Key takeaways
- Escape routes require facing and insulation materials strictly classified in group RF1.
- The framing includes reinforced studs to receive the frames of landing doors without compromising fire resistance.
- Continuous perimeter sealing prevents hot smoke from passing at the junction with the solid slabs.
- The safety inspection checks the type of boards, the visible fixings and the written certificates of conformity.
AEAI RF1 requirements and make-up of partitions lining a stairwell
In a Swiss building, the stairwell is the backbone of the rescue concept. Defined as a vertical escape route, it requires strict containment to ensure the escape of occupants and the intervention of the fire brigade. Unlike an ordinary dividing partition between two rooms of the same dwelling, the wall separating a unit of use from the stairwell must meet the fire protection regulations of the Association of Cantonal Fire Insurance Institutions (AEAI). These requirements dictate both the fire resistance of the complete element (often EI 30 or EI 60 depending on the use and the height of the building) and the reaction to fire of the constituent materials.
- Reaction-to-fire group RF1
- Designates, according to the AEAI requirements, materials that do not contribute to a fire (non-combustible). The material must not develop any critically toxic smoke nor produce burning drops or debris when exposed to heat.
For the dry-lining plasterer, the RF1 requirement on the escape-route side rules out the use of standard boards or coverings containing sensitive organic binders. Use enhanced-cohesion plasterboards reinforced with glass fibres, high-density plasterboards or fibre-gypsum boards classified as non-combustible. The insulation housed in the partition cavity is not left to chance: it must be a mineral stone wool with a melting point above 1000 °C, also certified RF1, laid with tight joints and without any air gap that could create a chimney effect.
| Partition element | Prescribed material | AEAI fire safety criterion |
|---|---|---|
| Facing on stairwell side | Fibre-gypsum or reinforced gypsum boards 2 × 15 mm | Group RF1, valid AEAI certificate |
| Metal framing | Galvanised sheet steel sections, thickness 0.6 mm | Non-combustible RF1, maximum spacing 600 mm |
| Internal insulation | Stone wool, minimum density 30 kg/m³ | Group RF1, melting point above 1000 °C |
| Facing on dwelling side | Fire-resistant plasterboards 2 × 15 mm | In accordance with the test report of the tested EI system |
The metal framing is also subject to specific stresses at openings. Fitting a fire-rated landing door (supplied and installed by the joiner, CFC 273) requires increased rigidity to support the weight of the leaf and the mechanical closing cycles without deforming the facing. The dry-lining installer sets up thick tubular reinforcing sections (UA sections of at least 2 mm), mechanically anchored at the floor and at the head into the concrete slab using reinforced fixing brackets. The opening must respect a minimum perimeter clearance to allow intumescent sealing without a thermal bridge.
Execution of junctions and points checked during the safety inspection
The performance of a fire-resistant partition lining an escape route depends on the absolute continuity of its envelope. The classic failure in fire tests does not originate from the centre of the panel, but from the perimeter connections. At the head of the partition under the rough slab, the connection must absorb the permissible deflections of the load-bearing structure while guaranteeing tightness against hot gases. The contractor uses telescopic head angles filled with RF1 mineral wool and closes the edges with an approved intumescent acrylic sealant.
- Sealing of the bottom track and the head trackPlace a resilient strip classified as non-combustible under the UW section and apply a continuous bead of fire-resistant sealant at the foot of the partition on the rough slab before the screed is subsequently poured.
- Staggered laying of multilayer facingsStagger the vertical and horizontal joints by at least 400 mm between the first and second layers of boards. Always fill the joints of the first layer before applying the second.
- Treatment of permitted technical penetrationsMake precise openings for the sanitary or electrical trades. Immediately fill every gap with RF1 plaster filler or with fire-resistant mortar approved for the system.
Before the handover of the work, the fire safety officer of the client's representative or the cantonal fire police inspector carries out a conformity inspection. This safety inspection is not limited to a visual examination of the surface finish. The expert examines the actual make-up of the wall before painting and requires the complete documentation file. The plastering contractor must present a signed certificate of conforming execution, stating the AEAI registration number of the partition system installed, as well as the data sheets of the sealants and mineral wools used on the construction site.
- Checking of the nominal thickness and the marking of the facing boards by non-destructive sampling.
- Verification of the spacing of the screw fixings on the studs, less than or equal to 250 mm on the visible layer.
- Inspection of the intumescent sealing around door frames and at slab-to-wall junctions.
- Examination for the total absence of loose cables or unshelled plastic electrical boxes passing through the wall.
- Comparison of the delivery notes for RF1 rock wool with the quantities actually installed on the escape routes.
Technical penetrations, access hatches and door-frame reinforcements in a stairwell wall
In a vertical escape route such as a stairwell, the lightweight partition tolerates no unqualified penetration. Every technical intervention that weakens the facing endangers the smoke-tightness and the thermal insulation required by the AEAI fire protection requirements. Electricians or plumbers regularly create openings for the passage of pipes or the installation of distribution boards. The dry-lining plasterer is responsible for restoring the full fire resistance of the wall at these penetrations, scrupulously respecting the approval of the chosen system.
For technical shafts and electrical boards built into the thickness of the lining alongside the stairwell, the internal lining of the recess must provide a fire resistance strictly identical to that of the overall build-up, most often EI 60 or EI 90 depending on the height of the building. This recessing requires a rear box-out made of fibre-reinforced gypsum boards or calcium silicate boards of class RF1. No combustible element may remain in the wall cavity facing the escape route.
| Built-in element | Facing material requirement | Fixing and reinforcement device | Perimeter sealing |
|---|---|---|---|
| Technical access hatch | Frame and leaf certified RF1 (EI 30 or EI 60) | Independent suspension on reinforced studs | Intumescent seal and fire-resistant acrylic sealant |
| Pipe penetration opening | Rigid non-combustible metal sleeve | Expanding metal anchors in heavy framing | RF1 grouting mortar or stone wool shell |
| Electrical device box | Certified box with intumescent pad | Mechanical fixing by claws without rear perforation | Intumescent paste applied to the back of the box |
| Opening for fire-rated landing door | Cross-layered boarding returned into the reveal, RF1 | Reinforced door-frame sections secured to the structural work | Tight packing in high-density RF1 stone wool |
The surround of fire-resistant door sets is a zone of maximum mechanical and thermal stress. The dry-lining installer ensures the structural stability of the opening by incorporating reinforced sections at least two millimetres thick, fixed at the floor slab and at the soffit by reinforced brackets and zinc-plated steel anchor bolts. The reveals receive a double thickness of non-combustible boards that cover the frame without a break in the material. The residual space between the metal section and the joinery element is packed solid with compressed RF1 mineral rock wool, ensuring that no flame or hot gas passes around the frame in the event of a fire.
AEAI conformity file, self-inspections and acceptance by the fire authority
The acceptance of a fire compartmentation on an escape route by the cantonal fire protection authority, the cantonal building insurance or the municipal fire police is not based on a simple visual estimate. The safety inspector rigorously examines the traceability of the materials installed, the conformity of the assembly with the Swiss approval certificates and the continuity of the sealed barriers. The slightest discrepancy between the system tested in the laboratory and the execution on the construction site leads to a refusal of the certificate of completion, blocking the occupancy permit for the building.
- Joint survey of framing and insulation before closingDraw up a dated photographic self-inspection record showing the actual stud spacing, the fixing of the floor and ceiling tracks, and the density of the RF1 mineral wool placed in the cavity without sagging.
- Verification of fixing lengths and board fasteningCheck by sampling that the drywall screws penetrate at least ten millimetres into the structural metal and that the heads sit flush with the paper without tearing the gypsum core.
- Systematic treatment of the underlying jointsFill every joint of the first facing layer with approved jointing compound before fixing the finishing boards, ensuring tightness even in the event of thermal expansion.
- Compilation of the certificate-of-conformity fileGather the declarations of conformity of the dry-lining contractor, the AEAI approval numbers of each component and the data sheets of the fire-resistant sealants for submission to the site management.
The plastering contractor formally issues its certificate of conformity for the partitions delimiting the stairwell. This legal document engages the liability of the company: it certifies that the construction strictly complies with the implementing provisions of the AEAI fire protection directive on escape routes. The conformity of the work depends directly on this documentary rigour, which validates the protection of users making their way to the emergency exits in the event of an emergency evacuation.
Non-conformities in an escape route: rectification and clearing of safety reservations
Finding a defect in a partition lining a stairwell is not a matter of a simple cosmetic touch-up. As soon as the fire protection authority or the fire quality assurance officer notes a deviation, the occupancy permit or the final certificate of conformity is directly blocked. Vertical escape routes are the last refuge of the occupants in the event of a fire; there is zero tolerance there regarding the type of materials and smoke-tightness.
Recurring failures involve the unintentional introduction of combustible components departing from the RF1 standard, the improvised sealing of technical penetrations with unapproved expanding foams or the absence of certified access hatches. When the inspector refuses the acceptance of the work, the project manager and the team leader must immediately start a methodical procedure to restore conformity without damaging the overall integrity of the separating element.
- Locating and targeted samplingCarry out a joint visual inspection with the site management. If doubt remains about the type of internal board or the thickness of RF1 stone wool mineral insulation, make a precise trial opening, photograph the internal build-up and record the manufacturer's marking of the board.
- Removal of incompatible materialsRemove all uncertified products completely. Standard foams, forgotten temporary timber furring or non-fire-resistant acrylic joints must be removed mechanically down to the sound substrate, without damaging the load-bearing metal framing.
- Reinstatement in accordance with the declaration of conformityFill the openings using a fire-resistant mortar or a sealing system under valid Swiss technical approval. Fit strictly non-combustible RF1 facings, respecting the screw pattern and the joint staggering prescribed by the manufacturer.
- Updating the safety fileDraw up the record of the corrective intervention, attach the data sheets of the substitute products and submit the revised self-inspection report to the fire authority for formal validation before commissioning.
Frequently asked questions
What should be done if a facing not classified RF1 has been fitted by mistake on the stairwell side?
The fire protection directive requires total non-combustibility for vertical escape routes. No surface treatment or fire-retardant varnish can requalify a combustible board as class RF1 on the construction site. The only solution acceptable to the fire protection authority is to remove the non-conforming facing and replace it with certified non-combustible gypsum or calcium silicate boards, fixed according to the approved construction system.
How should an undeclared electric cable penetration drilled after the partition was closed be treated?
Any perforation of the fire-resistant stairwell partition destroys smoke-tightness. It is forbidden to close the opening with ordinary plaster. The tradesperson must clear sufficient space around the conduit, install a sleeve or a modular sealing system under Swiss technical approval for the required resistance rating, then seal the perimeter with a compatible intumescent sealant, together with an identification label for the fire-resistant system.
Can the fire safety inspector require destructive sampling during the final inspection?
Yes, if the plastering company's self-inspection file is incomplete or if doubts arise about the continuity of the internal layers. The inspector may order trial openings to be made to check the actual presence of non-combustible mineral wool, the number of board layers and the conformity of the metal studs. These openings must then be closed again according to the installation instructions of the approved fire-resistant system.
Must access hatches to technical shafts installed in a stairwell be RF1?
Access hatches built into the walls delimiting a vertical escape route must offer the same fire resistance as the partition and have a non-combustible RF1 leaf on the stairwell side. They must be fitted with a valid AEAI approval, a smoke-tight seal and a key-locking system preventing any unauthorised access by the building's users.
Texts and standards cited
- Normes de protection incendie AEAIDirectives on the RF1 classification of building materials and on the compartmentation of escape routes
- Norme SIA 118General conditions for the execution of construction work and management of defects in the work
