Skip to content
Website
🧱 CFC 411Surface water: slope, drainage and infiltrationChapter 1 of 10 in the section

Fall: minimum away from facades, reverse fall and water at the base of the wall

This chapter gives you the leveling rules and control methods to guarantee the gravity drainage of surface water away from buildings. You will learn to set the minimum falls according to the surfacings, to set your altimetric reference points in relation to the facade plinths and to definitively check your foundation layers to prevent any stagnation at the base of the masonry.

Key takeaways

  • Standard SIA 318 prescribes a minimum drainage fall directed towards the outside of the building.
  • A reverse fall of two centimetres is enough to saturate the base of facades during rainy weather.
  • External paved or slabbed surfaces require a minimum fall of one point five per cent.
  • Systematic laser altimetric control eliminates the risks of differential settlement near the plinths.

Impose a continuous fall outwards from the setting out of levels

On an external works construction site, surface runoff management must strictly start against the building wall. Any waterproof or semi-permeable surface laid on the natural ground must discharge precipitation towards the outside of the plot or towards a landscaped infiltration structure. The minimum drainage fall constitutes the first line of defence against surface infiltration along emergent structures. According to standard SIA 318 governing external installations, a vehicular or pedestrian surface must never present a fall lower than a critical threshold that guarantees clear runoff, even in the presence of surface irregularities or slight joint clogging.

Recommended minimum drainage falls according to standard SIA 318 for external works
External surfacing (CFC 411)Minimum cross fallMinimum longitudinal fallSurface hydraulic behavior
Natural stone or concrete slab paving on gravel bed2.0 % (2 cm per metre)1.5 % (1.5 cm per metre)Rapid drainage, limitation of residual water film
Concrete or terracotta paving with sand joints2.5 % (2.5 cm per metre)2.0 % (2 cm per metre)Compensation for slight surface irregularities
Continuous bituminous surfacing in private roads2.0 % (2 cm per metre)1.5 % (1.5 cm per metre)Direct runoff without surface retention
Grass surfaces and planted beds3.0 % (3 cm per metre)2.0 % (2 cm per metre)Drainage towards low areas without scouring

The direction of the fall away from the facades must be set out from the general earthworks stage. The foundation platform must itself reproduce this inclination outwards. Too often, the mistake consists in setting the fall only on the laying bed or the finishing surfacing. If the untreated granular foundation layer remains horizontal or slopes towards the wall, water infiltrates through the paving joints, stagnates on the formation level and migrates by capillarity towards the foundation footing. Leveling must therefore be strictly parallel from the bottom of the excavation to the wearing surface.

Track down reverse falls and eliminate retention areas against facades

A reverse fall of two centimetres over the first few meters is enough to create a depression invisible to the naked eye when laying in dry weather. As soon as storm rains arrive, this deformation brings dozens of liters of water directly against the bottom of the wall. This phenomenon of reverse fall and stagnation at the base of the wall causes severe damage: rapid biological fouling, blackening of renders, detachment of plinth paints under the action of freeze-thaw cycles, and formation of dangerous black ice patches for pedestrians along access walkways.

  1. Setting out of altimetric reference pointsPosition leveling staffs or rotating laser rods against the facade and at a distance of three meters outwards, immediately integrating a drop of at least six centimetres to respect the two percent gradient.
  2. Enhanced compaction of the residual excavation zoneCompact the untreated aggregate by cross-passes with the vibrating plate along the facade, an area particularly prone to subsequent settlement if the underlying backfill has not been properly compacted.
  3. Check using the three-metre straightedgePlace an aluminum builder's straightedge perpendicular to the facade, topped with a spirit level, to detect any hollow or dip greater than five millimeters before spreading the laying bed.
  4. Check after compacting the pavingAfter final compaction of the pavers with an elastomer pad, check again for the absence of dips at the base of the building using a trial watering test if the weather is dry.

The connection between the landscaped surfacing and the plinth also requires meticulous treatment of kerbs or clean gravel strips. If a peripheral pebble band is implemented to cushion splashes, the bottom of this channel must also be excavated with a sloping cross fall. Under no circumstances should this zone form a permeable ditch trapping runoff water against the wall. Laying teams must scrupulously respect the execution tolerances of standard SIA 318, as a localized subsidence of a few millimeters on a surface that is insufficiently inclined reverses the direction of gravity drainage.

Permissible minimum falls according to surfacings (standard SIA 318)

Runoff water tolerates no altimetric defect on a private road or external terrace. To guarantee its continuous drainage towards permeable areas or infiltration structures on the plot, without risk of accumulation against the structural work, the minimum drainage fall must take into account surface roughness, joint width and the chosen laying method. Standard SIA 318 defines the geometric requirements and tolerances applicable to external works. A smooth and closed surface such as bituminous asphalt allows continuous drainage from 1.5 % transverse gradient onwards. Conversely, slab paving or block paving on a gravel bed requires a minimum fall of 2.0 % to 2.5 % to overcome the hydraulic resistance of the chamfered edges and compensate for dimensional variations of prefabricated elements.

Vegetated surfaces and grassed areas arranged in the immediate vicinity of a building obey specific physical constraints. The initial loosening of topsoil and its consolidation under the effect of precipitation frequently generate delayed surface subsidences. If the initial fall is too weak, these settlements reverse the drainage line and guide water towards the facades. On topsoil and stabilized gravel, an outward fall of at least 2.5 % to 3.0 % proves essential to prevent any stagnant water retention.

Minimum drainage fall values according to the nature of the surfacing (standard SIA 318)
Nature of surfacingMinimum fallEvenness toleranceBehavior of the running water line
Hot-rolled asphalt concrete1.5 %± 5 mm under 4 m straightedgeContinuous laminar drainage without retention zone.
Concrete slabs on gravel bed2.0 %± 5 mm under 2 m straightedgeSensitive to uneven joints; smooth drainage required.
Interlocking concrete pavers2.5 %± 6 mm under 2 m straightedgeJoints and chamfers slowing down water at low gradient.
Split natural stone paving3.0 %± 8 mm under 2 m straightedgeHigh surface roughness slowing down runoff.
Grass surfaces and planted beds3.0 %± 20 mm under stringPost-planting settlement requiring a marked fall.

Prevention of reverse falls and control of settlements at the base of the wall

The major risk of water accumulation along masonry plinths lies in the differential settlement of excavation backfills. Around the foundations of a building, excavated and then backfilled ground presents unstable and heterogeneous bearing capacity if it has not been subjected to methodical compaction in successive layers. When a terrace, an access path or a paved courtyard overlaps this zone of loose backfill and stabilized natural ground, the progressive consolidation of the earth creates a longitudinal depression. A reverse fall of two centimetres over three meters of width is enough to reverse all rainwater drainage: runoff water no longer flows outwards but converges directly at the base of the facade.

  1. Altimetric check of the formation levelCheck levels using a laser level on the crusher-run foundation layer. Prohibit any hollow near emergences and set a continuous fall of 2.5 % outwards.
  2. Adjustment of the laying bed with excess thicknessPull the laying bed in 2/4 or 1/3 crushed gravel using metal guides. Provide an allowance of 5 mm along the building to anticipate final mechanical compaction.
  3. Tamping and check with the straightedgeCompact the paving with a vibrating plate equipped with a synthetic pad. Check the surface with a 3-meter straightedge equipped with an electronic level to verify the absence of fall reversal.
  4. Clearance of the downstream outletCheck the downstream connection on the lawn or infiltration structure. The kerb or topsoil must never form an abutment higher than the edge of the surfacing.

Prolonged water stagnation at the base of a wall leads to clogging of the clean ballast, the appearance of algae and the aesthetic degradation of facades by splashing. Although below-ground waterproofing falls under structural work, the landscaping of surroundings conditions the hydraulic efficiency of the whole. Respecting the minimum drainage fall and uncompromizingly orienting the cross-section profile outwards guarantees the durability of the structure and sustainably protects thresholds and facades against the assaults of runoff water.

Remediation and correction of fall defects at the base of the facade

When a reverse fall or subsidence is detected after laying surfacings, runoff water inevitably converges towards the plinth of the structure instead of draining outwards. This water stagnation at the base of the wall accelerates the fouling of masonry, saturates the granular foundation and generates frost damage in the winter period. According to the general rules of the construction contract derived from the Code of Obligations, the landscaping contractor is liable for execution defects that render the installation non-compliant with recognized rules of the trade. Faced with reversed drainage, the construction site team must act methodically to restore sustainable gravity drainage without redirecting runoff towards neighboring plots.

  1. Diagnosis with laser level and altimetric surveyPosition the laser level to establish the actual profile on a strip of two to three meters from the wall. The survey makes it possible to quantify the exact extent of the hollow and determine whether the defect comes from poorly compacted backfill settlement or an adjustment error during the laying of kerbs.
  2. Removal of surfacing and repair of the load-bearing layerFor paving on a granular laying bed, the only sustainable measure requires the complete removal of elements on the subsided area. Topping up only the laying bed represents a major technical fault, because the maximum thickness prescribed by standard SIA 318 does not allow compensation of several centimetres. It is necessary to repair the non-frost-susceptible aggregate foundation layer, compact energetically, then recalibrate the laying bed with the minimum drainage fall outwards.
  3. Integration of a compensatory linear drainWhen the altimetric constraints of existing thresholds physically prevent the raising of the finished level towards the facade, the installation of a slot drain or a grating drain proves essential. This device captures runoff upstream of the wall base and directs water towards an infiltration basin or a landscaped swale.

A contradictory handover with a water jet spraying test definitively validates the absence of residual puddles and protects the company against subsequent disputes upon delivery of the work.

Frequently asked questions

What is the minimum permissible fall for concrete paving according to standard SIA 318?

For concrete paving laid on a gravel bed, standard SIA 318 recommends a minimum fall of 2 % to guarantee the gravity drainage of surface water. This gradient makes it possible to compensate for execution tolerances of pavers, avoid stagnant puddles and prevent clogging of sand joints. A fall below 1.5 % is prohibited outdoors because it promotes the formation of ice in winter and premature deterioration of materials.

How to correct a reverse fall without dismantling an entire terrace of slab paving on pedestals?

On slabs laid on adjustable pedestals on the ground, correction is carried out without heavy demolition thanks to the micrometric adjustment of the pedestal heads. It is sufficient to lift the slabs concerned using a suction slab lifter, screw or unscrew the support rings to restore the minimum fall outwards, and then check the level with the laser. This operation guarantees rapid drainage of runoff water and eliminates any risk of retention against masonry.

Why is a reverse fall of two centimetres critical at the base of a facade wall?

A two-centimetre hollow directs runoff from the entire adjacent surface right against the building. The accumulated water soaks the plinth renders, accelerates the appearance of salt efflorescence and penetrates under door thresholds. In winter, this pocket of water freezes, causing joint bursting and tearing of surfacings by frost heave. External works lose their protective function and create a direct pathology for all structural work.

How to prove the direction of water drainage during the handover of external works?

The contradictory spraying test constitutes the most convincing method on the construction site. Continuous watering with a water hose on the paved or asphalted surface allows immediate visualization of the water flow and identification of any residual low points. An optical or laser level survey recorded on the handover report confirms that each level drops regularly from the facade outwards, in accordance with execution plans and rules of the art.

Texts and standards cited

  • SIA 318External works - Technical requirements for earthworks, foundation layers, paving, slab paving and surface water drainage

In the same section