🧱 CFC 411Surface water: slope, drainage and infiltrationChapter 3 of 10 in the section

Infiltrating on site: municipal requirement, permeability test and soakaway

This chapter guides you step by step to validate the technical feasibility of on-site infiltration on a private property. You will learn how to conduct a reliable percolation test in the field before engaging your company, interpret soil permeability, size the required retention volume according to the collection area, and position the structure while respecting safety distances from buildings.

Key takeaways

  • The municipal requirement to infiltrate rainwater depends directly on the actual absorption capacity of the subsoil.
  • The constant-head or falling-head permeability test must be carried out before any project validation.
  • The sizing of the retention volume incorporates local precipitation intensity and connected runoff areas.
  • The infiltration structure is always positioned at a distance from foundations to preserve the load-bearing capacity of the soils beneath the structure.

Validate soil permeability before accepting the municipal requirement

In almost all Swiss municipalities, the general drainage plan (PGEE) imposes the principle of managing stormwater at the source. The landscape contractor is thus required to fully infiltrate roofs and private roads on the landscaped plot, with a strict ban on direct discharge into the combined or clean water sewer system. However, this administrative injunction regularly clashes with the geological reality of the subsoil. Between heterogeneous uncompacted fills, dense molasse, low-permeability glacial silts, or the presence of a shallow water table, the ground does not systematically allow the required runoff flows to be absorbed. The contractor must never validate a project or price a complex without first checking the actual permeability through targeted borings.

  1. Excavation of the test pitDig a trial pit measuring at least 40 centimetres per side with an excavator to the exact depth of the future infiltration level of the structure, carefully cleaning the walls to eliminate any smearing of the soil.
  2. Hydraulic saturation of the soilFill the pit with clean water and maintain a constant level for at least two hours to completely saturate the microporosities of the soil matrix before taking any measurements.
  3. Recording the infiltration rateRefill the pit to a water depth of 30 centimetres, then measure the drop in the water level using a metal ruler at regular intervals of ten to fifteen minutes until the rate stabilizes.
  4. Calculation of the permeability coefficientDetermine the k value expressed in metres per second based on the observed drawdown time, in order to formally classify the suitability of the receiving ground according to professional recommendations.

A permeability coefficient k greater than ten to the power of minus five metres per second guarantees an excellent infiltration capacity for simple gravel structures. When the measured value drops between ten to the power of minus five and ten to the power of minus six metres per second, infiltration remains technically feasible but requires very large retention volumes to compensate for the slow percolation. Conversely, below the critical threshold of ten to the power of minus six metres per second, the soil is deemed impermeable for continuous gravity absorption: the structure would saturate during the first storm and overflow onto the surface, creating damage to neighboring external works.

Sizing the useful volume and securing the surrounding buildings

The sizing of the infiltration structure is based on the balance between the volume of water collected during a reference rainfall event and the volume evacuated by percolation during that same period. The landscape contractor calculates the active impermeable surface by applying the runoff coefficients specific to each surfacing: from zero point one for an extensive green roof up to zero point nine for mortar-jointed paving or bituminous asphalt. The required buffer storage volume compensates for the difference between the peak flow arriving from the surfaces and the infiltrated outflow through the earthwork walls, while ensuring complete drainage in less than twenty-four hours.

Surface and underground infiltration systems in external works
SystemRequired footprintSoil permeabilityExecution characteristics
SwaleLarge surface areaMedium to goodLow-slope grassed depression ensuring filtration through topsoil before percolation.
Drainage trenchSmall and linearGood to very goodBackfill of 16/32 washed gravel wrapped in an anti-clogging geotextile under roads or grass.
SoakawayHighly concentratedGood at depthPerforated concrete rings on a clean gravel bed allowing deep permeable layers to be reached.

The installation of an infiltration system requires strict compliance with safety distances from neighboring buildings. The massive input of rainwater generates an imbibition bulb that alters the moisture state of the soil and can destabilize shallow foundations through differential settlement or the washing out of fines. Good practice dictates a minimum horizontal clearance of five metres between the outer edge of the infiltration structure and any building wall without a basement, and six metres in the presence of an inhabited basement. On sloping ground, this distance must be increased upslope to prevent any water resurgence under foundations or against low garden retaining walls.

Execution of soakaways and trenches: earthworks, filter backfill and wrapping

Earthworks for an infiltration structure require a rigorous method so as not to degrade the natural permeability identified during prior testing. The bottom of the excavation must imperatively be opened with a grading bucket, avoiding any smearing or smoothing of the receiving horizons. No heavy construction machinery must drive over the bottom of the excavation: accidental compaction of the soil under the tracks of an excavator drastically reduces soil porosity and cancels out the absorption capacities initially validated for the plot.

The choice of technical system depends on the available space in the surroundings and the depth of the water table or receiving layer. The following table summarizes the installation characteristics of the three main systems implemented by the landscape constructor.

Comparison of on-site infiltration structures
System typeGround footprintUseful void volumeOperational maintenanceClogging sensitivity
Soakaway (perforated concrete rings)Small (diameter 1000 to 2000 mm)High (100% in the tank, 35% in the surrounding gravel)Direct access via manhole cover for high-pressure jettingMedium with regular upstream silt trap
Trench or modular attenuation crate basinMedium to large, linear or areaVery high (approx. 95% of total excavated volume)Camera inspection, difficult cleaning if not jetting-compatibleVery high if upstream filtration fails
Grassed surface infiltration swaleVery large (gentle slope embankments)Low to medium (open-air storage)Regular mowing and strimming, periodic scrapingLow thanks to filtration through the topsoil layer

For trenches and ballast soakaways, the aggregate grading must be free of fines. Only washed rolled gravel or clean crushed aggregate of 16/32 or 32/45 grain size is used. The entire drainage mass must be wrapped in a heat-bonded non-woven permeable geotextile of a suitable class to prevent the intrusion of fine particles from the surrounding soil. The geotextile membrane is folded back at the top with a minimum overlap of fifty centimetres before placing topsoil or pavement base layers.

Connection of inflows, management of overflow and commissioning report

An infiltration structure never receives raw water laden with road or roof residues without physical pre-treatment. Sustainable infiltration relies on the systematic interception of sand, dead leaves, and sludge upstream of the storage zone. Every clean water supply pipe from gutters, yard drains, or downpipes must pass through a silt trap manhole equipped with a debris basket and a siphon wall. This manhole retains heavy particles and floating debris that would irreparably clog the geotextile or the pores of the modular blocks.

  1. Layout and altimetry checkCheck the excavation bottom levels using a laser level in relation to neighboring foundation levels and surface rainwater collector inlets.
  2. Installation of the filter wrapUnroll the non-woven geotextile over the prepared walls and bottom, taking care with joints to ensure a watertight separation against fine soils.
  3. Assembly of elements and backfillingInstall the perforated rings or assemble the modular crates, then methodically backfill with washed gravel in regular layers without striking the structure.
  4. Connection of the safety overflowInstall the overflow pipe at the top of the structure towards the emergency outlet approved by the general drainage plan.

The municipal water drainage requirement makes it mandatory to provide a discharge route for exceptional rainfall events that exceed the return period calculated for the structure. The soakaway or trench must include an overflow pipe connected either to the separate public network, if the municipality expressly authorizes it by derogation, or towards a secure surface spreading area located away from neighboring buildings. This high point prevents hydraulic pressurization of the ground around private masonry.

Finally, the sustainability of the installation implies the handover of an external works maintenance log. This document specifies the cleaning frequency for silt traps and sumps, set at a minimum of one annual intervention in autumn, as well as checking for the absence of abnormal water stagnation in inspection chambers after heavy weather.

Managing contingencies: insufficient permeability, saturation and use of the network

When pit or permeameter tests reveal permeability that is too low, the total infiltration required by municipal water distribution regulations becomes technically unfeasible. Trying to install an infiltration structure in compacted, silty, or clayey soil inevitably leads to surface waterlogging, suffocation of green spaces, destabilization of road subgrades, or water thrusts against neighboring buried structures. As soon as the permeability coefficient proves to be below the efficiency threshold, the landscape contractor must record the measurements and report the inadequacy of the ground in writing to site management in accordance with SIA 118, in order to rule out any dispute for defective work.

Faced with impermeable soil, a shallow water table, or contaminated ground precluding any underground discharge, the fallback solution consists of requesting a written municipal derogation. The system then transitions from pure infiltration to surface water retention with delayed discharge. The storage volume, created in the form of a vegetated swale, watertight basin, or modular retention crates, holds the stormwater volume before releasing it at a precisely calibrated flow rate into the public storm sewer network or a receiving watercourse. The integration of a flow regulator and a safety overflow ensures that the structure will not back up into vehicular areas or downstream plots.

  1. Geotechnical finding and work stoppageMeasure the actual infiltration time on site. If water stagnates for a prolonged period in the test pit after twenty-four hours, record the readings in writing and halt all commitments to total infiltration on the plot.
  2. Technical notification and retention variantTransmit the test report to site management as soon as the finding is made. Propose switching to a retention basin with restricted discharge, subject to the review of the municipal technical services and the client.
  3. Preventive maintenance and filter renewalIn the event of clogging on an operational structure, empty the sludge from the primary silt trap, strip the sand bed coated with fines, and clean the suction grilles to restore surface absorption.

Frequently asked questions

What to do if the municipality refuses connection to the storm network when the ground infiltrates nothing?

When the soil refuses all infiltration and the municipality prohibits direct connection, the landscaper must propose a combined retention and reuse system. Roof and road runoff is directed towards a watertight storage cistern equipped with an overflow to an evaporation vegetated swale. The stored water is used for watering green spaces or cleaning external areas, drastically reducing the residual volumes to be evacuated during rainfall events.

What minimum distance must be maintained between a soakaway and building foundations?

The general code of practice requires keeping the infiltration structure at least five to six metres away from any buried wall or unsealed foundation, to avoid soaking the building's base. If the plot has a slope, the soakaway is positioned downslope of the buildings. On flat ground with an inhabited basement, bringing an infiltration trench closer requires a vertical waterproof screen or prior validation by the structural civil engineer responsible for the building.

How to size the volume of an infiltration trench for a paved courtyard?

The calculation is based on the receiving area multiplied by the runoff coefficient of the paving and the region's ten-year rainfall depth. For a paved courtyard with draining joints, this useful volume is reduced by the surface's direct infiltration capacity. The volume of water to be stored is then divided by the void ratio of the backfill materials, i.e., approximately thirty-five percent for washed rolled gravel without fines.

Why must a permeability test be carried out at the final excavation bottom?

Permeability varies considerably depending on geological strata. A test performed at the surface, in topsoil or surface fill, gives misleading absorption rates bearing no relation to the reality of the receiving subsoil. The test must be dug to the exact depth where the bottom of the gravel bed or the base of the crates will rest. This makes it possible to identify potential impermeable clay lenses or the seasonal level of the groundwater table.

Texts and standards cited

  • norme SIA 118General conditions for the execution of construction works and duty to notify in case of ground inadequacy