Key takeaways
- A joint visual and photographic inspection record made before work starts blocks unfounded claims about existing finishes.
- Airtight containment using thick polyethylene and telescopic props separates the work zone from the occupied rooms.
- A mechanical air extractor keeps the polluted room under continuous negative pressure relative to the living areas.
- A technical vacuum cleaner with suitable filtration and daily wet cleaning eliminate any transfer to the common areas.
Drawing up a joint condition survey and installing airtight containment
Gypsum dust produced by cutting plasterboard or sanding plaster coats is extremely fine and infiltrates the smallest gaps. In an occupied building, the plasterer faces immediate complaints if dirt or surface damage is found in the adjoining rooms. Legal protection on the construction site starts with a rigorous initial survey before any tool is brought in.
- Drawing up the initial joint inspection recordInspect the entire dwelling together with the client or the property management company. Take detailed photographs of the floor coverings, door bottoms, wall corners and glazing located along the access route and around the construction site. Record in writing every scratch, stain or chip already present on a dated document signed by both parties.
- Fully protecting the circulation floorRoll out an absorbent non-woven membrane lined with a waterproof polyethylene film from the landing threshold to the entrance of the work zone. Fix the strips with cloth-backed bridging tape, covering the skirting boards by five centimetres to prevent dust from slipping under the protection.
- Erecting the frame of the mobile partitioningDeploy spring-loaded telescopic props fitted with non-marking rubber pads against the floor slabs and ceilings. Space the uprights about one metre twenty apart to ensure the stability of the structure against the air pressure variations created by windows or ventilation.
- Stretching and sealing the containment filmFix a reinforced translucent polyethylene film at least one hundred and fifty micrometres thick onto the props. Fold the film back by ten centimetres at the floor and ceiling, then seal the whole perimeter with technical adhesive tape ensuring continuous contact without air pockets.
The temporary partitioning must form a physical barrier that is one hundred per cent airtight. Technical pipe penetrations, hot-air distribution grilles and the undersides of interior doors that are not included in the construction site footprint must be sealed under airtight plastic before any demolition of light partitions or mechanical sanding is started.
Putting the zone under negative pressure, managing the airlock and carrying out daily cleaning
To protect workers' health and limit exposure to fine particles, art. 33 OTConst requires that hazardous substances be removed to the open air, filtered or diluted by artificial ventilation. For its part, art. 82 LAA requires the employer to take all measures that experience has shown to be necessary and that the state of the art allows to be applied. Negative air pressure combined with an access airlock is the reference technique for containing dust.
- Building a double-barrier access airlockCreate an intermediate transition space at least one metre fifty deep between the living area and the area under work. Fit both walls of the airlock with a reinforced adhesive zip fastener or a central magnetic strip ensuring automatic closing after each passage.
- Installing the negative-pressure unitPosition an air scrubber fitted with a pre-filter for plaster dust and a high-efficiency final filter. Connect a flexible duct to an airtight blanking panel fitted to a window left slightly open, facing the outside of the building.
- Balancing the pressure gradientAdjust the extraction rate so that the polyethylene of the airlock visibly bulges inwards towards the work zone. This continuous inflow of air physically prevents any airborne particle from passing through the openings and migrating to the occupied part of the flat.
- Setting up the decontamination stationPlace a multilayer adhesive mat with peel-off sheets on the airlock floor to capture dust from under shoes. Provide in this space for taking off disposable work overalls and storing respiratory masks before passing through the second door.
| Equipment | Main function | Maintenance protocol |
|---|---|---|
| Air scrubber with final filtration | Maintaining negative pressure and discharging cleaned air | Daily check of the pressure gauge and pre-filter |
| Flexible airlock with magnetic closure | Airflow break between two zones | Wet cleaning of the sheeting at the end of the day |
| Peel-off adhesive mat | Mechanical retention under safety footwear | Removal of the saturated sheet at midday each day |
| Construction site vacuum cleaner with fine filtration | Immediate capture on the floor and at the machines | Regular filter cleaning and airtight bagging |
Dry sweeping is prohibited on an occupied construction site: it stirs up the very fine particles, which settle on the containment walls and escape at the slightest opening of the airlock. The team cleans the dust with a technical vacuum cleaner fitted with sealed disposal bags, followed by wet mopping of the circulation route at the end of each shift.
Movement of materials and removal of waste without breaking the seal
The classic mistake in occupied renovation is to build a flawlessly airtight partitioning at installation, only to degrade it from the very first rotation of rubble removal or plasterboard supply. Every opening of a door or zip fastener causes an immediate air transfer if the flow is not locked. When materials pass through the protected private areas or the common parts of the building, the team leader applies a bagging and packaging protocol directly at the working face, before anything crosses the airlock.
Offcuts of cardboard-faced plasterboard, cut metal tracks and plaster coat debris must be removed in thick polyethylene bags sealed airtight with adhesive tape inside the containment zone itself. The bags must not show any powdery residue on their outer faces: wiping with a damp sponge or cleaning with an industrial vacuum cleaner fitted with a fine-dust filter is required in the first chamber of the airlock before passing into the clean zone.
| Type of flow | Required packaging | Procedure in the airlock | Destination and protection |
|---|---|---|---|
| Gypsum rubble and waste | Sealed bags of max. 25 kg, closed with cloth-backed adhesive tape | External dust removal of the bag, check that it is not punctured | Soft-wheeled trolley on a protected runway to the outdoor container |
| Supply (profiles, plasterboard) | Factory packaging or partial unpacking in a neutral zone | Direct transit with the airlock open as little as possible, negative pressure maintained at the higher setting | Immediate buffer storage inside the airtight compartment |
| Plastering personnel | Dedicated work overalls or disposable overshoes | Brushing of soles on a sticky mat, removal of overshoes in the intermediate airlock | Direct access to common circulation areas without transferring dust under the soles |
| Portable power tools | Machines disconnected, housings cleaned with a damp cloth | Vacuuming of the motor ventilation fins and packing in a closed crate | Storage in the vehicle or workshop without dispersal in the access areas |
Decontainment protocol, withdrawal and closing record
Lifting the containment is the most critical phase from a legal and relational point of view. A company that has perfectly contained sanding dust for two weeks can ruin its work by abruptly dismantling the temporary walls. If a cloud of dust escapes when the polythene sheeting is taken down, the plasterer is liable for the soiling caused to furniture or adjacent coverings. Decontainment follows a methodical sequence that begins with complete clarification of the ambient air.
- Final air purgeOnce the sanding and smoothing work is finished, the air scrubber with final filtration is kept running continuously for at least two hours. The vertical and horizontal surfaces are vacuumed with a class M (minimum) appliance fitted with automatic filter cleaning.
- Wet dust removal of the airlock and containment wallsThe polyethylene films, telescopic uprights and zip fasteners are washed with damp sponges and microfibre cloths to trap the residual particles that cling to the plastics through static electricity.
- Rolling up the sheeting inwardsThe holding adhesives are removed gently so as not to tear off the paints or varnishes of the retained substrates. The plastic films are folded and rolled onto themselves, dusty side facing inwards, then immediately tied and placed in sealed bags.
- Final vacuuming of the floors and removal of the walkway protectionThe absorbent felt or rigid protection boards laid on the floor of the occupied flat are vacuumed one last time before removal, from the inside of the room towards the landing door, without creating air turbulence.
As soon as dismantling is complete, the foreman or site manager invites the client, their representative or the tenant to draw up the joint inspection record at the end of the construction site. This document follows the entry condition survey point by point. It systematically checks for the absence of dust in wardrobe tracks, on skirting board grooves, along door frames and on household or electronic appliances located around the work area.
Managing dust incidents and settling disputes in occupied buildings
In the renovation of an occupied flat, the slightest leak of fine dust from sanding plasterboard or opening dry partitions triggers an immediate crisis with the occupant. As soon as a white deposit appears outside the contained perimeter, or on a complaint from the client, the team leader suspends the dust-emitting operations. The priority is to contain the incident before any discussion of responsibility. Continuing to sand on the pretext of finishing the pass permanently damages relations on the construction site and exposes the company to costly repairs to furniture or hangings.
- Freezing dusty activities and locating the breachStop the machines and long-reach sanders. Carefully inspect the temporary polythene, the adhesive-tape joints on skirting boards or mouldings, the technical shafts passing through and the pressure flap of the access airlock to identify the tear or detachment.
- Restoring the seal and checking the negative pressureApply new adhesive tape over the faulty joint. Check the operation of the construction site air extractor and how clogged its pre-filter is. The negative pressure must keep the plastic film taut towards the inside of the work zone.
- Carrying out corrective cleaning outside the zoneVacuum the soiled areas with an industrial fine-dust vacuum cleaner fitted with an absolute filter cartridge. Avoid dry sweeping at all costs, as it puts fine particles back into suspension in the living rooms.
Once the incident is under control, the site manager arranges a joint inspection with the occupant to record the restoration of the surrounding areas. The incident and the corrective cleaning are recorded in writing. This habit protects the plasterer against unjustified deductions at the final account and allows plaster coat application to resume in a calm atmosphere.
Frequently asked questions
How should one react if the resident finds fine dust in their living room next to the airlock?
The team leader suspends sanding and goes to the spot with the occupant. He examines the airtightness of the airlock and the adhesive fixing the film to the floor. The company carefully cleans the surfaces with a vacuum cleaner fitted with absolute filtration, then wipes with a damp microfibre cloth. The event is recorded in the construction site log, with the corrective measures taken, before any resumption of plaster coats.
What air flow rate should be chosen for the extractor that puts an occupied room under negative pressure?
For a closed room of ordinary size, the extractor must renew the volume of the work zone at least six to eight times per hour. This flow rate ensures that outside air is drawn into the construction site when the airlock is opened, preventing particles from escaping. The stale air flow is discharged outside or filtered by equipment suited to fine mineral dust before release.
What should be done if the tenant or the client refuses to sign the initial condition survey?
If signature is refused, the site manager draws up a very detailed unilateral record. He takes dated close-up photographs of the parquet floors, skirting boards, glazing and adjoining furniture. This bailiff's report or complete photographic file is sent to the client's representative in a traceable written form before the partitions are erected and dust-emitting operations begin.
Can a plaster coat be sanded by hand in an occupied building without installing an extractor?
Manual sanding produces plaster microparticles that stay in suspension for several hours. In an occupied building, working without an extractor is not recommended because repeated passages through the airlock inevitably push dusty air into the clean rooms. Even for local finishing, the plasterer must use a vacuum sanding block connected to a sealed vacuum cleaner or a mobile dust extractor fitted with a high-efficiency filter cartridge.
Texts and standards cited
- norme SIA 118General conditions for the execution of construction work