strip of fire-rated board fixed to the framing without rigidly connecting the sliding head to the slab. Carry out the visual inspection before final closing, record the rework with time-stamped photographs and log the intervention on the self-inspection sheet sent to the fire quality assurance manager.

Frequently asked questions

Can RF1 rock wool be replaced by fire-resistant polyurethane foam from a spray can?

No. Polyurethane foams, even when labelled fire-resistant, are only permitted if they appear specifically in the VKF/AEAI approval certificate of the tested partition system. With a sliding head, the deformation of the slab requires a material that remains flexible and stable at high temperature. Compressed RF1 rock mineral wool, closed with a compliant intumescent sealant, remains the proven standard solution on Swiss construction sites.

How can the sealing be demonstrated if suspended ceilings conceal the partition head?

The visual inspection must take place before the false ceilings are closed. The dry-construction plasterer draws up a self-inspection protocol documented by systematic photographs of each bay of partition head, showing the compressed RF1 wool and the bead of fire-resistant sealant. This as-built file is handed to the site management and to the fire protection expert to release the next stage.

What void tolerance is permitted at the head if a metal cover strip is applied?

No through-void tolerance is permitted, even with a finishing sheet. The cover strip provides only mechanical or aesthetic protection; it in no way guarantees tightness against cold and hot smoke. The dense VKF/AEAI RF1 rock wool packing and the elastic fire-resistant joint must be carried out continuously over the full width of the framing before the cover strip is fitted.

What should be done if the actual slab deflection exceeds the allowance provided in the sliding profile?

This non-conformity must be reported immediately in writing to the site management within the meaning of the Code of Obligations. Excessive compression of the section risks bursting the screw heads and cracking the plasterboard. The technical rework requires the agreement of the civil engineer and the fire specialist to adapt the sliding profile or widen the fire-resistant joint according to a tested detail.

Texts and standards cited

  • Directives de protection incendie AEAISwiss fire protection regulations on the use of RF1 building materials and fire-resistant compartmentation
  • Norme SIA 118General conditions for the execution of construction work, inspection of the works and handling of notices of defects
  • Code des obligationsRules governing the contract for work, the contractor's duties and liability for defects in the work