Key takeaways
- The countersigned maintenance sheet formally transfers the responsibility for watering to the client.
- JardinSuisse conditions exclude the establishment guarantee without verifiable watering and appropriate maintenance.
- First-season watering requires a massive deep application at the root ball level.
- Early formative pruning balances the crown without mutilating the leading axes of young trees.
Formalise the transfer of custody and apply JardinSuisse professional rules
Upon acceptance of the work in accordance with SIA 118, the client takes possession of the landscaped surfaces. For inert works such as paving or a dry-stone wall, the observed condition remains stable. For plants, however, acceptance marks the beginning of a critical phase: transplantation stress. A woody plant takes a full season to regenerate its root hair network beyond its initial root ball. If water inputs are interrupted or incorrectly measured during summer heatwaves, the drying out of foliage tissues occurs within a few days, leading to the death of the plant.
In the practice of construction sites in Western Switzerland, the client instinctively associates the decline of a tree with a supply defect or poor planting attributable to the contractor. Without conclusive documentation certifying the transmission of maintenance instructions, the landscaper is left defenceless against demands for free replacement. However, the professional recommendations issued by JardinSuisse specify that the establishment guarantee cannot be invoked if the plants have not received the essential watering care, or if extreme climatic conditions have occurred without corrective intervention by the owner.
The maintenance sheet must constitute a mandatory contractual annex to the final account or the acceptance report. It lists precisely the duties incumbent upon the site operator from the very first day following the completion of the work. This document enumerates the watering frequencies, the obligation of manual weeding at the base of the root balls, the monitoring of staking after windstorms, and the prohibition against spreading phytosanitary products or de-icing salts in the immediate vicinity of the watering basins.
- Signing by the client with a handwritten mention of having read and understood the watering instructions.
- Explicit reminder of JardinSuisse general conditions concerning the forfeiture of the guarantee in the event of watering negligence.
- Standard schedule of maintenance interventions for the twelve months following the acceptance of the work.
- Priced proposal for a completion and maintenance contract if the client declines to carry out the care themselves.
Manage first-season watering, root control and formative pruning
First-season watering does not consist of superficially moistening the soil with an oscillating sprinkler. The entire volume of water must penetrate the volume of the original root ball and the peripheral loosening zone. For a standard tree of size 16/18 or 18/20, requirements range between 50 and 80 litres of water per intervention during the summer period, delivered on a weekly or bi-weekly basis depending on the permeability of the existing soil. The water must be channelled by an earth watering basin with a minimum relief of 15 centimetres, calibrated to the diameter of the planting pit.
| Plant type | Water volume per application | Frequency in hot, dry weather | Distribution system |
|---|---|---|---|
| Standard tree (circumference 14 to 20 cm) | 50 to 80 litres | 1 to 2 times per week | Closed basin or perforated watering sleeve |
| Isolated container shrub (3 to 10 l) | 10 to 15 litres | 2 times per week | Direct base watering at low pressure |
| Hedgerow or mixed hedge (per linear metre) | 15 to 25 litres / lm | Every 3 to 5 days | Self-regulating drip line or micro-porous hose |
| Perennials and ornamental grasses (per m²) | 10 to 15 litres / m² | 2 to 3 times per week | Soft watering rose, no forceful jet |
- Visual check of deep moistureProbe the soil using a soil auger or manual core sampler to a depth of 30 centimetres directly plumb with the root ball. The soil must form a plastic ball without free water oozing out. Permanently saturated soil asphyxiates the root hair and causes root rot.
- Checking and adjustment of stakingCheck the tension of biodegradable straps and collars after prevailing winds. The trunk must not rub against the stakes, and the root collar must not undergo any shearing movement that would tear the developing rootlets.
- Formative pruning at the end of the first winterRemove branches competing with the main leader, eliminate dead, broken or inward-facing shoots within the crown. Never top the axial leader on shade trees to preserve the natural habit of the species.
- Replenishing organic mulchAdd clean wood chips to a thickness of 7 to 10 centimetres, ensuring the root collar is cleared within a radius of 10 centimetres to prevent attacks by wood-decaying fungi and rodent damage.
The maintenance sheet handed over against signature: technical content and evidentiary value
As soon as the planting work is completed, the plant installation enters a critical phase where the survival of the specimens depends on the care given to the soil and the root system. If the client or property manager receives no precise protocol, the plants wither due to under-watering, excess water or lack of pruning. In the event of a dispute, the absence of written instructions systematically leads the client to claim a supply defect or poor execution. The maintenance sheet handed over against a formal receipt constitutes the pivotal document that proves the transfer of know-how and transfers operational responsibility.
This technical document is not limited to a summary instruction leaflet. It details the required interventions, seasonality, recommended water volumes by plant type and visual criteria for water or mechanical stress. To possess probative legal value during the final account or in the event of damage, the sheet must be initialled and signed in two copies during the acceptance report of the work, pursuant to the delivery rules provided by standard SIA 118.
| Plant item | First-season watering instruction | Formative pruning and coppicing | Vigilance points for the client |
|---|---|---|---|
| Standard trees and multi-stemmed trees (whips, root balls) | Weekly deep application of 50 to 100 litres per specimen in the basin or via the aeration tube, from April to October. | Removal of competing branches, sucker growth on the trunk and maintenance of the main leader during the dormant period. | Mandatory maintenance of the retention basin; visual check of the loosening of guy ropes and staking collars. |
| Hedgerows and shrub beds | Generous watering via drip irrigation or porous hose: 15 to 25 litres per linear metre, 2 times per week in dry weather. | Tip-pruning of terminal shoots at the beginning of the first summer to force basal branching; cleanliness pruning on dead wood. | Checking the thickness of organic mulch (chips or bark) to limit evaporation and block weeds. |
| Lawn surfaces (sowing or turfing) | Daily superficial moistening for the first three weeks, followed by spaced-out but generous watering (10 to 15 mm per pass). | First high mowing as soon as the grass blade reaches 8 to 10 cm, with a sharpened blade, without excessive collection if mulching is controlled. | Prohibition of foot traffic during germination; prohibition of fast-release nitrogen fertiliser during summer heatwaves. |
Responsibilities, establishment guarantee and contractual management according to JardinSuisse
In construction contracts governed by Swiss construction standards, the plant establishment guarantee is never absolute or automatic. The general conditions of the umbrella organisation JardinSuisse specify that the establishment guarantee applies only if the work included appropriate soil preparation, the supply of plants by the company and, crucially, the joint conclusion of a completion maintenance mandate or strict compliance with watering directives notified in writing.
To protect both parties, the recommended professional approach consists of offering the client a watering and formative pruning contract for the first operational season. If the client refuses this service for economic reasons and prefers to carry out the maintenance themselves, this refusal must be expressly recorded in the handover report of the work, accompanied by the maintenance sheet.
- Joint handover of instructionsHave the client sign the watering protocol, pruning schedule and usage restrictions on the day of provisional or final acceptance of the outdoor landscaping.
- Written notification of maintenance refusalIf the client declines the first-season maintenance package, record formally that material custody and care obligations are entirely incumbent upon them in accordance with the Code of Obligations.
- Establishment assessment at bud breakOrganise a control visit in the spring following planting. In case of plant failure, check root ball moisture, anchoring and root cutting to establish the technical causes of the decline.
- Handling of reservations or invoicingReplace specimens suffering from a hidden horticultural defect free of charge. Invoice the replacement on a time-and-materials basis or according to the price schedule when a lack of water management or unsuitable pruning is attested.
The management of the first season is therefore based on a transparent contractual balance: the company guarantees the vitality of the plant material delivered and the compliance of the planting in accordance with professional standards, while the client is responsible for water supply and compliance with vegetative cycles as from acceptance of the work.
Management of establishment disputes: joint inspection record and enforceability
When plants decline during the first twelve months, the client almost systematically attributes the failure to the quality of the supply or the planting. Without a formal document established at acceptance, the landscaper finds themselves defenceless against this challenge. Activating the usual guarantees of the trade, as defined by the contractual conditions of JardinSuisse, nevertheless requires a strict distinction between a hidden plant defect and post-planting care deficiencies.
- Convene a joint inspection recordAs soon as foliage desiccation or delayed bud break is reported, schedule an on-site visit. Do not replace any specimens before having jointly inspected the condition of the root collar, the moisture of the root ball and the root anchorage in the presence of the client.
- Check the watering profile and mechanical conditionProbe the soil with a soil auger to a depth of forty centimetres directly at the root ball and outside the root ball. A shrunk and powdery root ball proves a break in the first-season watering, whereas a sulphide odour indicates asphyxiation due to stagnant water.
- Expose the absence of prescribed careConfront your observations with the instructions provided. Non-compliance with watering frequencies, abandonment of weeding at the base or improvised out-of-season formative pruning release the executor from liability if the notice was duly notified.
The maintenance sheet handed over against signature constitutes the legal pivot of your protection. Annexed to the acceptance report governed by standard SIA 118, it formally transfers the custody of the living work to the client. If the latter has refused to sign a watering and crop monitoring contract with your company, this release attests that they knowingly assumed the agronomic management of the plants. In the event of a persistent deadlock, resorting to a neutral expert appointed by JardinSuisse will make it possible to establish scientifically whether the decline results from water desiccation attributable to the client or an original root defect.
Frequently asked questions
What should be done if the client refuses to sign the maintenance sheet at acceptance?
Immediately record this refusal on the acceptance report of the work, specifying that the document was handed to them in person. Then notify them of the complete technical sheet by registered mail within forty-eight working hours. This written traceability proves that the client had the essential watering and maintenance instructions, thus releasing the landscaping company from any presumption of fault in the event of subsequent decline.
How can a lack of water be technically proven in the face of a claim?
During the joint inspection record, carry out a spade or auger probe down to the base of the planting hole. Take a sample of substrate from the core of the original root ball and the immediate periphery. A completely dry root ball surrounded by moist backfill soil demonstrates the absence of targeted saturation watering in the basin. Take dated photographs of necrotic roots and the shrunken root felt.
Does the JardinSuisse establishment guarantee apply after a harsh winter or a heatwave?
The usual JardinSuisse establishment conditions expressly exclude damage caused by force majeure, including exceptional late frost episodes, extreme droughts with municipal water restrictions, as well as pest attacks occurring after delivery. The guarantee covers only the intrinsic viability of the plant at the time of its delivery and planting, subject strictly to normal cultural care having been applied.
Is the first formative pruning part of the initial planting service?
The planting pruning intended to balance the ratio between the root volume and the crown is included in the installation. On the other hand, the formative pruning taking place during the first growing season falls under completion maintenance. If this service has not been explicitly ordered via a separate crop monitoring contract, it is entirely incumbent upon the client in accordance with the technical directives provided.
Texts and standards cited
- norme SIA 118General conditions for the execution of construction work, governing the acceptance of the work, transfer of risks and exercise of rights in the event of defects.
- JardinSuisseGeneral delivery conditions and professional customs for landscaping work, setting the limits of application of the plant establishment guarantee.