🧱 CFC 411Surface water: slope, drainage and infiltrationChapter 10 of 10 in the section

Water test: surface watering, recorded puddles and report

This guide details the implementation of the water test on external surfacings prior to acceptance of the work operations. You will learn how to organise the hose test, precisely measure the depth and extent of retentions according to SIA 318 standard, and then jointly record these findings in a report to avoid any subsequent disputes with the client.

Key takeaways

  • The preliminary water test simulates driving rain and immediately reveals surface fall defects.
  • The SIA 318 standard defines the permissible flatness and water retention tolerances for external works.
  • Rigorous marking with wax chalk delineates the exact footprint and water depth of each puddle.
  • The jointly signed report on site seals the findings before formal notification of completion of works.

Organise test watering to simulate actual runoff

Waiting for the first autumn storm to check the proper drainage of paving or flagging poses a major contractual risk. The client will discover the residual puddles before you and raise immediate reservations. Methodical watering carried out as soon as the bedding layer is finished and the joints are sanded makes it possible to visualise the runoff kinematics in ten minutes and spot counter-falls invisible to the naked eye.

  1. Surface preparation and site access safetyThoroughly clean the surfacing with a broom to remove any gravel residue or excess jointing sand. Check that the connected drainage gullies and channel slots are clean to prevent any premature clogging during the test.
  2. Pressurisation and sustained wateringDeploy a construction site hose of at least 19 mm internal diameter connected to the site water network or a water bowser. Water generously, sweeping the surface from upstream to downstream with a lance adjusted to a dense spray for about fifteen minutes to saturate the facing.
  3. Observation of water trickle trajectoriesVisually monitor the path of the water sheet. The water must converge homogeneously towards the drainage slots, swales or soakaways without overflowing onto building facades or crossing external door thresholds.
  4. Waiting and gravity drainage phaseTurn off the water supply and time how long it takes for the surface film to disappear. Depending on weather conditions and wind, the running water must have left the surfacing in less than fifteen minutes, leaving only the natural damp adhesion film.

This water test does not replace the hydraulic sizing calculation for collectors, but it definitively sanctions the geometric execution compliance. When the untreated granular sub-base or the bedding layer has undergone localized differential settlement under the passage of the vibrating plate, the behavior of the water immediately reflects this defect through the formation of a basin.

Map retentions and record the joint report

Fifteen minutes after stopping the lance, the moving water has completely drained away. Areas where water still stagnates constitute potential retentions that must be rigorously characterised. Not all puddles necessarily constitute a defect within the meaning of trade standards; the analysis depends on their maximum depth, surface area and location within the landscaping.

Classification and admissibility of stagnation according to SIA 318 standard
Type of stagnationGeometric criteriaFunctional impactRequired corrective measure
Superficial water filmDepth less than 2 mmResidual moisture without standing water depthTolerated without repair
Tolerated local puddleDepth of 2 to 4 mm, reduced surface areaRapid evaporation, no pedestrian inconvenienceObservation without intervention
Excessive puddleDepth greater than 4 mmRisk of black ice and splashingRelaying of pavers and bedding layer
Counter-fall towards thresholdEven minimal, runoff towards the buildingRisk of infiltration through low thresholdsImmediate dismantling and fall readjustment

The foreman traces the outline of each residual puddle with wax chalk directly onto the dry or damp paving. A 2-metre aluminium straightedge placed diagonally and across the puddle is used to check the hollow under the straightedge, while a metal ruler measures the water depth at the lowest point. These measurements are transferred to the site setting-out plan.

Having a validated watering report before the official acceptance meeting cuts short subjective claims made under a rainy sky. If localized repair proves essential, lifting a few square metres of interlocking pavers or flags on a gravel bed is easily carried out before the site is fully demobilised, ensuring a clean delivery without reservations.

Diagnosis of drainage anomalies and technical surface repair

Test watering immediately visualises the runoff kinematics and detects parasitic low points before the client arrives. When water stagnates instead of flowing towards channel slots, infiltration swales or gullies, the defect generally stems from an irregularity in setting the laying course or localized settlement of the granular infrastructure. The mapping established during the test dictates targeted interventions that avoid rebuilding the entire platform.

Hydraulic anomalies identified during the hose test and rectification procedures
Finding during jet testFrequent construction originLandscaping corrective measure
Basin with persistent puddle in the middle of a paved areaDifferential overcompaction or bedding layer washed away by finesRemove elements, scrape off contaminated 2/4 gravel, refill with clean crushed material, re-level and compact with a plate fitted with a polyurethane pad.
Water backflow around a slotted channel or gullyTop of grate set higher than the surfacing edgeRemove kerbs or edge flags, saw the concrete haunching if necessary, relay with a clear 5 mm step below the metal edge.
Water migration towards the foot of a low retaining wallAccidental counter-fall created during grading of the foundation layerDismantle the hollow area, reprofile the 0/32 frost-free aggregate with an inverted fall of at least 2 %, relay the permeable bedding layer.
Prolonged stagnation in the joints of a pedestal-mounted flaggingInsufficient fall of the sub-base prepared beneath the pedestalsLift the flags, micrometrically readjust the self-levelling pedestal heads to redirect the general water flow towards the natural outlet.

Repairing concrete paving or natural stone requires delineating a clear geometric surface around the depression, never working on a single isolated element. The team removes the pavers until a stable area is found, extracts the degraded bedding sand, and adjusts the crushed gravel layer with a straightedge. Laying is always done with a slight surplus height of about three to five millimetres to anticipate final compaction with the vibrating plate. Sweeping with dry, clean jointing sand locks the repaired panel before the second water test.

Joint report, acceptance criteria and final re-test

Holding a joint meeting between the landscaping site manager and the site management concludes the hydraulic verification of the landscaping. All findings from the watering are reported on the execution plan: compliant surfaces with continuous flow, identified stagnant water points with their floor measurements, and the deadline set for remediation. This jointly signed document serves as a technical condition report and protects the company against late claims regarding the normal use of the pavement.

  1. Recording hydraulic reservations in the reportPrecisely record the topographical location of disputed areas, dimensions measured with a tape measure of puddles exceeding tolerances, and the deadline set for the team's corrective work.
  2. Execution of rectifications by the laying teamCarry out dismantling, foundation fall readjustment and replacement of degraded elements in accordance with technical requirements, under the supervision of the foreman.
  3. Joint watering re-testCarry out a new targeted watering test with the garden hose on the repaired sectors, in the presence of the site management representative, to validate the absence of any residual low point.
  4. Signing of the snag removal certificateDraw up an addendum to the report confirming the correct hydraulic functioning of all external surfacings, an essential condition for recording formal acceptance of the landscaped work.

This rigorous self-control before handing over the work turns a potential client complaint into a demonstration of quality assurance. By documenting the effectiveness of falls and the responsiveness of repairs in writing, the landscaping company delivers a stable, durably draining platform that fully complies with the construction contract.

Management of drainage non-conformities and disputes before acceptance

When the test watering reveals stagnant water retentions exceeding the geometric tolerances of the SIA 318 standard, or if the site management refuses to sign the joint report, the site manager must neutralise the dispute through methodology. The precise purpose of the hose test is to identify basins before the client moves in. Discovering a puddle during an internal check avoids work rejection or financial retention at final delivery according to the Code of Obligations.

  1. Qualify the geometric defect with a straightedgeMeasure the puddle using a four-metre straightedge and a metal ruler. Record the maximum hollow under the straightedge and the thickness of the water film after waiting fifteen minutes. If the puddle exceeds the tolerances permitted for external surfacings by the SIA 318 standard, record the exact value in the report without subjective qualification.
  2. Map and document jointlyTrace the exact outline of the retention with grease pencil or site chalk on the still damp pavers. Take overall and detailed photographs including an open folding rule for scale. Plot the area on the setting-out plan, specifying the planned fall direction and the position of kerbs.
  3. Diagnose the structure without blind demolitionCheck whether the defect stems from a localized dip on the bedding layer, a kerb misalignment acting as a dam, or settlement of the foundation layer. Remove a few pavers at the low point to inspect the thickness of the sand or gravel bed and the behaviour of the unbound aggregate.
  4. Record corrective measures and repeat the testDefine the repair: partial removal, adjustment of the bedding layer, correction of the fall towards the drainage or infiltration point, then tamping. Record in the joint report the date set for the water re-test, performed under the same flow conditions to validate the conformity of the work.

Frequently asked questions

How long should one wait after test watering to map puddles?

Wait fifteen to twenty minutes after stopping the watering. This delay allows complete surface runoff towards kerbs and channels or the start of infiltration through the joints. Water still present after this period forms a measurable real retention. Rushing the mapping while water is still flowing would distort the survey by confusing the dynamic flow sheet with a residual basin.

Does the SIA 318 standard allow the presence of residual water on external paving?

The SIA 318 standard tolerates temporary surface moisture or minimal water films caused by the inherent roughness of pavers and flags. On the other hand, it excludes the formation of continuous stagnant water pockets resulting from counter-falls or localized settlements under the straightedge. Persistent water retentions that exceed flatness tolerances constitute an execution defect that the company must correct.

What to do if the water puddle is caused by a kerb level imposed by the plans?

If the installed kerb scrupulously respects the design level but retains water by creating a dam, immediately notify site management in writing. According to the Code of Obligations, the contractor has a duty to notify in the event of defective design. Propose a technical solution in the report: drainage core drilling, sawing a discreet notch or local readjustment of the cross profile.

How to record the water re-test after local paving repair?

The re-test is carried out using the same hose watering protocol as the initial test, in the presence of the same parties. Draw up an addendum to the original joint report mentioning the corrected area, the disappearance of the basin and proper drainage towards the outlets. Joint signature of this act definitively closes the technical reservation before final acceptance of the work.

Texts and standards cited

  • SIA 118General conditions for the execution of construction works
  • SIA 318External works