🧱 CFC 271Drywall partitions: framing, linings and performanceChapter 3 of 10 in the section

Wet room: moisture-resistant board, cement board and the limits of each

This chapter details the selection of facings in wet rooms according to their exposure to water. You will be able to distinguish the absorption of humidity from the air from watertightness against liquid water, specify impregnated plasterboard or cement-based boards, and deliver substrates that comply with the finishing work interfaces.

Key takeaways

  • Impregnated board withstands humidity in the air but never forms a waterproof barrier.
  • The SIA 242 standard defines the requirements for facings according to the moisture loads on rooms.
  • Cement board is required in zones exposed to running water and direct splashing.
  • The plasterer delivers a rigid, jointed facing ready to receive the waterproofing beneath tiling.

Distinguishing ambient humidity from liquid water according to SIA 242

On construction sites in French-speaking Switzerland, confusion between resistance to humidity in the air and watertightness against liquid water causes major defects. A moisture-resistant plasterboard, commonly recognisable by its green facing, is treated throughout its core by the addition of silicones or water-repellent agents to limit its water uptake by capillary action. This treatment allows the board to keep its mechanical cohesion and rigidity in air saturated with water vapour. However, the surface paper and the plaster core end up disintegrating if they are in prolonged or repeated contact with running liquid water.

The facings of partitions and ceilings must be selected and dimensioned according to the moisture exposure classes of the rooms and the nature of the subsequent coverings.

norme SIA 242
Moisture exposure classification and choice of facings for interior rooms
Exposure classType of roomMinimum facing permittedProtection required
LowBedrooms, offices, living roomsStandard plasterboardDirect finish without waterproofing
ModerateDomestic kitchens, WCs without showerType H moisture-resistant plasterboardStandard wall covering or tiling
HighPrivate bathrooms, showersReinforced moisture-resistant board or cement boardWaterproofing beneath tiling mandatory
Very highCommunal showers, sports centresCement-based boardWaterproofing system beneath heavy tiling

Managing wet rooms therefore requires mapping the zones. In an individual bathroom, areas outside direct splashing allow an impregnated plasterboard. As soon as you enter the immediate area of the shower tray or bathtub, the facing becomes a mechanical substrate whose durability depends entirely on the water-repellent barrier applied to its front face, or on the rot-proof mineral nature of the board selected.

Choosing between moisture-resistant board and cement board for the tile interface

To choose between a moisture-resistant plasterboard and a cement-based reinforced board, the dry-lining plasterer takes into account the level of water exposure, the dead weight of the planned tiling and the configuration of the metal framing. Cement board contains no paper: made of Portland cement and lightweight aggregates, reinforced on both faces with a glass-fibre mesh, it is completely insensitive to rotting, swelling and deformation under the effect of free water.

Substrate for waterproofing beneath tiling
A flat, non-deforming and clean surface, made of boards or panels fixed to a properly dimensioned framing, intended to receive the liquid waterproofing system applied by the tiler before the ceramic is bonded.
  1. Reduce the spacing of the metal studsIn shower areas or beneath heavy cement boards, reduce the spacing of the vertical CW profiles to forty or three hundred millimetres instead of the usual sixty centimetres to ensure rigidity under load.
  2. Fix the boards with corrosion-resistant fastenersUse only screws treated against oxidation to fix cement boards or impregnated boards, observing a fixing pitch suited to the density of the material.
  3. Treat the joints with compatible componentsUse a tile adhesive or a water-repellent compound combined with an alkali-resistant glass-fibre reinforcing tape, never using a standard plaster smoothing compound in a wet area.
  4. Observe the required clearance above the floorFit the bottom of the facings leaving a clear gap of ten to fifteen millimetres above the raw slab or the screed, thus avoiding any capillary rise during the construction site phases.

Where the work includes very large-format or very thick porcelain stoneware coverings, cement board is required regardless of water, owing to its higher permissible load capacity. In the event of an inconsistency between the architect's plans and the constraints of the covering, art. 365 para. 3 CO requires the contractor to notify the client immediately if a circumstance jeopardises the proper execution of the work.

Physical limits of impregnated board and risks of direct running water

A frequent confusion on construction sites is to regard impregnated plasterboard, recognisable by its green facing, as a waterproof material. This is an error of judgement with serious technical consequences. A moisture-resistant board withstands high, intermittent ambient humidity, typical of a ventilated bathroom. Its plaster core contains silicone additives that reduce capillary absorption. However, this formulation slows the penetration of liquid water without blocking it indefinitely. Subjected to direct water splashing or prolonged standing water, the gypsum absorbs the fluid, loses its mechanical cohesion and swells, causing its facing paper to come away and the partition to sag. In poorly ventilated wet rooms, permanently saturated air prevents the plaster from drying, ruining its residual strength.

The moisture exposure classification governs the dimensioning of lightweight partitions according to SIA 242. In moderately humid rooms, periods of saturation with water vapour must necessarily alternate with complete drying phases ensured by effective ventilation. By contrast, in the direct impact zone of a shower without a raised tray or around a bathtub, splashing onto the walls is direct and repeated. If liquid water passes through the tile joints in the absence of a protective membrane, it seeps into the core of the moisture-resistant plaster. The calcium sulphate dihydrate softens under immersion, promoting mould beneath the covering and compromising the anchorage of tap fittings or glass-screen profiles. This is why SIA 242 recommends, as soon as exposure to liquid water becomes intense or continuous, the use of cement-based boards without paper, completely insensitive to rotting and softening in saturated conditions.

Comparative behaviour of facings according to exposure to humidity and water
Room zoneWater exposureBehaviour of moisture-resistant facingMinimum construction requirement
Outside splash zone (ceiling, distant walls)Intermittent vapour, temporary relative humidityDimensional stability and reduced absorptionSingle or double-layer moisture-resistant board
Moderate splashing (around washbasin)Light water splashes and condensationAdequate resistance beneath washable finishMoisture-resistant board with water-repellent joints
Direct impact (shower or bathtub walls)Daily running water and driving liquid waterRisk of the core becoming soaked and the paper coming awayCement board or moisture-resistant board beneath waterproofing
Very humid rooms (communal showers, saunas)Permanent saturation and high-pressure jet washingUnavoidable degradation of the calcium sulphateCement board in all cases beneath waterproofing

Interface with the tiler: substrate preparation and composite waterproofing

The professional boundary between trades must be scrupulously respected to prevent any insurance dispute. The dry-lining plasterer under CFC 271 erects the framing, fits the moisture-resistant facing or the cement board and carries out the joint treatment. Applying the waterproofing system beneath tiling, comprising the liquid resin, the corner waterproofing tapes and the pipe collars, is exclusively the tiler's responsibility under CFC 282. However, the durability of this waterproof barrier depends on the rigidity and stability of the facing delivered. A partition showing excessive deformation under the load of large-format tiling will cause the liquid membrane to rupture and internal leaks. The tiler's acceptance of the substrate before applying the liquid membrane formally marks the transfer of responsibility for the flatness and cleanliness of the surface.

  1. Reduce the pitch of the metal framingIn areas to be tiled, reduce the spacing of the framing studs to 400 mm or fit a double crossed facing in order to limit the bending of the wall under the weight of the ceramic covering.
  2. Treat the joints with a water-repellent compoundApply a jointing compound expressly resistant to humidity, reinforced with a suitable tape, to prevent any premature degradation of the binder under the residual moisture of the tile adhesive.
  3. Provide a clearance above the floor at the foot of the facingStop the moisture-resistant boards or cement boards approximately 10 mm above the raw floor to avoid any capillary wicking of water during the construction site phases or when screeds are poured.
  4. Adjust the plumbing penetrationsMake the pipe penetrations with a suitable hole saw, keeping a regular circular clearance of 5 to 10 mm, without chipping, to allow the tiler to fit the collars watertight.

Water-ingress damage in a wet room: remedial protocol and demarcation of responsibilities

The discovery of a leak behind shower tiling requires an immediate halt to all water loads. The degradation of the impregnated plasterboard shows itself quickly through swelling of the facing, tiles coming away or efflorescence appearing on the opposite face of the partition. Faced with this defect, the dry-lining plasterer must recall the basic principle set out in SIA 242: the moisture-resistant facing slows water uptake by capillary action in a saturated atmosphere, but in no case does it constitute a waterproof barrier against liquid water under pressure or running.

  1. Opening up and joint inspection recordRemove the sanitary fittings and the damaged tiling. Call in the site management and the tiler to record the condition of the liquid waterproofing beneath tiling, the absence of waterproofing collars at pipe penetrations or the lack of a perimeter upturn.
  2. Complete removal of the affected facingCut out the damaged plaster facing until a sound area is reached, extending at least 20 centimetres beyond the traces of moisture. Any impregnated board that has been subjected to prolonged immersion must be sent to disposal.
  3. Checking the framing and drying outCheck the state of corrosion of the galvanised metal profiles. Replace the soaked internal insulation and keep dehumidifiers running until an acceptable residual moisture content is reached in the technical cavity.
  4. Rebuilding suited to the exposure classificationClose up the wall by adapting the type of board. If the area remains exposed to severe splashing or to walk-in showers without a tray, replace the impregnated plaster with a rot-proof cement board reinforced with mineral fibres.

The new substrate is accepted in writing. The dry-lining contractor delivers a flat, stable and dust-free surface that meets the tolerances of SIA 242. From that moment, the application of the mat or the waterproofing system beneath tiling, as well as the flexible treatment of partition penetrations, is strictly the responsibility of the tile installer.

Frequently asked questions

Can tiles be laid directly on a moisture-resistant board without liquid waterproofing?

No, this is not permitted in the direct splash zones defined by SIA 242, such as around a bathtub or inside a shower enclosure. Mortar joints remain porous and let moisture through by capillary action. Without waterproofing beneath tiling applied by the tiler, water soaks the facing paper and breaks down the gypsum core within a few months.

Why prefer cement board to moisture-resistant board for a walk-in shower?

Moisture-resistant board contains silicone additives that limit absorption of ambient water, but its core remains plaster, which is sensitive to prolonged contact with water. Cement-based board is entirely inorganic and rot-proof. Even in the event of a localised failure of the tiling or accidental water ingress, the cement board keeps its full mechanical strength and does not grow mould.

How should the cut edges of a moisture-resistant board be treated on the construction site?

When cutting, the plaster core is left exposed and loses the relative protection provided by its paper surfacing. In wet rooms, the cut edges should be chamfered and a coat of bonding or waterproofing primer applied before finishing with a suitable water-repellent jointing compound, keeping the clearance above the floor.

Who is responsible for fitting the waterproofing collars at the sanitary water outlets?

The plasterer is responsible only for neatly cutting the opening around the pipes with minimal fitting clearance. Supplying and bonding the watertight elastomer collars, and embedding them in the composite waterproofing system beneath tiling, are the tiler's responsibility before the tiles are bonded, in accordance with the professional rules for interior waterproofing.

Texts and standards cited

  • SIA 242Plastering, rendering, dry lining: requirements for substrates, flatness tolerances and classification of rooms according to their exposure to humidity.