Skip to content
Website
🧱 CFC 411Earthworks, foundation and compactionChapter 4 of 10 in the section

Geotextile: separation of a fine-grained soil, fine particle pumping and sheet overlap

This chapter guides you through the dimensioning and installation of a separation geotextile on soft soil. You will learn how to neutralise fine particle pumping under traffic, select the geotextile class suited to the earthwork constraints, and plan sheet overlaps according to recognised requirements to ensure the durability of the formation level.

Key takeaways

  • The upward migration of clayey fines clogs the crushed gravel and destroys the load-bearing capacity of the foundation.
  • Standard SIA 318 governs the physical separation between soft supporting soil and compacted crushed gravel.
  • The choice of separation or reinforcement geotextile depends on the granularity and traffic.
  • The sheet overlap varies from thirty to fifty centimetres depending on the ground's load-bearing capacity.

Understanding fine particle pumping and the degradation of compacted crushed gravel

On a private road platform or vehicular courtyard, unbound 0/45 crushed gravel ensures pressure distribution towards the natural ground. When this formation level consists of water-sensitive fine soil, such as silt, weathered marl or lacustrine clay, the absence of a physical interposition triggers a destructive mechanical phenomenon. Under the effect of rolling loads combined with water saturation of the subgrade soil, pore water pressures create a direct pumping effect. Fine particles from the supporting soil migrate vertically through the voids of the stonework.

Fine particle pumping
Ascending migration of fine soil particles (silts, clays) towards the pores of the foundation crushed gravel under the combined action of pore water and repeated dynamic loading cycles.

This rise of fines into the foundation irretrievably alters the behaviour of the granular layer. By infiltrating the interstices of the mineral skeleton, the clay fraction lubricates the contact points between the edges of the crushed aggregate. The granular interlocking gives way, internal friction collapses and the overall modulus of elasticity plummets. As soon as the fines content of the sub-base exceeds a critical threshold, the foundation loses its load-spreading capacity and begins to punch through.

Contamination results in marked ruts, hollows where water stagnates, and then settlement of paving elements. In an external works project executed in accordance with standard SIA 318, the interposition of a geotextile membrane forms an impassable permeable filter for soil grains, while allowing gravitational water to pass through towards outfalls or the drainage network.

Geotextile selection and sheet overlap rules on the construction site

The choice of a geotextile is not limited to its mass per unit area, but depends on its tensile strength and dynamic puncture resistance. On low-consistency soil, a needle-punched polypropylene non-woven fulfils the function of pure separation and filtration. When the soil exhibits a very low bearing capacity index or marked heterogeneity, the use of a separation and reinforcement geotextile, often in the form of a high-tenacity woven fabric or geogrid composite, is essential to take up tangential stresses and limit rutting during the passage of the first delivery trucks.

Geotextile selection criteria according to the nature of the supporting soil
Nature of the groundMechanical behaviourRequired functionRecommended membrane type
Silt or plastic claySensitive to puncture and waterSeparation and filtrationThick needle-punched non-woven
Peat soil or soft fillVery low load-bearing capacity under loadReinforcement and separationWoven geotextile or composite with geogrid
Compact silty crushed gravelMedium to stable bearing capacitySafety anti-contaminantStandard non-woven of suitable class

The performance of the structure depends directly on the continuity of the geotextile barrier. Approximate unrolling or sloppy joints cause the strips to move apart during the levelling of the crushed gravel with the backhoe bucket. Sheet overlap must scrupulously follow the constraints of the formation level: the more deformable the subgrade ground, the greater the overlap must be to prevent any detachment when pushing the backfill material.

  1. Preparation and grading of the subgrade levelRemove large roots and protruding rock blocks. Level the platform with a roof or crossfall profile to direct water towards external kerbs or swales.
  2. Unrolling and anchoring of stripsLay the rolls in the direction of travel of the trucks to prevent tyres or tracks from turning back the membrane. Secure the edges using metal staples or shovelfuls of gravel.
  3. Checking longitudinal and transverse overlapsMaintain an overlap width of 30 cm on stable ground, and increase up to 50 cm minimum on plastic or highly deformable ground, without any discontinuity.
  4. Unloading and spreading of crushed gravelAlways unload sub-base materials from the front of the area already backfilled. Never drive mechanical plant directly onto the bare geotextile.

Installation of the geotextile on the formation level in accordance with standard SIA 318

The installation of a separation and reinforcement geotextile takes place immediately after the levelling of the earthwork formation level. On external works subjected to the traffic of light vehicles, maintenance plant or private delivery trucks, standard SIA 318 sets out the ground preparation requirements before bringing in foundation materials. The formation level must present a flat surface, free of roots, stumps, demolition waste and protruding rock blocks. A sharp protrusion that is not cleared will pierce the membrane under the mass of the crushed gravel and initiate a tear as soon as transport plant passes over.

The geotextile does not compensate for neglected earthworks: it preserves the integrity of the granular structure only if the underlying sub-base is cleared of soft clay pockets or residual topsoil. When the in-situ soil shows a very low bearing capacity or high water content, direct rolling of trucks or excavators on bare soil destroys natural compactness through shear. Geotextile rolls must be stored protected from direct sunlight and unrolled as work progresses, parallel or perpendicular to the axis of the track, depending on the geometry of the plot and the cross-section.

  1. Cleaning and dressing of the platformManually remove sharp stones exceeding 30 millimetres and fill in ruts created by the excavator tracks with stable material.
  2. Unrolling and tensioning of the membranePull the sheet by hand to eliminate longitudinal creases. A creased geotextile forms interstitial water pockets and creates weak points under the compacted crushed gravel.
  3. Temporary anchorage against wind and displacementSecure the edges using mild steel staples driven into the ground or place mounds of gravel at regular intervals of three to four metres.
  4. Checking sheet overlapMeasure the actual overlap between successive strips before any delivery of granular material, strictly respecting the direction of progress of the levelling.

Crushed gravel levelling, compaction and puncture prevention

The absolute prohibition against driving a dumper truck or loader directly onto the uncovered geotextile constitutes the primary construction site rule. Unloading untreated crushed gravel, such as 0/45 limestone or certified recycled gravel, is carried out exclusively using the push-out advancing method. The truck empties its load onto the already spread crushed gravel, and then the levelling plant pushes the materials forward over the tensioned geotextile, forming a continuous protective cushion. This method avoids direct shearing of the synthetic fibres under turned tyres.

The thickness of the first layer of crushed gravel determines the mechanical survival of the textile. A layer that is too thin transmits excessive point loads during the passage of vibrating rollers, puncturing the membrane against the compacted ground. Standard SIA 318 and professional recommendations advise a minimum loose thickness of 20 to 30 centimetres before the start of any heavy compaction. For the first pass, the vibration of the roller must be deactivated or set to low amplitude so as not to liquefy the underlying fine soils, which would initiate forced mechanical pumping through the pores of the felt.

Implementation parameters according to formation level bearing capacity (external works CFC 411)
Nature of supporting soilMinimum overlapPrimary function of the felt1st pass crushed gravel thickness
Stable silty soil, well drained30 cmSeparation and filtration20 cm compacted
Wet clay or compressible silt50 cmSeparation, filtration and reinforcement25 to 30 cm loose
Heterogeneous private road fill40 cm stapledAnti-contamination and distribution25 cm loose
Weathered or shaly rocky formation level30 cmAnti-puncture protection20 cm compacted

When the ground exhibits extreme sensitivity to temporary heavy traffic, the use of a combined geotextile associating a filtering non-woven membrane and a woven reinforcement geogrid provides high tensile strength. This reinforcement blocks the lateral displacement of foundation aggregates, improves the overall deformation modulus and prevents deep rutting. If a tear occurs during the pushing of the crushed gravel, it is required to clear the soiled area one metre beyond the rupture, lay a new patch overlapping the breach by 50 cm all around, and then level the aggregate again.

Management of defects: tears, sheet slippages and excavation areas

On site, an installation incident or local rupture of the geotextile membrane permanently compromises the physical separation between the soft infrastructure and the granular sub-base. Two major causes lead to these defects: the slippage of a sheet caused by front-pushing of crushed gravel with the bucket without adequate support, and tearing by dynamic puncture during direct rolling of wheeled plant on a crushed gravel layer that is still too thin. As soon as a visual indicator reveals the original soil through the aggregates, or mud rising appears after driving rain, corrective intervention is essential before any passage of the vibrating plate or tandem roller.

To clean a perforated or displaced area, the team manually clears the soiled crushed gravel with a shovel, without damaging the underlying membrane. Compacting a polluted crushed gravel-silt mixture is ruled out, because the fines content would destroy the internal friction angle of the graded aggregate. If the geotextile is pierced or torn, cut out a repair patch from a new roll of the same non-woven or woven material. This patch must overlap the tear by at least fifty centimetres all around, or even a full metre if the formation level proves particularly soft or unstable. Cover the patch with clean crushed gravel advancing diagonally, as work progresses, to secure the membrane without creasing it or displacing the overlap.

When the formation level exhibits a generalised hydraulic cushion phenomenon before installation, the simple separation membrane is no longer sufficient. Laying a geotextile on liquid mud traps pore water and prevents any subsequent compaction of the foundation layer. It is then appropriate to strip out unstable silty pockets, excavate the unsuitable material and reconstitute the level with draining backfill crushed gravel or coarse rockfill wedged in place before redeploying the separation and reinforcement geotextile, complying with the requirements of standard SIA 318 for external works.

Frequently asked questions

Can dumpers or loaders be driven directly onto the unrolled geotextile?

No, direct rolling of plant on the bare geotextile is prohibited. The passage of tyres or tracks causes shear stresses that stretch, crease or tear the membrane. Earthmoving plant must systematically travel on a protective crushed gravel layer spread progressively, with a minimum thickness of fifteen to twenty centimetres. This method guarantees the integrity of the separation function and prevents dynamic puncture on the rocky edges of the soil.

What minimum overlap should be applied between two sheets on soft or compressible soil?

On a stable and well-levelled platform, an overlap of thirty to fifty centimetres is generally sufficient. On the other hand, if the underlying ground is very soft, wet or compressible, increase this overlap up to eighty centimetres, or even a full metre. The pressure exerted during the levelling and compaction of the crushed gravel risks pulling apart unattached sheets, creating a fault conducive to the rise of fines and the destabilisation of the foundation.

Should geotextile sheets be stapled to the formation level before dumping the crushed gravel?

Mechanical stapling or ballasting by piles of rubble is strongly recommended. In the absence of fixing, wind or material thrust during the dumping of crushed gravel causes the membranes to slide and reduces the overlap width without workers noticing under the granular layer. Placing metal staples or a few shovelfuls of gravel on the joints ensures rigorous maintenance of the sheets during levelling with the mechanical excavator.

How to differentiate a separation geotextile from a surface drainage felt?

A thin felt used to wrap drainage pipes or for horticultural filtration has puncture and tensile strength that is too low for a vehicular foundation. For separation under crushed gravel according to standard SIA 318, a thicker felt or a specific woven fabric presenting a robustness class adapted to mechanical stresses is used. Laying a felt that is too light inevitably leads to its perforation during the compaction of 0/45 crushed gravel.

Texts and standards cited

  • norme SIA 318External works: implementation requirements for earthworks, foundation layers and private road infrastructure and landscaped areas.

In the same section