🧱 CFC 411Paving and slabs: laying, joints and kerbsChapter 5 of 10 in the section

Raised paving slabs: adjustment, sub-slab drainage, wind uplift and free edge

This chapter guides you step by step through the installation of raised paving slabs for external works. You will learn how to adjust self-levelling heads to compensate for slopes, ensure water drainage compliant with SIA 318 and mechanically lock free edges to withstand wind gusts.

Key takeaways

  • Adjustable pedestals make it possible to achieve a perfectly flat surface while maintaining a proper drainage slope underneath.
  • Water infiltrates freely through the open joints without any risk of surface puddling.
  • Full disassembly facilitates the maintenance of technical conduits and the rapid replacement of damaged elements.
  • Rigid locking of the free edge prevents slabs from sliding under the effect of the wind.

Altimetric adjustment and free drainage under the removable decking

Installation on adjustable synthetic pedestals separates the horizontal walking plane from the load-bearing surface. Unlike installation on a gravel bed or a bonded coating, the system operates with open joints. Rainwater passes through the three to five millimetre gaps created by the spacers on the pedestal head, then flows directly down the inclined substrate towards the outlets. This design eliminates surface stagnation and protects the slabs against internal freeze-thaw stresses.

Self-levelling pedestal
Synthetic support with a rotary screw jack whose oscillating head automatically compensates for substrate slopes of up to five percent to ensure the paving remains horizontal.

Levelling is carried out element by element by adjusting the threaded ring of the pedestal, often using a specific spanner without lifting the slab. According to the execution principles of SIA 318, the final flatness of a pedestrian paving surface requires strict regularity, generally checked using a two-metre straightedge. The contractor compensates for sub-base variations without altering the underlying drainage slope, which must always remain at least one point five percent to prevent any water retention beneath the slabs.

  1. Substrate check and setting outCheck the bearing capacity of the compacted soil or mineral base, then set out the starting square using a chalk line from the main access line.
  2. Installation and wedging of base pedestalsPosition the corner and edge pedestals by breaking off unnecessary lugs on the support head to properly seat the edge slabs.
  3. Fine adjustment and installation of shock absorbersAdjust the height using a rotary laser and insert an elastomeric acoustic shim on each pedestal head to absorb impact noise.
  4. Placement of central slabsLay the ceramic or concrete slabs using a double suction lifter, then check the flush alignment with a spirit level at each intersection.

Edge stabilisation, free edge and resistance to wind loads

The vulnerable point of a raised terrace lies in the treatment of edges that are not abutted against a facade. Without peripheral restraint, the repeated loads from users and air turbulence cause the outer slabs to shift progressively. When a slab loses its full support on the pedestal spacer, it tilts and exposes the entire row to uplift under the effect of aerodynamic suction generated by wind gusts.

Comparison of free edge restraint systems
SystemField of applicationConstruction site advantagePoint to monitor
Top and bottom metal clipsFree edge with closed riserInvisible aesthetic finish and vertical lockingRequires strictly calibrated slab thickness
L-shaped aluminium profile fixed to the pedestalOpen edge with drip edgeExcellent linear rigidity against windStrict alignment of end pedestals required
Independent external concrete kerbDirect connection to level green spaceMassive stop resistant to side impactsClean foundation outside the raised system
Stabilisation plate under the baseExternal corners and highly exposed areasPrevents the eccentric pedestal from tiltingMust rest on a perfectly flat ground

Edge fixing must be planned during the marking-out stage. For peripheral slabs, the pedestals are fitted with stainless steel clips that grip the edge of the upper slab and support the vertical skirting board. This closure creates a barrier against air entering beneath the decking. In strong wind corridors, the contractor glues elastomeric shims to the pedestal heads or uses a dab of flexible polymer adhesive under the corner slabs to prevent any movement while still allowing future dismantling with a utility knife.

Execution of wedging and management of sub-decking drainage

The installation of raised paving slabs in external works meets two fundamental requirements: providing a perfectly adjusted traffic plane with no visible slope and ensuring the rapid evacuation of rainwater through open joints. According to SIA 318, the system relies on a stabilised sub-base, most often a compacted crushed gravel formwork or load-distribution concrete slabs laid directly on the landscape foundation layer. Unlike bonded paving, this system preserves the complete removability of surface elements, facilitating the maintenance of drainage channels, infiltration manholes and concealed technical networks.

Height adjustment per pedestal is carried out using millimetric rotary rings or self-levelling heads. In the presence of local counter-slopes in the raw ground, these heads compensate for up to five percent inclination to keep the slab seating level. The installation team adjusts the jacks using a specific notched spanner, checking the elevations with a three-metre straightedge and an optical level. Free drainage under the slabs requires a minimum clearance between the underside of the coating and the prepared ground. This ventilated space prevents water stagnation against mineral materials, avoids rising damp and allows fine sand washed down by runoff to flow freely towards the natural outlet without blocking the telescopic mechanisms.

Handling the slabs requires the use of double-handled mechanical suction lifters to avoid chipping sharp edges when placing them onto the spacer lugs. A systematic stability check underfoot is carried out as work progresses: each element must rest in a balanced manner on its four corner supports, supplemented by a central pedestal for formats larger than sixty centimetres square.

Locking of free edges and anti-uplift devices

The behaviour of raised paving differs significantly from traditional paving due to the total absence of binder or jointing sand. While this characteristic ensures continuous permeability and instant removal, it makes the system vulnerable around its perimeter. Whenever the terrace does not abut against a building facade or an existing masonry kerb, creating a stable free edge represents the major challenge for the landscape constructor. Without a rigid enclosure, the peripheral slabs slide under the dynamic thrust of users, destabilising the layout and exposing the underside to air infiltration.

The fixing of edges exposed to wind responds to a direct aerodynamic risk: under a gust of wind, a depression forms on the surface while air rushes under the decking through the open edge. This pressure differential generates an uplift force capable of ejecting the end slabs, causing property damage and personal injury. Peripheral locking requires the installation of anchored metal edge angles, stainless steel edge clips inserted onto the base and head of the jacks, or integrated risers that seal the underside while retaining lower ventilation slots.

Support components for edges and free boundaries
Stabilisation elementMain functionAnchorage method to the substrate
Lower stainless steel edge clipHolding the vertical riser at the foot of the pedestalMechanical clamping under the polymer base of the jack
Upper stainless steel edge clipHorizontal locking of the end slab and vertical stopDirect insertion onto the notched head under the slab
Peripheral aluminium edge angleComplete perimeter containment to prevent slidingMechanical fixing into concrete foundation blocks or kerbs
Intermediate ballast plateIncreasing surface mass against strong windsPlacement under slab or mechanical connection by clipping
  1. Alignment of edge pedestalsCut off unused spacer lugs on the head of edge pedestals using cutting pliers or a utility knife to obtain a flat support without offset.
  2. Installation of edge stopsInstall the metal stop clips to prevent any lateral movement of the last row of slabs towards the lawn or adjacent flowerbed.
  3. Cladding the riserSlide the vertical slab cutout into the upper and lower stainless steel clips to seal the underlying space against direct air drafts.
  4. Final check of the locking systemApply lateral pressure with your foot and a manual uplift check on each edge slab to ensure the overall assembly holds firm against gusts.

Management of defects on removable decking and edge repairs

On a raised slab terrace construction site, defects noted upon handover or after a severe windstorm almost systematically originate from a lack of peripheral blocking or adjustment failure under load. When slabs move or wobble under traffic, forcing the spacer lugs is useless. The first step is to methodically remove the affected line using a mechanical suction lifter to inspect the pedestal seating and substrate condition.

According to SIA 318, the stability of external finishes relies on the durability of the wedging and the free evacuation of water. If you observe abnormal water retention under the slabs, check the slope alignment of the underlying formwork and the general cleanliness under the pedestal heads. Plant debris or construction residue can quickly clog the free drainage gaps and create hard spots. Methodical cleaning with clean water without pressure restores regular runoff without risking the displacement of unanchored pedestals.

  1. Diagnosis of edge instabilityCheck whether the misalignment comes from lateral sliding of the end pedestals or poorly absorbed thermal expansion. The wind-exposed free edge must have an immovable mechanical stop to prevent any shifting.
  2. Plumb correction and wedgingAdjust the height setting ring on each pedestal using the specific spanner. If the seating has a local out-of-plumb issue, insert a slope corrector or notched shim without stretching the thread to its maximum limit.
  3. Locking the free edgeIn the event of dislodgement caused by air suction, install metal anti-uplift clips secured to the pedestal head or lock the edge with a continuous ballasted edge profile.
  4. Checking gaps and relayingRelay the clean slabs while maintaining a regular joint of three to five millimetres. Tap with a white rubber mallet to engage the edges against the spacers without chipping the material.

In the event of a dispute relating to uplift or repeated edge chipping, apply the claims procedure defined in SIA 118. The ability to dismantle the system slab by slab constitutes a major advantage to prove whether the defect stems from settlement of the sub-base, a lack of peripheral fixing against gusts, or a slab thickness unsuited to the span between supports.

Frequently asked questions

How to prevent a raised terrace free edge from tilting under load?

To neutralize tilting at the edges, systematically double up the end pedestals or use specially cut bases to abut against the stop profile. The addition of stainless steel edge clips secures the last slab to the pedestal and maintains the joint spacing. A continuous aluminium or galvanized steel edge profile, sealed or fixed to the substrate, durably blocks this free edge.

Why is it necessary to maintain free drainage under the slabs without filling the voids?

The fundamental principle of raised installation lies in the rapid evacuation of surface water through open joints. Water flows directly beneath the decking towards the drainage system of the supporting formwork. Filling the void under slabs with gravel or allowing sediment to accumulate creates water retention, accelerates fouling and prevents rapid inspection or removal for terrace maintenance.

What is the minimum bearing capacity required to install pedestals on external ground?

In accordance with the rules of SIA 318, pedestals are never placed on topsoil or loose earth. The ground must receive a compacted granular foundation layer guaranteeing sufficient resistance against punching. On prepared ground, concrete distribution tiles are inserted under each base to ensure proper seating and preserve altimetric adjustment under operational loads.

How to secure raised paving slabs against wind uplift?

On terraces highly exposed to gusts or in windy areas, wind uplift is contained by the mass of the elements and mechanical fixings. Thick and dense slabs are preferred. At the free edge, the implementation of locking clips secured to the pedestals, supplemented by a closed peripheral skirt, prevents air from rushing under the paving and tearing the slabs away.

Texts and standards cited

  • norme SIA 318External works, requirements for finishes and foundations
  • norme SIA 118General conditions for the execution of construction work