🧱 CFC 271Drywall partitions: framing, linings and performanceChapter 9 of 10 in the section

Partition and floating screed: which comes first, and why it matters

This chapter details the sequencing rules between erecting lightweight partitions and laying floating screeds. You will be able to identify the acoustic and mechanical risks of building on a finished screed, apply decoupling measures at the foot of the profile and carry out remedial techniques when the construction site sequencing has not been respected.

Key takeaways

  • The dry partition must be fixed to the bare floor before the screeds are poured.
  • Building on a floating screed creates a direct transmission of impact noise under SIA 181.
  • The resilient strip under the UW profile ensures mechanical and acoustic decoupling of the metal framing.
  • For remedial work on an existing screed, complete sawing of the screed remains the prescribed acoustic solution.

The installation sequence on the bare slab to lock in acoustic performance

Under the accepted rules of Swiss finishing work, the erection of plasterboard partitions on metal framing systematically takes place before the screed layer comes in. The floor UW profiles must be mechanically anchored to the bare reinforced concrete slab, cleaned of all sweepings and free of plaster deposits. This arrangement ensures that the partition interrupts the floor layer over the full height of the storey.

Interposing a resilient strip of closed-cell polyethylene foam or bituminous felt under the floor UW profile is an inseparable part of this step. Glued or stapled under the outer flange of the profile before plugging, this strip seals the joint against air and absorbs structural micro-vibrations. The floor fixings, spaced at a maximum of 60 or 80 centimetres as prescribed, must compress this seal evenly without shearing it.

Once the metal framing has been clad with its boards down to the bare floor, the floating screed can be installed on each side of the lining. The perimeter edge strip laid by the screed layer then runs up against the plasterboard facings, creating two strictly decoupled screed bays. The insulating build-up under the screed and the poured mass no longer transmit their vibrations from one room to the other.

Consequences of poor sequencing and remedial methods on a finished screed

The coordination error of pouring the whole liquid or traditional screed over a floor slab before the partitions are set out causes two major defects. The first is an acoustic bridge through the screed: the covering mortar, resting on a continuous compressible insulation layer, acts as a soundboard from one room to the other. Footfall and chair impacts travel beneath the partition, short-circuiting the insulating performance of the mineral wool panels and the double plasterboard skins.

The second defect is mechanical. The floating screed was not designed to withstand heavy line loads. The self-weight of the complete partition, increased by any suspended loads (kitchen cabinets, radiators, heavy furniture), creates a hard spot on the resilient acoustic insulation under the screed. This localised differential settlement inevitably cracks the screed along the framing and causes skirting boards to come away or the plaster joints at the ceiling to debond.

When the screed has already been laid and the partitions must absolutely be erected, two construction site solutions compete depending on the required performance level:

Comparison of remedial erection solutions on an existing floor
Remedial methodAcoustic impactExecution on the construction siteFloor heating
Complete sawing of the screedCompliant with SIA 181 (continuity cut)Cutting through the full thickness, removing the insulation, fixing on the bare slabProhibited if coils cross the line
Erection on floating screed with resilient stripLow (permanent lateral acoustic bridge)Chemical fixing or structural bonding, UW profile on heavy elastomer stripCompatible by bonding, partition load strictly limited
  1. Finding and technical notificationNote the presence of the continuous, unjointed screed. Under art. 365 CO, the contractor must immediately inform the client or the site management if a circumstance jeopardises the proper execution of the work, notifying that sound insulation cannot be guaranteed.
  2. Checking the embedded servicesConsult the heating engineer's service layout drawings and locate the routes using a thermal camera or an inductive detector to avoid any damage.
  3. Making the clean cutMake two parallel diamond-saw cuts with source-controlled dust extraction, at a width equal to the thickness of the finished partition plus 10 millimetres of perimeter clearance.
  4. Removal and preparation of the baseBreak out the sawn strip of screed with a light chisel hammer, remove the strip of floor insulation beneath, then dust off the bare slab before fixing the UW profile on a resilient strip.

Where sawing proves impossible because of active underfloor heating beneath the partition, only a lightweight interior distribution partition can be accepted. The UW profile must then be laid on a high-density synthetic rubber resilient strip wider than the framing, and bonded with a highly elastic polymer sealant so as to rule out any mechanical drilling of the floating screed.

Decoupling at the foot and preventing hard spots on an existing screed

Building a dry partition on an existing floating screed requires the dry-construction installer to neutralise two interdependent problems: the acoustic bridge by structure-borne transmission and the structural hard spot. When a screed is poured on a flexible acoustic insulation, it remains free to deflect under service loads and hydraulic shrinkage. If the metal framing is plugged into it without precautions, the partition becomes an unexpected rigid support that blocks the natural movement of the mortar. The slightest differential settlement causes micro-cracks to appear at the board joints and at the junctions with plastered ceilings.

To limit these defects when erection on the bare slab was not carried out beforehand, the resilient strip at the foot of the partition is the key technical element. This strip, made of elastomer or closed-cell extruded polyethylene foam, must be bonded under the metal flange of the bottom track. Its width must imperatively project on both sides to support the full thickness of the facings. The mechanical fixings of the profile must stop within the usable thickness of the screed, without perforating the resilient underlay or reaching the load-bearing slab. Short fixings suited to the measured mortar thickness avoid any localised crushing.

Comparative behaviour of connection methods according to the erection configuration
Erection configurationConsequence under SIA 181Mechanical behaviourInstallation requirement
Erection on bare slab (correct sequence)Maximum compliance; complete break in lateral transmissionAbsolute stability; no risk linked to screed shrinkageAcoustic strip under profile, sealed upturn of the edge insulation against the partition
Erection on continuous floating screedMajor acoustic bridge through the screed; degraded sound insulationHard spot; localised crushing and cracking of jointsProjecting resilient strip at the foot of the partition, short fixings
Erection on screed decoupled by sawingSound insulation restored; lateral transmission limitedMechanical independence of the two mortar baysSawing down to the insulation, fitting backing rod and elastic sealant

SIA 181 requirements and after-the-fact decoupling protocol

The SIA 181 requirements impose strict limit values for insulation against airborne and impact noise between protected rooms of different uses. In a compliant structure, the mass-spring-mass principle applies both to the partition build-up and to the complete cut of the floating floor. As soon as the sequence of partition and screed is reversed without sawing the mortar, the acoustic bridge through the screed turns it into a direct conductor of structure-borne vibrations. Waves generated in one room travel without attenuation beneath the bottom profile to the adjacent room.

  1. Diagnosing the route and locating servicesLocate any electrical conduits or underfloor heating embedded in the screed before any cutting, using a thermal camera or a metal detector.
  2. Cutting the mortar down to the acoustic resilient layerMake a straight saw cut along the axis of the partition, setting the depth to split the mortar without cutting into the insulating layer beneath.
  3. Fitting the resilient strip and the trackPlace a resilient strip at the foot of the partition under the UW profile, with sufficient overhang to also decouple the plasterboard facings.
  4. Short mechanical anchoringFix the track with short plugs whose expansion takes place in the upper half of the screed, avoiding any contact with the structural slab.
  5. Flexible sealing at the foot of the facingMaintain a 5 millimetre gap under the plasterboard above the finished floor, then fill the void with a permanently elastic sealant.

When the course of the works requires the partitions to be erected on an already completed screed, the team leader issues a written notice of anomaly to the site management, in accordance with SIA 118. The technical note states that keeping a continuous screed jeopardises achieving the acoustic performance required by SIA 181. Without a written change order prescribing complete sawing of the floating slab, the plastering contractor cannot be held liable for acoustic insulation defects found during final inspections.

Handling non-conformities and remedial protocol on an existing screed

When the dry-construction plasterer discovers on the construction site a floating screed poured continuously where the plans provided for erection directly on the bare slab, the alert must be recorded without delay. Building a distribution or separating partition directly on this continuous screed turns the floor element into a major sound bridge and creates a mechanical hard spot. The insulation under the screed is crushed by the self-weight of the facings, causing shear cracks at the skirting and failure of the joints. Compliance with the SIA 181 requirements can then no longer be guaranteed without methodical remedial work.

  1. Notice of technical reservationImmediately notify the non-conformity in writing to the site management in accordance with the Code of Obligations and SIA 118, recording that the target acoustic insulation values cannot be achieved.
  2. Decoupling saw cutAfter approval by the site management and strict location of the underfloor heating services, make a through cut in the screed mortar along the line of the partition.
  3. Fitting the resilient stripPlace a continuous closed-cell resilient strip at the bottom of the cut and along the sawn edges to neutralise any hard contact.
  4. Erection and flexible sealingFix the metal floor profile, erect the framing, screw on the boards leaving a 5 mm gap at the foot, then fill this joint with a flexible, durable sealant.

If mechanical sawing is ruled out because the floor services are too dense, the partition will be set on the existing mortar using a suitable resilient sole and limited fixings. In this forced configuration, the contractor formally records that sound reduction will be penalised by flanking transmission and declines any guarantee on the SIA 181 comfort values.

Frequently asked questions

Can a lightweight partition simply be built on a floating screed without any special precautions?

No, this is strongly advised against. Fixing a profile directly onto the floating screed creates an acoustic bridge that transmits airborne and impact noise from one room to the other through the mortar. In addition, the line load imposed by the plasterboard can locally compress the thermal or acoustic insulation under the screed, causing differential settlement, cracks at the floor-partition junctions and skirting boards coming away.

How should one proceed if the underfloor heating is already embedded in the screed where the partition is to go?

In this situation, complete sawing of the mortar is prohibited so as not to puncture the heating pipes. The solution is to set the partition on the finished screed, systematically interposing a continuous resilient strip under the UW profile. Fixing to the floor is done by structural bonding or short screwing after prior thermographic survey. A written reservation concerning acoustic performance under SIA 181 must be sent to the site management.

What exactly is the role of the resilient strip under the bottom partition track?

The resilient strip, generally made of cross-linked polyethylene foam or elastomer, provides mechanical decoupling between the metal framing and the floor. It attenuates the transmission of structure-borne sound vibrations between adjacent rooms, compensates for small irregularities in the substrate and ensures airtightness under the profile. Without this component, the metal framing resonates directly with the screed, degrading the overall sound reduction index of the wall.

What is the contractual procedure if the imposed sequencing departs from the accepted rules of the trade?

As soon as the reversed sequence is noticed on the construction site, the plastering contractor must record the situation and warn the client or the site management in writing. In accordance with the principles of SIA 118 and the Code of Obligations, this preventive notice must describe the expected acoustic degradation with respect to SIA 181 and relieve the contractor of liability before any fixing onto a floating screed.

Texts and standards cited

  • norme SIA 181Noise protection in buildings, requirements for insulation against airborne and impact noise
  • norme SIA 118General conditions for the execution of construction work, duties of notification and management of technical reservations
  • code des obligationsGeneral rules governing the contract for work and the contractor's duty of care