🧱 CFC 271Interior plasters: substrates, coats and smoothingChapter 3 of 10 in the section

Plastering with gypsum: thickness per coat, setting time and drying of the room

Successfully applying a gypsum plaster requires strict compliance with the maximum thickness per coat and rigorous thermal management of the construction site. This chapter details the application rules according to SIA 242, the permissible thicknesses per coat to eliminate crazing, and the ventilation protocols needed to ensure even drying without impairing the crystalline strength of the material.

Key takeaways

  • The nominal thickness of one coat of interior gypsum plaster is between eight and a maximum of fifteen millimetres.
  • Beyond twenty millimetres of build-up, application must be split into two coats with mechanical scoring in between.
  • Direct ventilation is prohibited during the initial twenty-four-hour setting period to prevent the gypsum from burning.
  • Removing the excess water requires regular cross-ventilation and construction site heating without direct combustion.

Controlling the thickness per coat to prevent shrinkage and cracking

On the construction site, the temptation to build up a plaster in a single coat to make up for a significant out-of-plumb or to hide technical ducts inevitably leads to defects. A sprayed or hand-applied gypsum plaster does not harden by simple evaporation: it first develops a rapid hydraulic set through the formation of a crystalline network, before expelling the excess mixing water by capillarity. As soon as the thickness exceeds the cohesion capacity of the paste, the inner mass remains soft while the outer face begins to shrink. This tension differential causes internal shear, which shows up as surface crazing, deep cracks and loss of adhesion.

Setting and drying of gypsum plaster
Setting refers to the exothermic chemical reaction in which the hemihydrate combines with water to form rigid gypsum crystals. Drying is the subsequent physical evaporation of the excess free water, which is essential to give the plaster its final mechanical hardness.

SIA 242 governs the application rules for interior gypsum plasters. For a standard single-coat plaster, the application thickness is kept between 8 and 15 mm. If the flatness of the substrate requires levelling beyond 20 mm, the work must be carried out in two coats. The first coat forms the body of the plaster: it is screeded with a straightedge, then immediately scored with a notched float to create mechanical keying grooves. The second coat is applied after the first has fully set, without waiting for it to dry completely, in order to preserve the moisture balance between the two coats.

Permissible thicknesses and application methods per coat
Interior substrateThickness per coatRecommended application method
Brick or calcium-silicate masonry10 to 15 mmOne coat screeded with a hatchet-type straightedge, then tightened with a plasterer's trowel
Smooth cast-in-place concrete (with bonding agent)8 to 12 mmPolymer bonding coat first, then a single coat screeded without exceeding 15 mm
Levelling on rough masonry (> 20 mm)12 to 15 mm per coatTwo successive coats with herringbone scoring of the first coat before the final set

Managing ventilation and heating of the room to stabilise drying

Mixing a plastering gypsum incorporates between 500 and 700 litres of water per cubic metre of dry material applied. About one third of this water takes part in the mineral crystallisation reaction; the remaining two thirds is free water that must leave the body of the work without destabilising the substrate. In a completely closed, unventilated room, the air immediately saturates at 100 % relative humidity, which blocks drying, liquefies the plaster surface and causes mould to appear. Conversely, a direct draught on fresh plaster causes premature evaporation of the mixing water: the plaster is burnt, becomes powdery and loses all surface hardness.

  1. Phase 1: Initial set in still air (0 to 24 hours)Close the openings to eliminate draughts on the fresh surfaces. The air must remain still to allow the crystalline network to form fully without surface desiccation.
  2. Phase 2: Continuous removal of moisture (days 2 to 7)Arrange regular air renewal by opening transom windows or low-speed forced ventilation. Air laden with water vapour must be discharged outside to avoid condensation on slabs and glazing.
  3. Phase 3: Thermal stabilisation and drying to the core (from day 8)Maintain a minimum ambient temperature of 12 °C. In humid or cold seasons, electric condensation dehumidifiers must be used to bring the relative humidity below 65 %.

In accordance with SIA 242, the site supervisor checks that the façades are closed and weatherproof before ordering the plaster to be sprayed. A regulated construction site heating system is required as soon as the building temperature falls below 10 °C. Applying gypsum plaster on a frozen substrate is prohibited, and the work must remain protected against frost for at least fourteen days after application, to prevent the gypsum crystals from breaking down through expansion of residual water.

Number of coats and timing according to total build-up (SIA 242)

In traditional plastering as in mechanical spraying, the application of interior gypsum plaster follows two successive phenomena: chemical hydraulic setting and drying by evaporation of the excess water. Setting, which transforms the hemihydrate into dihydrate by needle-like crystallisation, is complete within one to two hours depending on the additives formulated by the manufacturer. During this crystallisation stage, the material undergoes only a tiny dimensional change. By contrast, the mixing water not used by crystallisation represents nearly half of the mix volume and must escape into the surrounding air by capillarity. When the thickness of a coat exceeds the diffusion capacity of the mass, the surface dries prematurely while the core remains saturated. This severe differential shrinkage creates internal tensile stresses that inevitably cause surface crazing or open transverse cracks.

Timing of coats according to plaster thickness
Total thicknessNumber of coatsFinish of first coatRecoating interval
Up to 10 mm1 coatDirect screeding with straightedgeContinuous drying without recoating
From 11 to 20 mm2 coatsScreeding and horizontal combingWet on stiffened wet (45 to 90 min)
From 21 to 35 mm2 coatsScoring with a nail floatFull set of the base coat (minimum 24 h)
More than 35 mmNot recommendedReinforcement or dry liningSpecific technical study required

In strict compliance with good practice, SIA 242 governs the execution of interior plasters to ensure mechanical adhesion and flatness of substrates. When the specified total thickness requires two separate coats, the first coat must never be smoothed or closed with a trowel. It is screeded with a hatchet-type straightedge, then scored horizontally to form a rough key. In "wet on wet" application, the second coat is applied as soon as the first layer resists pressure without sagging, while retaining some surface moisture. If this window is missed and the base has hardened at the surface, wait for it to set completely through and lightly dampen it or apply a base regulator before spreading the finishing coat.

Construction site ventilation protocol and dryness check

Drying a gypsum plaster is a decisive airflow and thermal phase for the mechanical stability of the surface. The common site mistake is to seal up the rooms while heating abruptly with direct hot-air cannons running on gas or oil. These combustion appliances release large quantities of water vapour and saturate the atmosphere instead of drying it. In an enclosed space, a high temperature combined with a relative humidity close to one hundred per cent blocks evaporation, softens the plaster and causes mould to appear quickly. Plaster needs constant air renewal to expel its residual water.

  1. Setting without draughts (0 to 24 h)Close the windows and doors during application and the first hours. A direct draught causes rapid desiccation that burns the plaster before crystallisation is complete.
  2. Cross-ventilation (days 2 to 7)From the next day, open the transom windows or set up a permanent through-flow to evacuate the water vapour released in large quantities by the plaster.
  3. Active dehumidification in cold weather (days 8 to 14)If the outside air exceeds seventy per cent humidity or falls below ten degrees, close the room and run condensation dehumidifiers combined with indirect heating.
  4. Dryness check before coveringCheck that the surface has turned completely white and record the residual moisture measurement using the capacitive method or the calcium carbide bomb.

On construction sites in French-speaking Switzerland, rigorous coordination with site management prevents interface defects. The team leader records in the site diary any input of stray moisture, such as the pouring of a screed or accidental leaks. Properly controlled ventilation and temperatures prevent shrinkage cracks and ensure the work complies for final acceptance according to the agreed criteria.

Drying defects: diagnosing damage and compliant repairs

When gypsum plaster is subjected to excessive build-up in a single coat or to faulty thermal management on the construction site, defects appear within the first few days. Drying that is too abrupt under a hot, dry airflow causes the burnt plaster phenomenon: the water needed for mineral crystallisation evaporates before the chemical set is complete. The surface then becomes powdery, rubs off like flour under the fingernail and loses all mechanical cohesion. Conversely, a confined room saturated with humidity blocks the evaporation of the excess water. The plaster stays soft at depth, yellows, and surface mould quickly colonises the plaster.

Shrinkage cracking is the other major defect resulting from a coat that is too thick. When the applied thickness exceeds the usual tolerances set according to SIA 242, the moisture gradient between the wet core and the ventilated surface generates strong tensile stresses. The result is random crazing or open cracks. To deal with these defects, start by sounding the overall adhesion with a plasterer's hammer. Hollow, detached or drummy areas must be stripped without hesitation down to the rigid base. Never try to hide an active cracked network with a simple skim coat: the defect will reappear at the first humidity cycle.

  • Complete mechanical removal of powdery or detached areas using a scraper and a triangular scraper.
  • Careful dust removal by vigorous brushing followed by continuous industrial vacuuming of the base and rebates.
  • Restoring ambient conditions with controlled supplementary ventilation or by installing professional condensation dehumidifiers.
  • Application of a mineral impregnating primer to seal porous bases and ensure adhesion.
  • Careful rebuilding in cross-applied coats not exceeding the limit thickness, bridging stabilised cracks with a non-woven reinforcing fabric bedded into the mass.

Frequently asked questions

How to react on the construction site when the plaster has set too quickly and is powdery on the surface?

A plaster that turns powdery has lacked water to complete its mineral hydration, often because of a hot draught or an excessively absorbent substrate. Brush the powdery film vigorously with a soft wire brush to get back to sound material. If the core is solid, apply a transparent mineral base fixative to consolidate the surface before applying a thin skim coat. If the plaster remains soft on the underside, complete removal is necessary.

How to tell a gypsum shrinkage crack from structural cracking?

A shrinkage crack has a spider-web pattern, is superficial and localised, and is caused by a local excess thickness or too rapid dehydration. A structural crack, by contrast, runs through the full thickness of the plaster and generally follows masonry joints, partition heads or concrete-brick junctions. Open the crack locally with a scraper: if it continues into the structural work beneath, it is a structural defect related to a detached bridging and not an application failure.

Can propane gas heaters be allowed to speed up the drying of plasters?

No, direct-combustion propane hot-air generators are strongly discouraged. When burning, the gas releases a large volume of water vapour that overloads the ambient humidity instead of drying the building. This phenomenon delays drying to the core while abruptly heating the plaster surface, creating major risks of detachment and crazing. Always prefer indirect heating units with fresh-air intake or professional electric dehumidifiers.

When can plastered walls be released for the painter's work?

According to professional rules and SIA 242, the plaster must have completed its drying before any painting. The check is made by measuring residual moisture with a carbide hygrometer or an approved dielectric tester. In practice, the moisture content by mass must fall below the maximum tolerated threshold, generally set at one per cent. A uniform white colour across the whole surface is an essential preliminary visual indicator, but does not replace the physical measurement.

Texts and standards cited

  • SIA 242Plastering, rendering, dry construction