🧱 CFC 411Low walls, retaining structures and external stairsChapter 5 of 10 in the section

Outdoor stairs: lower rise, wider tread, drainage slope and frost

In external works, climbing a staircase requires a longer and safer stride than indoors. This chapter details the geometric sizing rules according to Swiss practices and the SIA 318 standard, the implementation of the runoff slope on each step and the surface finishes required to prevent falls in freezing weather.

Key takeaways

  • External steps require a reduced height of between twelve and fifteen centimetres to secure the stride.
  • The external tread widens between thirty-five and forty centimetres to support the natural cadence of the step.
  • A slope of one and a half to two percent immediately drains surface water.
  • Bush-hammered, flamed or shot-blasted surfaces prevent winter slips from the first Swiss morning frosts.

Sizing the rise and tread according to the SIA 318 standard

On a private plot or in a landscaped area, a user's progression differs significantly from walking in an interior stairwell. Outdoor clothing, walking shoes and the visual perception of the slope alter the stride. The mechanical application of building dimensions leads to stairs that are too steep, uncomfortable and dangerous as soon as bad weather occurs. The landscape constructor therefore adapts the proportions right from the earthworks phase.

External stairs and steps must be designed to ensure easy and safe movement in all seasons, by adapting the stride ratio to the topography and the intended use of the development.

norme SIA 318

Blondel's formula remains the basis for calculation, expressed as two rises plus one tread. Inside a villa, the ideal stride aims for sixty-three centimetres with risers of seventeen to eighteen centimetres. Outdoors, the technical recommendations and rules of the art set by the SIA 318 standard lead to lowering the riser to between twelve and fifteen centimetres, while stretching the tread between thirty-five and forty-two centimetres. This geometry relaxes the stride and considerably reduces muscular effort when climbing landscaped slopes.

Comparison of step profiles according to project location
LocationStep height (H)Usable tread (G)Stride (2H + G)
Traditional interior stairs170 to 185 mm260 to 290 mm600 to 640 mm
Terrace and main external access140 to 150 mm340 to 370 mm630 to 650 mm
Landscaped path and gentle slope120 to 135 mm380 to 420 mm630 to 660 mm

For long flights overcoming a significant gradient on natural terrain, the landscaper intersperses regular rest landings. These landings break the acceleration on the descent and make it up for a change in rhythm. The length of the landing must always correspond to an odd number of normal strides on flat ground, i.e., approximately one hundred and forty centimetres for two steps and one tread, in order to approach the next flight with the opposite foot.

Managing the water drainage slope and preventing winter slips

Unlike a sheltered step, an external step is directly exposed to rain, snow and freeze-thaw cycles. If a step is laid perfectly level in the depth direction, the surface tension phenomenon retains a thin film of water. The slightest hollow or differential settlement creates a stagnant puddle that turns into a sheet of ice as soon as the temperature drops below zero degrees.

Each step must have its own drainage slope, directed towards the nosing and oriented towards the lower step. This slope, between one and a half and two percent, is sufficient to drain water by gravity without giving the user the unpleasant sensation of slipping forward. When installing heavy preformed concrete elements or natural stone blocks, the spirit level check is carried out systematically on the bedding layer before final tightening.

  1. Preparation of the draining baseExcavate the ground down to the stable layer and install a foundation of compacted frost-resistant granular material to prevent any future subsidence.
  2. Creation of the bedding layerLay a setting bed of lean mortar or clean crushed grit, without any binder likely to block water infiltration under the piece.
  3. Adjustment of the tread slopeLay the block step, providing a regular forward crossfall of fifteen to twenty millimetres per linear metre of tread using a spacer shim.
  4. Checking alignmentsCheck the regularity of the step nosings with a chalk line and lock the rear heels with draining backing concrete.

Water drainage at the bottom of the stairs deserves equal attention. Water discharged from step to step accumulates at the base of the flight. The landscape constructor provides a gravel infiltration zone, a slotted channel or a direct connection to the plot's drainage system to prevent the formation of a frozen water table at the foot of the last riser.

Installation of block steps and execution of the slope on a concrete bed

On site, the layout of a garden staircase or building access does not tolerate interior formwork improvisation. The stride formula applied to external pathways requires a rigorous breakdown: two rises plus one tread must result in a shortened stride, generally between 63 cm and 65 cm, favoring low risers and generous treads to match the natural outdoor walking rhythm. The SIA 318 standard governs the geometric and qualitative requirements of external works, in particular the absolute regularity of heights over the entire flight. A variation of a few millimetres between two successive steps is the primary cause of stumbling.

  1. Earthworks and frost-free foundationExcavate the slope in tiers while respecting a minimum frost clearance according to the altitude of the plateau or the Pre-Alps. Install an untreated gravel foundation layer mechanically compacted in regular layers.
  2. Installation of the starting step on a footingPour a lean concrete backing with a damp-earth consistency at least 15 cm thick. Lay the first block step made of granite, sandstone or preformed concrete using a lifting clamp or a mechanical suction pad.
  3. Chalk line adjustment and gradingCheck the transverse level with a mason's rule and immediately apply the drainage slope of 1.5% to 2% towards the step nosing using the digital spirit level. Tap the piece with a white rubber mallet without fracturing the edges.
  4. Overlapping and locking the flightEngage the upper step onto the heel of the previous one with an overlap of 2 cm to 3 cm. Maintain a recessed joint or lay on an elastomer strip to prevent stone-on-stone contact and allow thermal movement.

Frost resistance, surface roughness and flight-base drainage

Outdoors, the choice of material and the mechanical treatment of the upper surface determine user safety during the French-speaking Swiss winter. Stairs subjected to freeze-thaw cycles as well as de-icing agents must have a sufficient roughness class without accumulating organic impurities. Smooth, honed or simply sawn surfaces are prohibited for access steps: shot-blasting, bush-hammering or flaming are preferred, as they create a microscopic granular texture ensuring sole grip even under a thin film of wet snow.

Behavior of external step coverings in winter conditions
Material and finishFrost and salt resistanceAnti-slip behaviorRecommended use in CFC 411
Plain power-floated or polished concreteAverage (surface crazing)Dangerous once water-saturatedStrictly prohibited outdoors
Exposed aggregate or shot-blasted preformed concreteHigh if manufactured without capillary poresExcellent in rain and thawPublic paths, ramps and tiers
Flamed / bush-hammered granite or gneissTotal, insensitive to de-icing saltsVery good grip coefficientMain access stairs and villas
Split or raw sawn natural sandstoneVariable depending on bed porosityCorrect, risk of flakingPrivate gardens protected from damp shade

In situations where open or metal steps complete the landscaping, the integration of an attached anti-slip profile or a grooved angle bead at the step nosing reinforces grip. For natural stone and concrete, scrupulous compliance with the recommendations of the SIA 318 standard ensures that the structure withstands freeze cycles without edge spattering or bedding detachment, preserving the durability of the landscaping investment.

Management of non-conformities: stagnant water, reverse slope and remedial work

On a completed external staircase, the appearance of a residual puddle or a counter-slope reveals a critical execution defect. When rainwater stagnates on the tread instead of draining naturally towards the nosing, nighttime re-freezing turns the steps into a particularly dangerous icy surface. This drainage defect commonly stems from differential settlement of the lean concrete bedding layer, poor compaction of the frost-free sub-base gravel, or a reading error with the optical level during the initial shimming of the block steps.

  1. Diagnosis with a straightedge and levelMeasure the actual slope of each step using a one-metre level and check the stride rule over the entire flight. A height deviation exceeding standard tolerances creates a stumbling hazard.
  2. Mechanical removal of the block stepRig and remove the defective step using suitable lifting clamps, working from above or below so as not to destabilize neighboring step nosings.
  3. Remedial work on the bedding layerChisel off non-adhering foundation concrete, clean away all dust and rebuild a fresh base of lean concrete or draining laying mortar with the required slope of one to two percent towards the downstream side.
  4. Reinstallation and altimetric checkTap the element with a mallet without bouncing on shims, check alignment with a chalk line and test drainage effectiveness by watering.

When the surface condition of sawn natural stone or preformed concrete proves too slippery in the rain or frosty weather, mechanical treatment by in situ bush-hammering, shot-blasting or superficial flaming restores the necessary roughness without having to dismantle the structure. If the dispute concerns out-of-plumb alignments or excessive tread variations between the start and finish, the SIA 118 standard defines the procedures for the notice of defects and remedial work in consultation with the site management.

Frequently asked questions

What is the mandatory minimum slope to apply to the tread of an external step?

The SIA 318 standard recommends a forward-directed runoff slope of 1% to 2% on each individual step, i.e., a drop of 3 to 7 millimetres over a conventional tread of 35 centimetres. This gradient guarantees the rapid evacuation of rainwater and melted snow, preventing surface stagnation which promotes the rapid formation of patches of black ice at the slightest cold snap.

Why is the modified Blondel formula applied to a garden staircase?

Outdoors, the stride naturally lengthens to offer more relaxed and secure movement than indoors. While the basic formula remains two rises plus one tread, the target is a sum close to 64 to 66 centimetres, with reduced risers between 12 and 15 centimetres and generous treads of 34 to 40 centimetres, thus avoiding the feeling of climbing on long flights.

How should the connection at the foot of the flight be treated to prevent soil erosion?

The foot of the stairs receives the accumulated runoff from all the steps. It is imperative to install a frost-anchored concrete footing there, supplemented by a draining gravel backfill bed or a slotted channel connected to surface water drainage. Without this interception device, water infiltrates under the first riser, erodes the setting bed and causes the gradual loosening of the stair start.

Which surface treatments guarantee the anti-slip properties of natural stone steps in winter?

To prevent slips without altering the durability of the material, rough finishes produced at the quarry are preferred: flaming, shot-blasting, bush-hammering or fine sandblasting. Polished or simply honed finishes are to be strictly prohibited outdoors. On limestone or granite slabs already installed, applying an in situ chemical or mechanical anti-slip treatment improves grip in wet weather.