Skip to content
Website
🧱 CFC 271Section 4 of 610 chapters

Surface quality grades and tolerances: the execution reference

This section sets out the execution and inspection rules applicable to plastering and lightweight partition surfaces under SIA 242. It gives team leaders, foremen and site managers the precise methods to classify facings from Q1 to Q4, measure flatness under the straightedge, check plumb and squareness, and manage the interfaces with the painter. You will know how to refuse requirements that were not agreed and secure the acceptance of the work.

  • 10chapters
  • 22 000words
  • 6sections in the training course
  • 60chapters in total

Key values to remember 4

norme SIA 242

5 mm

Maximum deflection permitted under the 2 m straightedge for a standard Q2 surface

norme SIA 242

3 mm

Maximum permissible deflection under the 2 m straightedge for a careful Q3 surface

norme SIA 242

1 m 50

Minimum perpendicular viewing distance for the visual inspection of facings

art. 367 CO

60 days

Statutory deadline for the notice of defects for a building work after inspection

Technical scope, finish grades and boundaries of responsibility

Defining the finish level of an interior surface is the main source of disputes between consultants, painters and plastering contractors. SIA 242 strictly governs the geometric and visual characteristics that can be required under four execution grades: Q1, Q2, Q3 and Q4. The aim of this section is to equip site managers and foremen in French-speaking Switzerland to set the quality grades contractually from the tender stage, check tolerances on the construction site with calibrated tools, and enforce the physical limits of the materials against disproportionate aesthetic expectations.

Delimitation of plastering services and interfaces with adjacent trades
Area of workCFC 271 services includedService limits and interfaces
Plasterboard facingsMetal frameworks, linings, partition walls, suspended ceilings, jointing according to grades Q1 to Q4.Raw concrete and masonry (CFC 201/211.1), specific reinforcement for heavy loads not defined in the contract.
Applied plasters and rendersBonding scratch coats on admissible substrates, smooth or felted plasters, metal or PVC stop beads.External thermal insulation (CFC 221), self-levelling floor screeds and liquid screeds (CFC 281).
Primers and final finishSanding of jointing compounds, skim-coat surfacing linked to grade Q4 where expressly specified.Base coat, pigmented absorption-regulating primer, finishing paint, wallpapers (CFC 272).
Built-in elementsGeometric openings, profiled frames, fire-stopping or acoustic sealing of penetrations.Routing of ducts, wiring, electrical boxes (CFC 232), sanitary pipework (CFC 250), doors (CFC 273).

The operational boundary with the painter's trade (CFC 272) requires a clear demarcation: the dry-lining plasterer guarantees a surface that complies with the agreed grade under natural diffuse lighting. He does not deliver a continuous closed film free of micro-porosity if a full Q4 skim coat has not been paid for. Likewise, the structural stability of the substrate depends on the rigidity of the structural work; excessive deformation of concrete slabs or deflection of load-bearing elements is not part of the plastering package.

Organisation of the chapters and professional reading strategy

The ten chapters follow the logical cycle of a project, from the initial offer to the final settlement of technical reservations. This structure lets the foreman anticipate disputes during partition erection, and lets the project manager build his defence at site meetings against unjustified demands from the site management.

  1. Phase 1: Define and measure the geometric requirements (N4-01 to N4-04)The first four chapters break down the technical content of grades Q1 to Q4 and set the inspection protocol. They cover the measuring method under the two-metre straightedge with a tapered gauge, the pitfall of artificial raking light, which is not admissible for judging work, and the plumb and squareness tolerances required by SIA 242.
  2. Phase 2: Secure acceptance and handle defects (N4-05 to N4-06)Chapters five and six deal with the joint inspection before the secondary trades intervene. Under art. 367 CO, the client must promptly report the defects found. The site manager learns to distinguish hygrometric shrinkage microcracks inherent to drying from structural defects resulting from faulty installation.
  3. Phase 3: Manage interfaces, the offer and repairs (N4-07 to N4-10)The last four chapters clarify the limits between the plasterer's skim coat and the painter's priming, the mandatory production of a reference sample validated on site, the contractual wording of an unambiguous offer, and the technical choice between a local repair and a complete skim coat under art. 370 CO governing acceptance of the work.

Rigorous application of these ten modules protects the profitability of your construction sites. Each party thus has the normative arguments to refuse services that were not ordered, justify its formal notices and deliver work that complies with the rules of Swiss building practice.

📘 Chapters in this section 10

Surface quality levels and tolerances

Q1 to Q4: what each grade really covers, and what it does not promise

Distinguish the real requirements of each level so you can refuse plastering services not provided for in the original quote.

Surface quality levels and tolerances

Measuring flatness: two-metre straightedge, gauge wedge and tolerance by grade

Apply the official method under the two-metre straightedge to validate flatness beyond dispute.

Surface quality levels and tolerances

Raking light: what it reveals, what it does not prove, and the finish level to specify

Show why the use of a raking floodlight is not a contractual method for inspecting finishes.

Surface quality levels and tolerances

Plumb and squareness: tolerances, accumulation of deviations and consequences for the following trades

Check vertical and corner deviations to ensure joinery and adjoining partitions are fitted perfectly.

Surface quality levels and tolerances

Accepting the plasterwork: joint inspection record, useful reservations and rectification deadline

Draw up the joint inspection report with precise reservations to block abusive end-of-construction-site claims.

Surface quality levels and tolerances

Crack after acceptance: normal shrinkage, workmanship defect and warranty

Demonstrate the structural origin of cracks caused by the structural work to safely clear your craftsman's warranty.

Surface quality levels and tolerances

Coordinating plasterer and painter: required grade, painter's primer and who skims what

Define precisely who bears the cost of the skim coat, plasterer or painter, before the priming coat is applied.

Surface quality levels and tolerances

The reference sample: a validated control area, and what it settles

Have a representative reference sample signed off to fix definitively the aesthetic result expected by the general management.

Surface quality levels and tolerances

Writing the grade into the tender: wording, priced option and refusal of implicit standards

Include precise contractual wording in your offers so that each upgrade in surface grade is priced properly.

Surface quality levels and tolerances

Partial or full rework: what shows afterwards, and how to decide

Decide between local touch-up and complete renewal of a panel to preserve visual uniformity without excessive extra cost.