🧱 CFC 271Dust, health and the plasterer's construction site managementChapter 7 of 10 in the section

Storing plasterboard: flat, dry, and the bowed board that must not be fixed

Storing plasterboard on a construction site requires rigorous logistics to avoid deformation and damage. By the end of this chapter, you will know how to support pallets according to good practice, protect the facings from residual moisture, schedule deliveries as late as is useful and uncompromisingly sort out damaged boards before screwing.

Key takeaways

  • Delivering as late as is useful avoids prolonged exposure to the weather and to site dust.
  • Storage must be strictly flat, on aligned bearers distributed under the stack.
  • A thick polyethylene film isolates the boards from the residual moisture of concrete slabs.
  • Any bowed, twisted board or board with delaminated paper must be set aside immediately and not fixed.

Organising just-in-time delivery and support on the slab

Managing plasterboard starts with the supply schedule. In finishing work in French-speaking Switzerland, the golden rule is to plan delivery as late as is useful. A pallet dropped off four weeks before the metal framing is erected is exposed to water splashes, draughts from a structural shell that is not yet closed and repeated mechanical impacts from other trades. Supply must coincide with the complete completion of the building envelope and the actual start of the setting-out of the lightweight partitions.

From the moment of unloading, the choice of the drop-off area determines the integrity of the product. Under no circumstances may boards be stored upright, leaning at an angle against a partition or a façade wall. A standard plasterboard twelve and a half millimetres thick has a natural flexibility; under prolonged static bending, it sags under its own weight. After three days in this position, the deformation becomes irreversible because of the creep of the gypsum and the relaxation of the cellulose fibres of the lining paper.

  1. Checking the load-bearing capacityCheck the permissible load on the concrete slab or the intermediate floor. A stack of fifty standard boards represents approximately fifty kilograms per square metre of floor area, i.e. a concentrated load that must never be placed on an unpropped walkway area.
  2. Installing the moisture barrierLay a waterproof polyethylene film at least two hundred micrometres thick on the floor, with a generous overlap, to block rising water from fresh concrete or condensation moisture.
  3. Arrangement of the timber bearersPlace dry timber battens or bearers of uniform thickness, at least fifty millimetres high, spaced at most fifty centimetres apart, to support the stack without intermediate deflection.
  4. Stacking and vertical alignmentStack the boards flat, making sure that the edges are perfectly plumb. When several pallets are stacked, align the intermediate bearers vertically with the lower bearers to transmit the loads directly without bowing the boards.
Recommended parameters for the horizontal support of plasterboard
Board lengthMinimum number of bearersMaximum centre-to-centre spacingMinimum ground clearance
200 cm to 250 cm5 bearers50 cm50 mm
260 cm to 300 cm6 bearers50 cm50 mm
More than 300 cm7 to 8 bearers45 cm60 mm

Checking moisture and sorting boards before fixing

Water is the worst enemy of set and compacted gypsum. On a building site, direct contact with a still-damp slab quickly saturates the lower edges by capillary action. The gypsum then loses its internal mechanical cohesion, the protective paper softens and the starch adhesive bonding the facing to the mineral core dissolves. A board that has absorbed residual water never regains its original rigidity, even after complete air drying.

Before starting to clad a framing, the team leader systematically sorts each board taken from the stack. A board with a residual curvature visible with a two-metre straightedge must not be screwed to the metal studs. Forcing a bowed board with self-drilling screws induces permanent tensile stresses in the framing. This inevitably causes transverse cracking of the joints when the building is put into service, or the paper bursting at the fixing heads.

  • Boards with softened or crumbly edges under simple thumb pressure.
  • Boards with surface mould, drying stains or blackening of the kraft paper.
  • Bowed boards with a free deflection greater than five millimetres over their length.
  • Tapered edges crushed, broken or ragged during handling with a pallet truck.
  • Boards whose paper facing lifts or comes away from the gypsum core.

Rejected boards are immediately marked with a cross in grease crayon and isolated from the installation area to prevent any unintentional use by the fitters. After cutting, these offcuts can sometimes be used for small cut-outs or low-height casings not subject to acoustic or mechanical requirements, provided that the retained area is completely sound and dry. Otherwise, they go to the sorting skips in accordance with construction waste management.

Defects of the deformed facing and refusal of mechanical straightening

The temptation to use a bowed board in the hope of straightening it when screwing it to the metal framing is a frequent execution error on finishing-work sites. A standard or moisture-resistant plasterboard that has sagged under its own weight or absorbed the residual moisture of a slab shows an irreversible change in its internal structure. During mechanical tightening against the vertical sections, the tensile stress exerted on the outer paper facing exceeds its elastic limit, which causes the gypsum core to break even before the plaster is applied.

A deformed board systematically produces millimetric misalignments between adjacent boards. For the dry-lining fitter, these defects prevent any compliant treatment of the joints according to the flatness requirements for standard or high-quality finish levels. Even if the screw manages to press the sheet of paper temporarily against the flange of the stud, the residual tension releases a continuous thrust that eventually lifts the reinforcing tape or pops out the screw heads through reverse punching.

Behaviour and defects of damaged boards when attempting to fix them
Initial defect of the boardBehaviour under the screw gunConsequence on the finished workWorkshop or site decision
Longitudinal bowing (stored on edge)The paper tears under the screw head; the core crushes without reaching the metal studMisalignment exceeding the flatness tolerances; rapid cracking of the jointSet aside immediately and scrap the board
Swelling of the edges (contact with a puddle or fresh screed)Immediate crumbling of the dampened gypsum when the self-drilling screw penetratesComplete lack of mechanical hold; the facing comes away under loadCut out the damp area if enough board remains, otherwise reject entirely
Transverse undulation (bearers too widely spaced under the stack)Bulging board creating an air gap between the acoustic insulation and the rear faceBuckling visible in raking light; rupture of the joint tape under tensionSet aside for concealed infills or dispose of

Sorting protocol, marking of rejects and methodical removal

The team leader or plasterer foreman must formalise the sorting of the boards before they are distributed to the rooms of the building. Every board with a measurable residual deflection under the two-metre straightedge, local delamination of the facing or softening of the tapered edges must receive a visible physical marking in grease crayon. This marking strictly prohibits the fitters from incorporating it into partition walls, thermal linings or suspended ceilings.

  • Systematic check of the straightness of the tapered edges before butting them against the studs.
  • Measurement of the relative humidity of the gypsum with a pin-type or capacitive moisture meter in case of visual doubt.
  • Marking of the damaged areas with a line or crayon to prevent inadvertent installation.
  • Immediate isolation of the downgraded boards away from the main installation area to avoid any mixing with sound deliveries.

Rejected boards must not remain in the circulation areas of the building. The provisions of the ordinance on construction work require workstations to be protected against clutter and falling materials. The contractor therefore organises the removal of non-reusable rejects as work proceeds, observing the gypsum recycling channels prescribed by the ordinance on the limitation and disposal of waste. Sound large-format offcuts can be recut on a bench to serve as door transoms or linings for service ducts, on the express condition that the gypsum core has not undergone any liquid impregnation.

Managing storage damage and formal notice of non-conformity

When site organisation fails, the consequences for plasterboard are direct. A delivery dropped off in a room that is not weathertight, accidental contact with a puddle on fresh screed or an improvised vertical stacking against raw masonry ruin the mechanical properties of the product within a few dozen hours. The gypsum core absorbs water by capillary action and the facing paper loses its adhesion. Faced with this finding, the team leader or plastering site manager must firmly refuse to install these degraded boards in order to prevent future cracking of the joints.

  1. Immediate joint inspection recordAs soon as you discover boards exposed to water or bowed by vertical support, call in the site management. Take clear photographs showing the deflection under the two-metre straightedge, the state of dampness of the facing paper and the lack of weathertightness of the room.
  2. Drafting the formal noticeDraft a written notice without delay in accordance with the rules of the SIA 118 standard. Notify the non-conformity of the site's ambient conditions, refuse to fix the damaged boards and ask for written instructions concerning the replacement of the destroyed stock.
  3. Recording and marking with a felt-tip penMark each damaged board with an indelible cross on the visible face to prevent its incorporation into the framing. Isolate the defective pallet away from the work areas and prohibit its use by the fitters.
  4. Removal and resupplyHave responsibility for the damage recorded in the site minutes. Order a new batch for delivery as late as is useful, only once the drying of the rooms and the weathertight closure of the building are certified.

Frequently asked questions

Can a bowed plasterboard be straightened by forcing it with screws onto the framing?

No, this practice is strictly prohibited. Mechanically forcing a bulging board introduces permanent tension on the self-drilling screws and on the metal studs. Under the effect of humidity variations, the screw heads end up shearing the facing paper or going through the gypsum core. The defect inevitably results in longitudinal joint cracks or visible bumps after the plaster is applied.

Why refuse a delivery of boards before the building is weathertight?

Standard plasterboard is a highly hygroscopic material intended exclusively for dry interior work. An early delivery onto a slab exposed to storm rain, damp draughts or mortar splashes condemns the batch. Storage on the construction site must take place as late as is useful, in rooms closed by weathertight joinery, heated if necessary and free of any residual moisture from the structural work.

What should be done with boards whose edge has absorbed moisture from a puddle without visible deformation?

These boards must systematically be set aside from installation in partitions or ceilings. Water absorption by capillary action at the edges destroys the internal cohesion of the gypsum at the very place where the perimeter screwing takes place. If only the lower end is affected over a few centimetres, you may possibly cut off the sound part for small infills or specific casings, provided that the paper remains perfectly bonded.

Who bears the financial cost of boards damaged by poor storage on the construction site?

If the plasterer stored his pallets without bearers or upright against a wall without observing good practice, the damage remains entirely at his expense. On the other hand, if the damage results from a sudden water infiltration attributable to a delay in closing the structural work or to a leak in the temporary sanitary installations, the site management must record the loss for compensation.

Texts and standards cited

  • norme SIA 118General conditions for the execution of construction work, duties to notify and management of notices of defects