🧱 CFC 411Low walls, retaining structures and external stairsChapter 10 of 10 in the section

At the boundary: boundary survey, permitted height, neighbour's consent and wall to be relocated

Building a boundary wall or a low retaining wall along a plot edge leaves no room for geometric approximations. You will learn how to order and use a licensed surveyor's survey, check the heights permitted by the municipal construction regulations, formalize the written consent of neighbouring owners and secure the building permit before starting excavation for the foundation footing.

Key takeaways

  • Have the real boundary marked and staked out by an official surveyor before opening the excavation.
  • An encroachment of a few centimetres onto the neighbouring plot exposes the structure to complete demolition.
  • The maximum permitted height is calculated relative to the natural terrain in accordance with the municipal regulations.
  • Any party wall straddling the boundary requires a signed agreement between owners.

Setting out and marking: official staking out by a licensed surveyor

On site, relying on an old hedge, a rusted wire fence or an existing concrete edging is the landscaper's most costly mistake. Historical fences frequently deviate from the cadastral boundary by several tens of centimetres. If your foundation or masonry facing extends onto the adjacent property, the injured owner can demand the removal of the structure at the exclusive expense of the party who had it erected. Resorting to a licensed surveyor to re-establish missing boundary stones and precisely set out the dividing line is not an optional precaution, but the essential starting point for any landscaping construction site.

  1. Verification of cadastral fixed pointsSearch for existing reference marks, metal plugs or granite boundary stones, then commission the official surveyor to survey the as-built condition and recalculate the exact cadastral coordinates.
  2. Staking out the alignmentThe surveyor marks out the axis of the property boundary using reinforcing bars topped with fluorescent markers or surveying nails driven into the asphalt or rock.
  3. Installation of offset batter boardsSet up rigid batter boards set back from the excavation area. Transfer the alignments using a chalk line while maintaining a clear clearance to allow the excavator bucket to pass without hitting the markers.
  4. Checking the outer facingVerify that the outer face of the blocks, prefabricated elements or dry stone aligns strictly within the plot, or precisely on the boundary agreed in writing.

When the terrain has a cross-slope, the position of the excavation modifies the temporary slopes. You must ensure that opening the excavation does not destabilize the neighbour's topsoil. According to the safety rules of the construction work ordinance, excavation faces must be battered or secured as soon as there is a risk of rockfall or collapse, which requires anticipating the total width of the work right from the layout phase.

Municipal regulations, party-wall agreement and file submission

The spatial planning act and cantonal construction law delegate to municipal regulations the task of setting the building police rules applicable to fences and low retaining walls. The maximum permitted height generally varies from one metre to one metre fifty along private party boundaries, and often decreases further near roadways to ensure vehicle visibility. This measurement is always calculated from the natural terrain level before work begins up to the upper edge of the coping.

Typology of property boundary walls and associated constraints
Type of setting outProperty foundation baseRequired contractual documentsAdministrative procedure
Private wall set backEntirety of the wall and footing on the client's propertyExecution drawings compliant with the surveyor's surveyExemption or work notification according to municipal regulations
Private wall on exact boundaryOuter facing flush to the millimetre with the dividing lineRecord of boundary stones and agreement for temporary access worksFormal notification or municipal inquiry exemption
Party wall straddling the boundaryMedian axis of the wall aligned with the boundary of the two plotsWritten party-wall agreement or easement in the land registerBuilding permit with co-signature of neighbouring owners

Erecting a party wall requires a bilateral written agreement signed before the first shovel is turned. The party-wall agreement specifies the financial breakdown of the work, the sharing of future maintenance costs, the choice of materials and the finished level elevation. To ensure this agreement remains valid against any future purchasers of the neighbouring plot, it is strongly recommended to register a corresponding property easement in the land register via a notarial deed.

Setting out on site: foundation overhang and profile control

On site, the physical marking of the reference points established by the licensed surveyor requires constant rigor before the first bucket strike. When setting out a low wall or a retaining structure in landscaping, the classic mistake made by the team leader is to align only the visible facing of the wall with the property boundary, without anticipating the actual footprint of the excavations and foundations. However, according to the Swiss Civil Code, property rights extend from the subsoil up to the airspace above. Any overhang of an unreinforced concrete footing, a bedding layer or a drainage pipe beyond the cadastral line constitutes a territorial violation treated as an unlawful encroachment. Setting out batter boards must be offset outside the excavation, with reference points transferred precisely from the official boundary stones.

Positioning of wall components relative to the property boundary
Structure componentStrict rule at boundaryRisk of encroachmentSite solution
Foundation footingEntirely on the plotClassic overhang of 10 to 20 cm on the neighbour's propertyEccentric footing or inner flange
Outer facingAligned or set back according to the planOut-of-plumb towards the exteriorRegular vertical check with the mason's straightedge
Drainage and weep holesDischarge onto the client's plotWater runoff onto the neighbour's propertyInternal longitudinal collector with compliant outlet
Coping or capDrip edge included within the profile envelopeAerial projection of a few centimetresProfile without exterior overhang or asymmetrical installation

The height permitted by the municipal construction regulations requires rigorous verification of the reference level. Municipal regulations define the allowable height relative to the original natural terrain, and not relative to regraded earth after excavation. For garden boundary walls or small retaining structures, local regulations in French-speaking Switzerland frequently limit the height without derogation between 1.00 m and 1.50 m on the downstream side. As soon as the height difference or earth pressure requires a taller wall, or when the project alters the site configuration, a formal building permit issued by the municipal authority proves essential. Building a wall that is too high at the boundary, even on one's own plot, exposes the client to non-compliance proceedings that can lead to a municipal demolition or reduction order.

The record of encroachment and the obligation of demolition

When a wall is erected even twenty centimetres on the wrong side of the cadastral boundary, the owner of the neighbouring land can demand the pure and simple demolition of the structure as well as the restoration of the site to its original condition. The Swiss Civil Code grants no leniency for land usurpation, unless the author of the encroachment proves their good faith and the neighbour has not raised an objection in a timely manner. Even in this exceptional hypothesis, the granting of an encroachment easement against compensation falls under the appreciation of the civil judge. In practice, a wall encroaching without legal title must be pulled down. A preliminary agreement or a simple letter signed by the current neighbouring owner proves insufficient: only a formal written agreement executed before a notary and registered in the land register guarantees the durability of the wall against future purchasers.

On the contractual level of the SIA 118 standard, the landscaping company is liable for execution defects and failure to comply with the setting-out data provided by the project plans. If the site manager starts masonry work without relying on staking out by an official surveyor, the rectification costs are borne by the company. Relocating a boundary wall generates considerable extra costs: mechanical demolition, diamond sawing, removal of excavated material in accordance with the waste ordinance, complete cleaning out of the buried footing, then excavation of a new offset foundation trench. Saving on a setting-out check by a surveyor before placing the first element invariably results in major financial loss and destructive party-wall disputes.

Management of encroachment disputes and deconstruction protocol

When the neighbouring owner reports an encroachment or the setting-out check reveals a deviation onto the adjoining plot, the team leader suspends the masonry work. Continuing installation while hoping for an arrangement exposes the company to a stop-work order issued by the municipal construction police, combined with a demolition order at the builder's expense. The initial step consists in requesting the licensed surveyor to draw up a joint survey of the actual situation. Informal discussions with neighbors never protect the company: only an authenticated written agreement or an easement registered in the land register guarantees a durable legal basis in the event of a dispute.

If the overhang is established and the neighbour refuses any party-wall concession, deconstruction remains the only technical solution. The construction manager plans the mechanical sawing of the incriminated masonry or the total removal of the structure and its base. The continuous concrete strip footing must be cut with a floor saw flush with the cadastral line, without destabilizing adjacent earth. The intervention requires scrupulous care to avoid pulling up existing boundary stones or damaging underground utilities. Demolition residue and excavated soil are then sorted and routed to a recovery channel in accordance with the waste ordinance.

  1. Official recognition and re-stakingThe official surveyor re-establishes fixed reference marks and confirms the compliance of the property alignment before any construction resumes.
  2. Reconstruction according to the regulatory profileThe new structure is erected strictly set back from the neighbouring plot, integrating the facing and the foundation within the authorized volume.
  3. Validation of the municipal fileThe site management transmits the as-built plan to the municipality to confirm the lifting of reservations and close the administrative incident.

Frequently asked questions

Can the neighbour demand the demolition of an invisible foundation footing in the subsoil?

Yes. Land property rights extend to the subterranean space necessary for the exercise of the right. If the foundation footing of a private wall extends onto the neighbouring plot, even sixty centimetres below the finished lawn level, it constitutes an unlawful encroachment. The injured neighbour can demand its sawing or complete removal, unless both parties sign a written agreement establishing an encroachment easement registered with the land register.

Does a verbal agreement from the neighbour suffice to build a boundary wall without a setback?

No, a verbal agreement has no probative value in the event of a dispute or subsequent sale of the plot. To set out a boundary wall or derogate from legal distances, a written agreement signed by the neighbouring owner is essential. Furthermore, this private agreement never exempts from the legal procedure: the municipality must issue an exemption or building permit in accordance with the municipal construction regulations before any implementation on site.

What should be done if a cadastral boundary stone has disappeared during excavation work?

It is strictly forbidden to replace a boundary stone or reference peg yourself. The team leader must stop excavation in the border area and alert the client's representative. Only an official licensed surveyor has the legal competence to carry out boundary re-establishment by cadastral triangulation. The cost of this official re-pegging is charged to the company responsible for the removal, and work resumes only after validation of the new reference mark on site.

What maximum height can a low wall reach without a building permit?

The building permit exemption depends exclusively on cantonal law and municipal construction regulations. In most municipalities in French-speaking Switzerland, boundary walls or low retaining structures are exempt from public inquiry only up to a height between one metre and one metre fifty. Beyond that, or in the event of a significant modification of the natural ground profile, the submission of an official file with setting-out plans remains required before any execution on site.