Interior plasters: substrates, coats and smoothing: the execution reference
Intended for site managers, foremen and plasterers in Vaud, Geneva and Valais, this section covers the efficient application of mineral interior plasters. From the mandatory dryness check of the structural work to the final tightening of smoothed surfaces, discover the rules of the trade governed by SIA 242. It provides workshop and construction site benchmarks to secure adhesion, neutralise cracking at junctions and guarantee a uniform finish, with no visible marks or misalignment.
- 10chapters
- 22 000words
- 6sections in the training course
- 60chapters in total
Key values to remember 4
5 °C
Ambient and substrate temperature required for the application and drying of gypsum plaster
10 mm
Nominal average thickness of a single-coat interior gypsum plaster on masonry
200 mm
Minimum embedding width of the reinforcing mesh at the junction between heterogeneous substrates
60 days
Legal period for checking and reporting defects in a building work
Technical scope of the trade and limits of services (CFC 271)
The plasterer-drywall builder is responsible for applying mineral interior plasters on raw or existing substrates, in accordance with the requirements of SIA 242. The technical scope includes applying gypsum plasters by hand or machine-sprayed, producing hydraulic or air-lime plasters in damp rooms and on historic walls, as well as all operations of levelling, trowel tightening and embedding textile reinforcement. The craftsman guarantees the overall flatness of the walls, the plumb of the edges and the agreed surface texture, from the application of the primary bonding coat to the careful surface finishing ready to receive decorative finishes.
A strict delimitation prevents interface conflicts and secures contractual responsibilities on Swiss construction sites. The construction of load-bearing walls in cast concrete or fired clay brick belongs to the structural work trades CFC 201 and CFC 211.1. External thermal insulation systems and their mineral renders fall exclusively to the facade builder CFC 221. The painter CFC 272, for their part, handles the regulating primers, decorative painting and the fixing of bonded wall coverings. The plasterer delivers a raw or smoothed mineral surface, compliant with the permitted geometric tolerances, but carries out no painting work. Floor screeds and self-levelling smoothing compounds remain the preserve of the screed layer CFC 281, while chases and embedded technical ducts are carried out by the electrical installers CFC 232 or sanitary installers CFC 250 before filling.
| Work or service | Responsible trade | Technical boundary CFC 271 |
|---|---|---|
| Reinforced concrete substrate | Masonry CFC 201 | Checking roughness, dryness and removal of oils |
| Sprayed gypsum plaster | Plastering CFC 271 | Application of primer, plaster body and smoothing |
| Painting and priming | Painting CFC 272 | Checking the delivered surface and insulating primer |
| Chases for fluid pipework | Sanitary installations CFC 250 | Filling with high-strength gypsum plaster and reinforced bridging of the surface |
| Guardrails and frames | Joinery CFC 273 | Lining of reveals and sealing of the opening edge |
Learning path and operational sequence
Applying mineral plasters requires a strict, methodical order to avoid adhesion defects, structural cracking and unsightly joints between passes. The ten chapters of this section guide teams step by step, from the initial inspection of the raw substrate to the final cleaning of the construction site protections. Following this sequence guarantees a perfect mechanical bond between coats, constant control of setting times and flawless flatness under natural or raking light.
- Phase 1: Substrate diagnosis and bonding primers (chapters 01 and 02)The path begins with checking the dryness, porosity and cleanliness of masonry and concrete. You learn to formulate a reasoned refusal in the case of a non-compliant substrate and to select the appropriate bonding coat to neutralise closed surfaces.
- Phase 2: Thicknesses, corner reinforcement and changes of background (chapters 03 to 05)This phase covers mixing, spraying at a uniform thickness and the setting time of gypsum plaster. You discover how to set galvanised corner beads precisely and how to embed strips of textile mesh at brick-concrete transitions to dissipate expansion stresses.
- Phase 3: Finishing, tightening and surface quality (chapter 06)Here the plasterer perfects the handling of the knife and the stainless steel trowel. The challenge is to tighten the fine paste without tearing or ridges, in order to deliver a uniform surface free of patching marks for acceptance inspections.
- Phase 4: Refurbishment, damp masonry and lime (chapters 07 and 08)Work on old buildings calls for careful acoustic sounding to remove degraded plasters. On walls affected by rising damp, you learn why breathable lime mortar must replace waterproof cement to regulate water vapour transfer without efflorescence.
- Phase 5: Winter conditions, sheeting and workshop clear-down (chapters 09 and 10)The concluding section details maintaining minimum temperatures and the ventilation required to counter powdering of gypsum plaster in winter. Finally, it covers the watertight protection of frames and the immediate cleaning of splashes to hand back clean rooms to the other trades.
📘 Chapters in this section 10
Accepting the substrate: dryness, cleanliness, absorbency and reasoned rejection
Secure your construction sites by identifying substrate defects before your company's liability is engaged.
Interior plasters: substrates, coats and smoothingBonding to smooth surfaces: primer, bonding bridge and formwork concrete
Avoid detachment on cast concrete by selecting the bonding primer suited to the actual porosity.
Interior plasters: substrates, coats and smoothingPlastering with gypsum: thickness per coat, setting time and drying of the room
Master the plaster passes and setting time to avoid any destructive blistering or crazing.
Interior plasters: substrates, coats and smoothingProtecting edges: corner bead, stop bead and window reveal
Fix your corner beads straight to guarantee edges that withstand everyday impacts.
Interior plasters: substrates, coats and smoothingChange of substrate: reinforcing mesh, concrete against masonry and anticipated cracking
Neutralise shrinkage cracks between concrete and brick by embedding a continuous glass mesh.
Interior plasters: substrates, coats and smoothingSmoothing: finishing plaster, tightening with the smoothing trowel and tool marks
Achieve a flawless smooth surface without trowel marks, ready for inspection under raking light.
Interior plasters: substrates, coats and smoothingPlastering over existing work: hammer sounding, stripping and repair by zones
Renovate without risk by sounding hollow backgrounds to methodically remove old unstable layers.
Interior plasters: substrates, coats and smoothingDamp old wall: lime plaster, vapour permeability and the cement mistake
Preserve the breathability of old damp masonry by banning cement in favour of lime.
Interior plasters: substrates, coats and smoothingPlastering in winter: room and substrate temperature, frost and construction site heating
Anticipate frost and winter humidity with strict heating and ventilation protocols.
Interior plasters: substrates, coats and smoothingProtect before spraying: joinery, screeds, services and cleaning of overspray
Sheet joinery and equipment effectively to eliminate any time lost on heavy cleaning after spraying.