Key takeaways
- Stripping separates the topsoil horizon from the subsoil to preserve fertility and avoid disposal costs.
- Topsoil heaps must not exceed two metres in height to prevent biological asphyxiation.
- The ADWO requires priority recovery of unpolluted soil and excavation materials on the landscaped site.
- Sorted mineral excavation material is used for technical road embankments or private landscape modelling.
Separate topsoil from excavation material right from the stripping stage
On a plot intended for external works, every cubic metre excavated has a precise technical and economic destination. Superficial stripping targets the topsoil horizon, which is rich in micro-organisms, earthworms and organic matter. Just below lie the transition horizon and then the mineral subsoil, consisting of gravel, silt or compacted moraine. The Ordinance on the Limitation and Elimination of Waste (ADWO) and the Ordinance on Soil Pollution (OSol) stipulate that these fractions must be recovered in a differentiated manner. Any premature mixing destroys the agronomic properties of the arable layer and downgrades the whole into heterogeneous excavated material.
- Unpolluted excavation material
- Mineral material extracted from the natural subsoil beneath the arable layer, free from anthropogenic pollutants, suitable for technical backfilling or terrain modelling in accordance with ADWO requirements.
- Identifying soil horizonsIdentify the thickness of the topsoil using a smooth bucket or spade before bringing in heavy machinery. Note the variations in thickness between old fill areas and natural ground.
- Selective stripping with a backhoeWork backwards using a crawler excavator equipped with a wide, toothless grading bucket. Avoid any tracking of the caterpillar treads over the topsoil layer so as not to shear the porous structure.
- Separate removal of layersLoad the topsoil separately from the mineral excavation material to their respective temporary storage areas, marked out by stakes and signs on the construction site.
- Visual check for non-contaminationContinuously check for the absence of demolition waste, foreign bodies or hydrocarbon stains. Immediately isolate any suspicious area for analysis prior to reuse.
Store windrows without asphyxiating the soil and reuse excavated material
Temporary storage of topsoil is the most critical phase for the survival of the soil biotope. Piled up under excessive weight or waterlogged, the soil becomes compacted, the capillary pores close and oxygen disappears in favour of an anaerobic environment. Nitrifying bacteria die, organic matter ferments and the soil takes on a greyish hue accompanied by a characteristic putrefaction odour. Such material loses its structural cohesion, collapses at the first watering and becomes unsuitable for the immediate rooting of lawns and shrub beds.
| Excavation category | Maximum pile height | Profiling and protection | Planned reuse on the plot |
|---|---|---|---|
| Topsoil (upper layer) | 1.50 m to 2.00 m | Roof shape, light smoothing with bucket, sowing if stored for more than six months | Finishing of green spaces, flower beds, lawn bed |
| Subsoil (intermediate layer) | 2.00 m to 2.50 m | Aerated trapezoidal windrows, peripheral drainage at the base of slopes | Agronomic transition layer, adjustment of planted levels |
| Stony excavation material / moraine | Limited by slope stability | Regular compact piles, stable sloping, protection against run-off water | Private road foundation backfill, topographic modelling, kerb setting |
Unpolluted mineral excavation materials resulting from the levelling of pedestrian paths, private garage accesses or terraces must be reintegrated into the site's earthwork volumes. In accordance with ADWO principles, crushing or mobile screening on site makes it possible to produce road foundation materials or backfilling materials under paving. Rigorous sorting carried out from the very first shovelled load guarantees a balanced mass balance on the plot, reduces the carbon footprint associated with transport and eliminates the disposal costs for high-grade materials.
Mechanical sorting and reuse of mineral excavation materials on the plot
The rigorous application of the ADWO to external works requires priority recovery of earthy and mineral materials directly at the extraction site. Unpolluted excavation material, originating from the geological layers underlying the topsoil (horizon C or rocky and morainic substrate), represents a considerable volume during levelling earthworks, terrace creation or access roads. This material does not possess the agronomic properties required for green spaces, but constitutes an essential technical resource for reconstituting slope shapes, backfilling depressed areas or establishing the foundation for future pathways.
Efficient reuse on site relies on immediate mechanical sorting as work progresses. The contractor uses a screening bucket mounted on the backhoe or installs a compact double-deck mobile screening plant when volumes exceed a hundred cubic metres. This operation separates the fine fraction (silty or sandy) from rock blocks and morainic pebbles. Coarse elements larger than 150 millimetres are crushed or set aside to create drainage masses, stabilization berms or landscaped slope riprap. The screened gravel fraction is used to calibrate non-load-bearing technical backfills without resorting to external supply materials.
| Particle size fraction | Nature of material | Destination on external works | Execution requirement |
|---|---|---|---|
| 0 to 45 mm (screened) | Clean morainic run-of-mine material | Light road sub-base, paths and terraces | Methodical compaction in passes with a vibrating plate |
| 45 to 150 mm | Earthwork stones and pebbles | Transition masses, foundation drainage layers | Installation without fines retention to preserve permeability |
| > 150 mm | Erratic boulders, large rocky elements | Low riprap, toe of slope stabilization | Individual placement with sorting grab on stable base |
| Cohesive fine fractions | Subsoil silts and clays (horizon B/C) | Deep terrain modelling, compensatory profiles | Execution at optimum water content, outside traffic areas |
To guarantee the required bearing capacity under paving and light vehicular traffic, the reused mineral excavation spoil must be completely free of plant inclusions or roots. The accidental introduction of humus into a foundation layer leads to delayed differential settlement due to biological decomposition of organic matter, causing kerb subsidence and cross-profile deformation. The foreman continuously monitors the excavation area to prevent mixing between the silty sub-base and the stony layers.
Biological preservation of topsoil stockpiles and reinstatement
The preservation of topsoil (horizon A) during the intermediate waiting phase directly controls the subsequent success of lawns and plantings. Uncontrolled storage destroys the crumbly structure of the soil within a few weeks. If the height of the windrow exceeds the technical safety limit, the weight of the soil itself and the lack of oxygen renewal in the core of the bund lead to anaerobic fermentation. Aerobic bacteria and mycorrhizal fungi disappear, the soil takes on a characteristic greyish hue and emits an odour of hydrogen sulphide. Asphyxiated soil loses its mechanical cohesion and agronomic power, making it unsuitable for direct revegetation without costly soil conditioning and prolonged aeration work.
- Checking the drainage of the mineral supportBefore any reapplication, check the moisture condition of the formation level and underlying ground. No spreading must be undertaken on soil saturated with water or waterlogged by recent precipitation.
- Mechanical transition looseningPass the tines of a subsoiler or the points of a ripper over the underlying mineral layer to a depth of 20 to 30 centimetres to break the compaction pan created by machinery traffic.
- Retrieval and spreading backwardsCollect the topsoil stored in windrows using a backhoe equipped with a smooth grading bucket. Deposit the material moving backwards, never allowing the machine's tracks or wheels to run over the spread soil.
- Finishing levelling without heavy rollingSpread the prescribed thickness in successive passes. Use exclusively a light machine with low ground pressure for final surface smoothing, prohibiting the passage of vibrating compactors.
By organising the construction site according to this closed cycle, the landscape contractor optimizes the earthwork mass balance from excavation to landscaping finishes. Topsoil stored in an aerated manner retains its native biological activity, enabling vigorous rooting of seedlings from the very first season. At the same time, on-site use of mineral excavation gravel for modelling profiles and secondary infrastructure eliminates lorry rotations on the municipal road network and removes the purchase of supply materials, bringing the fundamental circular economy objectives set by environmental legislation to life on the ground.
Procedures in the event of accidental mixing or soil degradation
When stripping is poorly executed or an equipment operator mixes the arable layer with silty subsoil or mineral run-of-mine material, the financial loss quickly adds up to thousands of francs. Within the meaning of the ADWO, topsoil mixed with inert excavation spoil or demolition residues loses its status as a noble, recoverable living soil. It is then automatically reclassified as mixed excavation material, unsuitable for landscaping recultivation, or even as mineral waste intended for disposal in a Type B landfill. The additional cost for the construction site includes controlled-channel transport, landfill taxes and the essential purchase of certified replacement topsoil to carry out the external works.
In the event of severe biological asphyxiation caused by non-compliant pile heights or the repeated passage of dumpers over stockpiles, the soil degrades in depth. The soil takes on a characteristic greyish colour, gives off foul-smelling hydrogen sulphide odours and loses its crumbly structure essential for plants. Mechanical retrieval must never be carried out by direct spreading over future planted areas. The earthworks team must spread the windrows to a maximum thickness of fifty centimetres during a dry weather window, then carry out aeration harrowing to reactivate aerobic microfauna prior to any planting.
- Interruption of earthworks and isolationStop earthworks at the exact location of the accidental mixing. Mark out and separate the altered volumes using a witness bund to prevent any contamination of clean stripped topsoil stockpiles.
- Joint inspection record and measurementRecord the event in the site diary with supporting photos. In accordance with SIA 118 standard, jointly calculate the altered volumes with the site management to prevent any disputes regarding measurements.
- Guidance into ADWO channelsEstablish the tracking slip for disposal through an approved channel in accordance with the ADWO. In the presence of suspicious residues or questionable fills, have a chemical analysis performed by an accredited laboratory before any transfer off-site.
Frequently asked questions
What maximum height should be observed when storing topsoil without risking soil asphyxiation?
For temporary storage not exceeding a few months, topsoil windrows must not exceed two to two and a half metres in height, with stable sloped gradients. If storage lasts longer than one season, it is recommended to limit the height to one and a half metres and sow the pile with a mixture of grasses and legumes. Beyond these dimensions, pressure and lack of oxygen destroy the biological structure in depth.
What does the ADWO say about the direct reuse of stripped topsoil on a construction site?
The Waste Ordinance, ADWO, requires the full recovery of earthy materials resulting from the stripping of the arable layer and subsoil if they are clean. The text prohibits treating fertile soil as ordinary backfill or sending it to landfill when reuse on site is feasible. This legal obligation promotes local resources and forces builders to plan earth movements to reuse soil horizons on site.
How to recover mineral excavation material extracted beneath topsoil?
Unpolluted excavation materials from underlying layers must be sorted upon extraction. Freed from all arable soil, sands, gravels and mineral run-of-mine materials can serve as levelling backfills, foundations under secondary roads or technical sub-bases after mechanical screening on site. This rigorous sorting greatly reduces volumes sent to Type B landfills and avoids ordering new quarry gravels to backfill the project's surroundings.
Why is it forbidden to drive over topsoil during stripping?
The repetitive passage of heavy construction machinery such as backhoes or dump trucks compacts the macro-pores of arable soil and irremediably destroys its permeability. Stripping must be carried out in reverse, with the bucket open and smooth teeth, without the tracks running over the unexcavated area. Soil compacted before storage loses its natural fertility, becomes impermeable to rainwater and promotes root rot as soon as it is spread for future plantings.
Texts and standards cited
- norme SIA 118General conditions for the execution of construction work and joint measurement records
- OLEDRules for sorting on site and recovery of earthy and excavation materials