Key takeaways
- The maximum height of a partition depends jointly on the metal profile, the stud spacing and the board facing.
- Reducing the stud spacing from 600 mm to 400 mm significantly increases the overall mechanical strength.
- Double boarding increases the rigidity of the work and allows a greater ceiling height.
- SIA 242 sets the deflection tolerances to ensure the durability of interior finishes.
Determining the limiting height according to profile section and board facings
On a drywall construction site, the stability of a non-loadbearing partition depends on the intrinsic moment of inertia of its galvanised steel metal profiles with a gauge of 0.6 mm and on the mechanical connection established with the screwed boards. SIA 242 governs the rules of good practice for lightweight partitions and requires the limiting height of use to be verified before any material is ordered. Ignoring the relationship between the stud section and the number of board layers leads to excessive deformation under horizontal pressure, cracking at the joints and defects at the junctions with transverse partitions.
Non-loadbearing partitions and their substructures must be sized so as to limit deflection under the permissible mechanical actions, in order to preserve the integrity of the finishes and adjoining works.
norme SIA 242
| Profile designation | Single boarding (1 x 12.5 mm) | Double boarding (2 x 12.5 mm) |
|---|---|---|
| CW 50 | 2.60 m | 3.00 m |
| CW 75 | 3.50 m | 4.20 m |
| CW 100 | 4.50 m | 5.25 m |
The thickness of standard metal profiles supplied in Switzerland is generally 0.6 mm nominal. Where a partition receives double boarding, each board is offset by at least one stud spacing relative to the underlying layer. This system acts as a composite box girder: screwing the second board into the first and into the framing shifts the neutral axis and prevents local buckling of the flanges of the CW stud. This gains between 40 and 75 centimetres of permissible height without having to increase the profile width.
Adjusting the stud spacing according to actual height and loads
The default setting-out pitch in French-speaking Switzerland is 600 mm, corresponding to half the width of 1200 mm plasterboards or a third of that of wide boards. However, where the ceiling height exceeds the maximum values in the standard table for a given profile, reducing the spacing to 400 mm or even 300 mm is a technical alternative validated by the application sheets of drywall system manufacturers. This closer spacing keeps the partition thickness small while meeting the deflection requirements.
- Measuring the gross slab-to-slab heightTake the height levels with a laser along the entire line of the future partition. Use the maximum value for the structural sizing of the metal profiles.
- Defining the nature of the applied finishesCheck whether the walls are to receive a heavy finish such as wall tiles or suspended loads. In wet rooms with ceramic tiling, the spacing is automatically reduced to 400 mm or the boarding is doubled.
- Selecting the profile-spacing combinationChoose the appropriate CW stud. If the limiting height is reached at 600 mm spacing, close the studs up to 400 mm or place two CW profiles back to back, joined by riveting or self-drilling screws.
- Adjusting the order for boards and accessoriesOrder the additional quantity of studs required by the 400 mm pitch, together with screws suited to the final layer: 25 mm plasterboard screws for the first layer, 35 mm or 45 mm for the second layer.
Two CW studs assembled back to back and joined at regular intervals of about 500 mm by sheet-metal screws or mechanical crimping form a double-T profile whose moment of inertia is more than doubled. This on-site solution often avoids ordering specific reinforced profiles in 2.0 mm thick sheet, while ensuring the connection of the boards without changing the finished thickness of the partition.
Comparative table of permissible heights: combining profiles, spacings and board facings
The sizing of a non-loadbearing distribution or separating partition cannot be improvised on the construction site at the moment of unloading. In drywall construction, mechanical stability and impact resistance depend directly on the technical triad made up of the thickness of the metal profile, the distance between two consecutive studs and the chosen boarding method. SIA 242 strictly governs plastering and drywall works by setting deflection criteria under horizontal loading. For standard use in private or administrative premises, the maximum permissible deflection must not exceed one two-hundredth of the ceiling height. If the actual height of the room exceeds the capacity of the selected stud, the partition will be excessively flexible, quickly causing cracking at the ceiling junctions and board joints. Before placing the order for profiles and boards, the foreman must cross-check the gross height under the slab against the operating requirements in order to fix the required framing.
| Metal profile | Boarding per side | Spacing 625 mm | Spacing 312.5 mm | Recommended use |
|---|---|---|---|---|
| CW 50 | Single boarding (1 x 12.5 mm) | 2.60 m | 3.00 m | Interior partitions in dwellings, secondary rooms |
| CW 50 | Double boarding (2 x 12.5 mm) | 3.15 m | 3.75 m | Offices, standard separations, circulation areas |
| CW 75 | Single boarding (1 x 12.5 mm) | 3.50 m | 4.00 m | High partitions without acoustic requirements |
| CW 75 | Double boarding (2 x 12.5 mm) | 4.50 m | 5.25 m | Commercial premises, technical corridors, reinforced separating walls |
| CW 100 | Single boarding (1 x 12.5 mm) | 4.25 m | 4.90 m | Non-accessible service shafts, freestanding linings |
| CW 100 | Double boarding (2 x 12.5 mm) | 5.50 m | 6.50 m | Entrance halls, atriums, light industrial premises |
Decision criteria before procurement and solutions for large heights
The choice of framing frequently runs up against the geometric constraints of the structural work and the floor space imposed by the architect's plans. Where the height under the slab exceeds the permissible values of a standard profile, the drywall contractor has several alternatives before fixing the order. The most economical solution in terms of space is to pair the studs back to back in I-profiles or H-shaped boxed sections. Two CW studs joined by self-drilling screws or rivets every 500 millimetres increase the moment of inertia of the framing by approximately 30 % compared with a single stud. This configuration avoids widening the total thickness of the partition at floor level, while still allowing standard UW tracks to be used.
The effect of the number of board layers on overall inertia is also decisive. Fitting two plasterboards on each side does not serve only for sound insulation or fire resistance. Double boarding stiffens the structure continuously: the boards of the second layer, screwed with the joints offset by at least 250 millimetres from the first, create a shear-panel effect that restrains lateral buckling of the studs. With an identical stud section, going from one to two board layers increases the permissible height by 20 to 35 % without changing the spacing.
- Check the net height under the slab along the entire line: record the high and low points in order to order adjusted stud lengths, deducting 10 to 15 mm for expansion and installation.
- Identify the areas subject to suspended loads: provide reinforced profiles of 2 mm thickness or specific metal trimmers for wall-hung sanitary fittings and high cabinets.
- Check the spacing according to the nature of the facings: observe 625 mm for standard boards fixed vertically, but close the spacing up to 312.5 or 400 mm without fail for tiled rooms.
- Cross-check delivery requirements against the site access: anticipate the passage of long studs through stairwells or goods lifts before approving the factory packing lists.
Managing height discrepancies and rectifying undersized framing
On the construction site, a misjudgement between the gross height under the slab and the finished height under the suspended ceiling frequently leads to undersizing of the metal framing. Where a single CW 50 or CW 75 stud is installed at 600 mm spacing while the actual storey height exceeds the permissible limiting height defined by SIA 242 and the manufacturers' technical data sheets, the partition loses its transverse rigidity. This defect leads to excessive deflection under impact or air pressure loading, causing microcracks to appear at the board joints even before the painters start work.
- Finding and stopping the screwingAs soon as the limiting height is found to be exceeded on the bare framing or on framing boarded on one side only, immediately stop fixing the boards to avoid scrapping paperfaced plasterboards.
- Reinforcement by pairing or reduced spacingIf the framing is still open, insert intermediate studs to reduce the spacing from 600 mm to 300 mm, thereby doubling the buckling resistance. If the profiles are already anchored at the foot and head, pair the studs back to back with self-drilling screws spaced at 500 mm to create an I-section.
- Changing the boardingOn a structure where replacing the CW 50 profile with CW 75 is ruled out by the reserved finished thickness of the partition, switch from single boarding to double boarding screwed in a staggered pattern. This solution increases the overall rigidity and raises the permissible height of the wall.
- Formal validation with site managementRecord the structural modification in a site bulletin sent to site management, certifying the conformity of the modified build-up with the acoustic and mechanical requirements of SIA 242.
Frequently asked questions
Can a metal stud that is too short be extended by splicing on the construction site?
Yes, splicing of vertical profiles is permitted provided the manufacturers' requirements are observed. Splicing is done either by telescopic nesting with an overlap of at least 50 cm fixed with eight self-drilling screws, or with a section of outer track. On the same partition, the splice heights must always be staggered from one stud to the next so as not to create a continuous line of weakness in the framing.
What solution should be adopted for a separating partition exceeding 4 metres under the slab?
Beyond 4 metres, single CW 50 and CW 75 studs are outside the permissible limits. At least CW 100 profiles at a closer spacing of 400 mm or 300 mm must be specified, or studs must be paired back to back. Double boarding on each face is mandatory to stiffen the whole, unless a specific structural analysis provides for heavy-gauge reinforced framing profiles in galvanised steel.
Why does the installation of heavy tiling require the stud spacing to be reduced?
Wall tiles and the associated adhesives apply an eccentric permanent load and a surface rigidity sensitive to micro-deformations. To limit deflection under load and avoid tiles detaching or joints cracking, the stud spacing must be reduced to a maximum of 400 mm, with double boarding made of specific moisture-resistant boards, thus ensuring the inertia required by SIA 242.
How should the metal framing be treated at a junction under a slab that deflects?
Under a concrete floor liable to deflect under service loads, the vertical stud must not be rigidly fixed to the top profile. A sliding connection must be made using a deep-flanged ceiling track, cutting the studs with a clearance of 15 to 20 mm at the head. The board screws must never pass through the flange of the top profile, so as to preserve the sliding movement.
Texts and standards cited
- SIA 242Plastering, rendering, drywall construction: execution tolerances, permissible heights of lightweight walls and rigidity criteria of metal framing
