Machinery, safety and external construction site management: the execution standard

Intended for team leaders, foremen and site managers in external works, this section compiles operating rules for earthwork machinery and the management of landscaping construction sites. It sets out protocols for co-activity between machines and pedestrians, the stability of unshielded excavations, the physical protection of teams against heavy handling and vibrations, as well as rigorous spoil logistics in accordance with federal safety ordinances.

  • 10chapters
  • 22 000words
  • 6sections in the training course
  • 60chapters in total

Key values to remember 4

OTConst art. 68

1 m 50

Maximum depth of an unshielded excavation requiring compliant sloping

OTConst art. 71

1 m

Minimum mandatory free width at the top of a sloped excavation

OTConst art. 71

50 cm

Minimum free clearance strip at the edge of a shored trench

Suva guidelines

25 kg

Indicative unit mass above which manual handling requires mechanical auxiliary means

Scope of application and demarcation of construction site responsibilities

External works and private roads (CFC 411) require rigorous safety management as soon as compact machines operate in confined spaces or in the immediate vicinity of workers on foot. The machine operator and the team leader share operational responsibility for the operating zone. This section deals exclusively with measures applicable to landscape works: movement of machinery on private plots, excavations for paths or terraces, light earthworks for low rockeries, management of inert waste and daily protection of workers against recurring physical risks.

Construction site management in external works requires a thorough command of the Ordinance on Construction Work as well as Suva guidelines. The primary objective is to eliminate the risk of crushing or striking during combined maneuvers of compact excavators and articulated dumpers. The excavated material generated must be managed in accordance with Swiss environmental rules to avoid disposal cost overruns related to illicit mixtures of topsoil and mineral materials.

Perimeter of intervention on external surfaces and structures
Work concernedCFC 411 Competence (External Works)Excluded trade branch (Boundary)
Excavations and trenchesIrrigation trenches and private road excavationsGeneral building excavation and deep shoring (CFC 201)
Retaining wallsLow gravity walls and vegetated landscape slopesCalculated reinforced concrete walls and soil-nailed walls (CFC 211.1)
Trafficable surfacesGranular foundations, interlocking paving stones and kerbsRoad asphalt surfacings under heavy communal traffic
DrainageSurface grading, swales and infiltration trenchesWastewater collectors and sub-slab connections (CFC 250)

Sequential organization of safety and operations management

To effectively use these ten technical chapters, the site manager must follow the chronology of risks encountered on site. The first three chapters deal with co-activity and the movement of mobile machinery. Excavators and dumpers constitute the main source of fatal accidents on restricted plots. The establishment of impassable turning zones and compliance with slope trajectories must precede any intervention, supplemented by municipal traffic sign permits as soon as the skip or boom extends onto the public sidewalk.

The following chapters cover excavations and the physical ergonomics of the teams. According to art. 68 OTConst, any excavation deeper than 1 m 50 that is not propped or shored must be sloped according to the nature of the soil. In addition, art. 71 OTConst requires leaving a horizontal strip of at least 1 m in width free at the top when the wall is sloped, preventing collapse under the weight of machinery or materials. These measures prevent instant burial during the installation of pipes or low wall foundations.

  1. Securing traffic routes and preliminary shoringOrganize separate traffic lanes, check bucket locking, monitor dumper blind spots and immediately slope any excavation exceeding 1 m 50.
  2. Prevention of musculoskeletal disorders and vibrationsDeploy mechanical clamps and vacuum lifters for kerbs weighing over 25 kg, alternate operators on vibrating plate compactors to limit accelerations transmitted to the upper limbs.
  3. Protection against climatic and mechanical aggressionsAdjust working hours during heatwaves, provide fresh water and shaded areas, enforce certified cut-resistant trousers for the combined use of chainsaws and brushcutters.
  4. Selective sorting of excavated materials and remediation of defectsIsolate topsoil in accordance with the waste ordinance to avoid downgrading to a mixed skip, and purge unstable sub-bases in the event of premature road subsidence.

The end of the operational cycle focuses on the rational evacuation of waste and the technical diagnosis of sub-base pathologies. Strict sorting on the construction site preserves company profitability by avoiding landfill taxes for mixed skips. If settlement occurs on a paved ramp after bad weather, repair requires going back to the source of the defect: dynamic plate load test for compaction control, purging of the contaminated formation layer and methodical reconstruction of the granular structure.

📘 Chapters in this section 10

Machinery, safety and management of the outdoor site

Around the excavator: slewing radius, blind spot, prohibited zone and eye contact

Secure the operation of compact excavators by mastering blind spots and restricted turning zones.

Machinery, safety and management of the outdoor site

The dumper: overturning on slopes, poorly distributed load, seatbelt and reversing

Avoid the destructive tipping of articulated dumpers on steep slopes of sloping plots.

Machinery, safety and management of the outdoor site

Working on the roadside: traffic marking, municipal permit and resident access

Obtain your municipal permits and effectively mark out your encroachments on the roadway without blocking local residents.

Machinery, safety and management of the outdoor site

The trench: depth without shoring, battering, exit ladder and collapse

Determine regulatory sloping gradients to work safely at the bottom of landscaping trenches.

Machinery, safety and management of the outdoor site

Handling elements: weight of a kerb, laying clamp, two-person work and back safety

Adopt laying clamps and lifting techniques to protect layers' backs over the long term.

Machinery, safety and management of the outdoor site

Vibrations: vibrating plate, rammers, daily usage time and permanent harm

Manage daily exposure to plate vibrations to protect your workers from irreversible vascular damage.

Machinery, safety and management of the outdoor site

The sun: heat stroke, skin cancer, water, shade and the hottest hours

Organize summer construction sites in the face of solar radiation to prevent severe illness and skin lesions.

Machinery, safety and management of the outdoor site

Cutting tools: projection, cut-retardant trousers, perimeter and chain kickback

Master the protective equipment and exclusion perimeters essential during intensive brush clearing and chainsaw work.

Machinery, safety and management of the outdoor site

Disposing of: plants, inert materials, soil, and the mixed skip you pay for twice

Separate soils from inert materials on site to eliminate exorbitant mixed skip invoices.

Machinery, safety and management of the outdoor site

The ramp is sagging: compaction diagnosis, excavation, removal of unstable soil and complete reconstruction

Identify compaction defects under subsided roadways in order to successfully complete your purge and final repair.