Paving and slabs: installation, joints and edgings: the execution reference guide
Intended for team leaders, foremen and landscape constructors, this guide brings together the execution rules for successfully installing exterior pavers and slabs on natural or stabilised ground. Drawing on the SIA 318 standard, it details the bedding layer, edge restraints, joint filling and water management. The objective: to guarantee durable surfacings that do not settle and resist both frost and traffic.
- 10chapters
- 22 000words
- 6sections in the training course
- 60chapters in total
Key values to remember 4
30 to 50 mm
Nominal thickness of the uncompacted bedding layer before tamping
3 to 5 mm
Prescribed width for concrete paver joints on grit
2.0%
Minimum crossfall for surface gravity drainage
4 mm
Maximum flatness tolerance under the 2 m straightedge in paving
Scope of application of CFC 411 and construction site interfaces
This section deals exclusively with paving, slab-laying and mineral stabilisation work carried out by the landscape constructor within the perimeter of the private plot (CFC 411). The work concerns access courtyards, pedestrian paths, vehicular ramps and terraces installed on natural ground, on stabilised backfill or on adjustable pedestals. Implementation is based on modular construction principles: permeable foundation layer, calibrated bedding layer, precise pattern layout and mechanical vibratory compaction.
Compliance with professional standards requires checking the condition of the earthworks formation level prior to any installation operation. According to art. 365 CO, the contractor must immediately report any bearing capacity defect, localised settlement or compaction anomaly of the substrate handed over by the earthworks contractor, failing which they will bear responsibility for future structural defects.
- Covered surfacings: interlocking concrete pavers, natural stone pavers, mineral slabs on grit beds or pedestals, permeable pavers and gravel stabilised on honeycomb panels.
- Covered operations: preparation of the uncompacted bedding layer, peripheral restraint using edgings or concrete abutments, joint filling and compaction, edge cutting and level connections.
- Formal exclusions: bonded screeds, bonded installations of ceramic slabs, high retaining structures and roof-terrace waterproofing.
Sequential execution method according to SIA 318 standard
The durability of a paved surface depends on a strict logical order: each layer conditions the stability of the next. An error in the thickness of the bedding layer or a lack of rigidity in the edgings can never be compensated for by the final vibration. The ten chapters of this section follow the actual chronology of the construction site, from the sub-base to winter performance.
- Sub-base and lateral containment (V2-01 to V2-03)Check the particle size distribution and uniform thickness of the uncompacted bedding layer, wedge the concrete edge abutments to block horizontal thrusts, then calibrate the joint width to prevent edge-to-edge contact.
- Installation, bonding patterns and demountable systems (V2-04 to V2-05)Arrange the elements according to a pattern that limits displacement under rolling loads (herringbone or stretcher bond), take care with edges and control the spacing as well as wind stability of terraces on pedestals.
- Water management and alternative surfacings (V2-06 to V2-07)Implement permeable pavers while protecting the sub-base layers against construction fines, and stabilise gravel paths using anchored cellular grids.
- Durability, inspection and reinstatement (V2-08 to V2-10)Prevent scaling caused by de-icing salts, check flatness tolerances using the straightedge to eliminate puddles, and apply the repair method after trench opening.
The rigorous application of SIA 318 standard requirements protects the company against claims related to axle-load deformations, edge spalling or residual water stagnation. Compliance with minimum slopes combined with a stable jointing material ensures a functional and durable private roadway.
📘 Chapters in this section 10
The bedding layer: thickness, particle size, uncompacted state, and the resulting rutting
Control the thickness and particle size distribution of the uncompacted bedding layer to eliminate any risk of rutting.
Paving and slabs: laying, joints and kerbsRetaining edges: edging, concrete backing, and paving that opens up at the edge
Permanently secure concrete edgings to prevent lateral spreading under rolling loads.
Paving and slabs: laying, joints and kerbsJoints: width, jointing sand, vibration, and the joint that never fills
Select suitable sand and methodically vibrate to obtain stable joints that never empty.
Paving and slabs: laying, joints and kerbsPaving patterns: herringbone for loads, edge cutting and guide line
Install in a herringbone pattern and carefully execute edge cuts to perfectly distribute mechanical stresses.
Paving and slabs: laying, joints and kerbsRaised paving slabs: adjustment, sub-slab drainage, wind uplift and free edge
Adjust the sub-base, secure free edges and ensure drainage under ceramic or concrete slabs on pedestals.
Paving and slabs: laying, joints and kerbsPermeable paving: infiltration capacity, fine particle clogging and maintenance
Guarantee long-term rainwater infiltration by preventing destructive clogging by construction fines.
Paving and slabs: laying, joints and kerbsGravel: cellular stabilization, potholes, raking and migrating gravel
Stabilise gravel paths on cellular grids to stop rutting and the migration of crushed aggregate.
Paving and slabs: laying, joints and kerbsWinter: freeze-thaw cycles, de-icing salt, scaling, and instructions for the client
Protect mineral surfaces against winter scaling caused by chemical de-icers and freeze-thaw cycles.
Paving and slabs: laying, joints and kerbsPlaneness: tolerance, permissible residual puddle, measurement using a straightedge and level
Check flatness with the straightedge according to normative tolerances to eliminate any unwanted residual puddles.
Paving and slabs: laying, joints and kerbsOpening and closing: marked removal, relaying, trench compaction and reserve pavers
Carefully remove and reconstruct the foundation layer without subsequent differential settlement during underground intervention.