Key takeaways
- Any unsealed opening cancels the EI resistance of the original lightweight partition.
- The choice of sleeve or sealant depends on whether the material passing through is combustible or non-combustible.
- Standardised labelling of each penetration is the only proof accepted by the building police.
- The site agreement must unambiguously assign the financial burden of residual sealing work.
Select a certified fire-stop system according to the type of services passing through
Every opening made in an EI 30 or EI 60 fire-resisting partition for the passage of electrical conduits, sanitary pipes or heating pipework destroys the integrity of the wall. The drywall plasterer supplies a partition tested in a precise configuration. As soon as the building services installers drill through the lining, the overall fire resistance collapses, unless the breach is restored with a sealing system approved by the Association of Cantonal Fire Insurance Companies.
- VKF RF1
- Swiss reaction-to-fire classification designating a non-combustible material that produces no smoke emission or burning droplets during a fire.
Closing an opening must not be improvised with standard plaster or offcuts of plasterboard. The type of sealing depends on whether the medium and the pipe are combustible. For non-combustible metal pipes in copper or steel, thermal conduction along the metal is the main risk of ignition in neighbouring rooms. The sealing requires an elastic intumescent acrylic sealant or a fire-stop sealing mortar, with mineral insulation of VKF RF1 reaction-to-fire class placed on the pipework on both sides of the plaster wall.
For combustible plastic pipes, such as polyethylene or polyvinyl chloride, the fire behaviour is entirely different. The pipe melts under the effect of heat, leaving a gaping opening through which hot gases and flames pass from one compartment to the next. The technical solution requires installing a fire-stop collar or an intumescent sleeve fitted with graphite inserts. As soon as the temperature exceeds 150 degrees, the insert expands with sufficient pressure to crush the molten tube and hermetically seal the void created.
| Type of service | Certified device required | Sealing material | Fire behaviour |
|---|---|---|---|
| Copper or steel pipework | Mineral pipe section and intumescent sealant | VKF RF1 rock wool and acrylic | Thermal blocking and smoke tightness |
| Plastic sanitary tubes | Collar or cast-in sleeve | Graphite-based intumescent strip | Mechanical crushing of the softened tube |
| Electrical cable trays | Coated boards or fire-stop bricks | High-density mineral wool and resin | Sealing of gaps between bundled cables |
| Single cables or small sleeves | Fire-stop sealant in cartridge | Intumescent elastomer sealant | Localised volume expansion |
Allocate installation responsibilities, label the work and record the proof
Managing fire-stop penetrations repeatedly causes friction between the CFC 271 plasterer and the electrical, sanitary or heating installers. If the specifications say nothing, each party considers that the closing falls to the neighbouring trade. In French-speaking Switzerland, the usual coordination rule is that the opening is sealed by the company that introduces the service, unless site management has awarded a specific package for cross-cutting fire protection. The plasterer delivers the lining intact, with the framing trimmers needed for the planned openings.
When ducts pass through the partition after the linings have been screwed on and jointed, the building services contractors must install the certified fire-stop sleeves in accordance with the system manufacturer's instructions. If an electrician passes through the plaster without restoring the fire rating, responsibility for the damage to the work lies with him. In the event of a dispute over defects compromising the safety of users, art. 229 CP imposes criminal penalties for the intentional or negligent breach of the recognised rules of construction where danger results.
- Cleaning and checking the annular gapRemove plaster dust and check that the gap between the pipe and the lining complies with the tolerances in the fire protection certificate.
- Installing the non-combustible fillingPack the gap with compressed VKF RF1-classified rock wool, or insert the metal collar fixed to the framing or the boards.
- Applying the sealing jointApply the intumescent sealant, observing the minimum extrusion depth required by the manufacturer, then smooth the surface flush.
- Fixing the identification plateFix the permanent label in the immediate vicinity of the penetration, showing the VKF registration number, the EI class, the date and the name of the company.
For the invoicing of sealing work not included in the initial bill of quantities, the client may exercise its contractual rights in the event of an omission by a subcontractor. In the event of defective execution, the rights relating to construction defects are applied under art. 368 CO to require remedial work at the expense of the defaulting party. Keeping a time-stamped photographic record before the suspended ceilings are closed prevents any undue transfer of financial burden to the drywall contractor.
Carrying out sealing work on lightweight partitions and RF1 materials
Opening a hole in a metal-framed partition immediately changes the mechanical and thermal behaviour of the wall. The drywall plasterer must guarantee the continuity of the linings and of the fire resistance rating prescribed by the Association of Cantonal Fire Insurance Companies. Where building services pass through the partition, the annular gap remaining between the duct or cable tray and the plasterboard cannot be filled with construction site debris or ordinary plaster. The whole space must receive a certified sealing device, laboratory-tested with the specific partition system installed on the construction site.
For combustible plastic pipes, the rise in temperature destroys the synthetic material within minutes and creates a direct draught from one fire compartment to the other. Fitting an intumescent collar or a cast-in sleeve is essential. Under the effect of heat, the intumescent strip expands to several times its original volume to compress and crush the softened tube, hermetically sealing the opening. For non-combustible metal pipework classified under the VKF RF1 directive, the main risk is heat transmission by conduction: the sealing then combines a dense stone wool section classified RF1 with an intumescent or ablative sealant that blocks cold and hot smoke.
| Type of service | Certified device required | Internal packing material | Perimeter finish of the partition |
|---|---|---|---|
| Combustible PVC or PE pipe (sanitary) | Intumescent collar or sleeve with integrated strip | High-density RF1 mineral rock wool | Fire-stop coating or fire-stop acrylic sealant |
| Steel or copper tube (heating) | Insulating sleeve of RF1 rock wool and sealant | Tight packing of high-melting-point rock wool | Fire-stop elastomer sealant on backing rod |
| Cable bundles and cable trays | Coated mineral wool boards or intumescent bricks | Compressed RF1 rock wool at the bottom of the opening | Certified ablative coating covering cables and sections |
Recording unauthorised penetrations, traceability and allocation of additional costs
On a building construction site, the classic conflict arises when the fire-resisting dividing partitions have been accepted as closed, jointed and ready for painting, and other trades then come in to run forgotten ducts. Electricians and sanitary installers then cut through the boards with a hole saw or chisel without warning site management or the plasterer. Each hole instantly degrades the fire certification of the whole wall. The allocation of responsibilities between trades must be locked down in the contract documents from the outset so that the plasterer does not bear the cost of making good.
- Cutting openings and routing the services are the responsibility of the technical trades (electrician, heating installer, plumber) in accordance with the coordination plans.
- Supply and installation of the certified sealing device must be clearly assigned by the tender specification, either to the building services installer concerned or to a company specialised in passive fire protection.
- The drywall plasterer delivers an intact partition fitted with the planned trimmers; he does not close at his own expense an opening drilled after his work.
- Any repair of a lining damaged after the initial closing is an additional service to be ordered by a daywork slip validated by site management.
Proof of conformity rests on the labelling of the penetration and the quality assurance file handed over at acceptance of the work in accordance with standard SIA 118. Each treated penetration receives a permanent identification plate fixed in the immediate vicinity of the sealing. This label states the VKF approval number of the system, the fire resistance rating achieved, the date of installation, the name of the approved installer and the reference of the product used. Without this visible label, the fire protection authority refuses acceptance of the compartmentation.
Dispute management, repair of breaches and administrative regularisation
On a construction site in French-speaking Switzerland, the late discovery of an unsealed or damaged penetration in a compartment partition holds up acceptance of the work. When the building services trades cut through the plasterboard linings after finishing, the integrity of the wall classified under the VKF fire protection directives collapses. The drywall plasterer must never bear the cost of such repairs without a formal instruction from site management.
- Joint inspection record and photographic documentationAs soon as a core hole or unauthorised tear is found, the team records the condition. The foreman photographs the opening, notes the room reference on the compartmentation plan, records the type of service involved and sends a written notice to site management in accordance with the rules of standard SIA 118.
- Validation of the certified sealing deviceSealing must not be improvised with offcuts of mineral wool or standard plaster. The chosen system must correspond strictly to the VKF approval for lightweight partitions: intumescent sleeve for combustible synthetic tubes, rock wool section with RF1 ablative coating for cable bundles, or fire-stop acrylic sealant for metal pipes.
- Reinstating the trimmer and the liningIf the diameter of the penetration exceeds the tolerances in the fire protection certificate, the plasterer opens up the lining, fits an intermediate metal framing trimmer and re-boards with the same type of acoustic or fire-resisting board, respecting the staggering of the joints.
- Installation, labelling of the penetration and traceabilityThe approved installer applies the fire-stop product to the prescribed thickness, then fixes the regulatory label in the immediate vicinity. This plate shows the date, the name of the installer, the product designation and the number of the VKF certificate of conformity, which is essential for the as-built file.
Frequently asked questions
Who must supply and install the fire-stop sealing when sanitary pipes pass through?
The demarcation of services depends on the contract specification according to the construction cost code. By default, the sanitary installer fits the intumescent collars around his combustible pipes because he knows the exact diameter and the thermal behaviour of his tubes. The plasterer, for his part, ensures the adjustment of the plasterboard lining and the framing reinforcement if the opening exceeds the dimensions prescribed by the certified fire-stop system.
Can a cable penetration in a partition be sealed with ordinary plaster mortar?
No. Even if pure plaster behaves favourably in fire in class RF1, an improvised filling has no VKF certificate of conformity for sealing technical penetrations. The cables heat up, the sheathing melts and creates a passage for toxic smoke. Only a certified sealing device comprising high-density mineral wool and an ablative or intumescent paste guarantees the fire resistance of the partition.
What should be done if a fire-stop penetration has no marking label at inspection?
The municipal or cantonal fire protection authority will refuse acceptance of the compartmentation in the absence of visible labelling. The company that carried out the sealing must identify the device installed, supply the manufacturer's declaration of conformity and immediately fix the regulatory label. If the internal composition of the sealing cannot be verified, site management will order the opening to be fully opened up and the penetration completely redone at the expense of the defaulting contractor.
How should a breach made by an electrician after acceptance of the fire-resisting partition be dealt with?
The plasterer immediately reports the damage by a written notice with photographs to site management. The electrician bears the financial responsibility for the damage. To restore the acoustic and fire performance, the plasterer works on the basis of a validated daywork slip: clean opening of the lining, fitting of a metal framing trimmer if necessary, reinstatement of the boards and application of the approved fire-stop sealing system.
Texts and standards cited
- Directives de protection incendie AEAISwiss fire protection regulations on compartmentation, reaction to fire of materials and approval of sealing systems
- norme SIA 118General conditions for the execution of construction work and management of defects in the work