Key takeaways
- Standard clearance protects the building from water but blocks access for persons with reduced mobility.
- Flush access requires a drainage channel with a removable grating directly in front of the external threshold.
- The invert of the drainage channel must strictly be located below the lower edge of the door seal.
- The slope of the adjacent paving directs runoff water away from the glazed bay.
Regulatory clearance and accessibility: reconciling technical requirements
In external works subject to standard SIA 318, the transition between the paved area and the building envelope is a critical point for stormwater management. The general construction rule requires a minimum height difference between the finished external paving and the door threshold to prevent liquid water backflow, snow accumulation and splashing against joinery. This vertical gap provides an essential safety margin when wind drives beating precipitation against the glazing.
However, this conventional elevation directly opposes the barrier-free construction requirements defined in standard SIA 500. A step of more than two centimetres constitutes an insurmountable barrier for a wheelchair user or a person with reduced mobility. To achieve a zero-level threshold without compromising the healthiness of the structure, the landscape contractor must compensate for the absence of vertical clearance by integrating a high-performance surface linear drainage system, directly coupled with rigorous management of external slopes.
| Configuration | Ground / threshold clearance | Required external device | Accessibility compliance |
|---|---|---|---|
| Traditional raised threshold | 150 mm or more | Paving with simple two percent counter-slope | Non-compliant for barrier-free access |
| Intermediate lowered threshold | 50 mm | Drainage gravel strip or slotted channel | Passable only with attached ramp |
| Flush level threshold | 0 to 20 mm | Connected grating channel and falling slope | Compliant according to standard SIA 500 |
Implementation of the threshold channel and junction with the paving
Installing a channel in front of a French window or a flush entrance door cannot be improvised on the paving bedding layer. The drainage element must rest on a stable lean concrete foundation, structurally separated from the building masonry to prevent any thermal and acoustic bridging. The channel body must have a useful width suited to the volume of water collected along the façade, generally between 100 and 150 millimetres, with a grating whose mesh does not trap pushchair wheels or walking sticks.
- Checking reference levelsCheck the lower edge of the door frame with a laser. The upper edge of the channel grating must be located between 5 and 10 millimetres below the water discharge point of the joinery.
- Pouring the bedding layerPlace a bed of earth-moist concrete 10 to 15 centimetres thick to seat the prefabricated channel bodies with perfect straight alignment.
- Connecting the drainageConnect the channel outlet pipe to the clear water collection network or to a filter bed provided on the plot, ensuring the presence of an accessible silt bucket.
- Laying the adjoining pavingLay the pavers or slabs on a 2/4 or 4/8 grit bedding layer, applying a falling slope of at least two percent that directs surface water away from the threshold channel.
- PRM mesh grating
- Metal channel grating with openings featuring longitudinal slots or square meshes not exceeding 10 millimetres of void to ensure safe rolling without blocking.
The space between the channel body and the first pavers requires a neat edge. The installation of a concrete edging or a kerb paver laid in mortar ensures lateral blocking of the paving without pushing against the channel. Adjacent joints must be filled with polymeric sand or clean crushed grit to prevent fines from being washed into the channel body during heavy storms. Biennial maintenance by lifting the gratings and cleaning the channel bottoms remains essential to maintain the hydraulic capacity of the structure.
Hydraulic regime of the channel and management of beating rain
Water projected against glazing and façades during a beating rain episode flows vertically at high speed towards the foot of the bay. When the clearance between the threshold and the finished ground is eliminated to satisfy flush accessibility, the usual 12 to 15 cm physical barrier disappears. Without this protective height difference, droplets splashing onto the adjacent paving and the dynamic pressure exerted by the wind force water under the waterproofing profiles of the joinery. The collection channel in front of the threshold then acts as an immediate interception receiver, breaking the continuity of the surface water film before it reaches the joinery joints.
To fulfil its role, the channel must have a geometry adapted both to the passage of persons with reduced mobility and to the volume of water captured. Standard SIA 318 governs external works and requires that runoff is drained in a way that preserves the durability of thresholds and façades. Particular attention must be paid to the choice of covering: a slot opening that is too narrow limits absorption during intense precipitation, while a grating that is too open blocks wheelchair wheels or walking canes.
| Cover type | Beating water absorption | Splash risk | Flush compliance |
|---|---|---|---|
| Tight-mesh grating (30/10 mm) | Maximum, breaks the water film instantly | Low thanks to blade depth | Excellent, trafficable and non-slip surface |
| Discreet linear slot (15 to 18 mm opening) | Medium, risk of overflow due to air saturation | Medium, partial return of droplets | Perfect visually and for rolling |
| Perforated grating with longitudinal perforations | High if the void ratio exceeds 40% | Moderate, depends on plate thickness | Acceptable if slot width is less than 10 mm |
The channel body must systematically be connected to an active drainage system, whether it is a rainwater collector or a pipe leading to a dedicated infiltration zone on the plot. A blind channel or one draining solely through its bottom onto a gravel layer is inadequate at an entrance door: in the event of a severe storm, the sub-layer becomes saturated, the basin is put under pressure and water rises through the threshold profile into the interior of the building.
Singular points at extremities and operational constraints
Standard SIA 318 requires strict geometric coordination when laying adjacent paved surfaces. The external paving must obligatorily feature a falling slope directed away from the building, ideally between 1.5% and 2%, starting from the outer edge of the channel. This arrangement ensures that only precipitation falling directly on the joinery and the channel is handled by the linear structure, excluding general runoff from surrounding terraces or paths.
- Altimetric setting of the upper edgePosition the channel grating between 5 and 10 mm below the lower level of the external sash joint to create a water drop break, while maintaining flush alignment with the finished paving.
- Construction of the support bed and lateral packingPlace the channel body on an earth-moist lean concrete blinding layer, then execute a rear buttress without blocking the connection openings or deforming the plastic or metal walls.
- Connection of drainage pipesFit the watertight outlet sockets towards the site's surface water network, providing a removable silt bucket to retain fine particles originating from the paving.
- Junction with the paving bedding layerSeparate the crushed grit bedding layer from the channel setting concrete using a non-woven geotextile to prevent the migration of fines under the grating and stabilise the paving edges.
The efficiency of a flush threshold channel relies on its ease of maintenance. Clogging by mineral dust, dead leaves and plant debris quickly reduces the useful flow cross-section. Gratings must remain removable without heavy tools and settling basins must be accessible for regular biannual clearance. This preventive maintenance prevents blockage of the system during summer storms, a time when peak flows severely test the watertightness of ground-floor joinery.
Management of threshold defects: infiltrations, saturation and subsidence
On site, eliminating the usual waterproofing clearance to meet step-free access requirements exposes the bottom of the door to severe hydraulic stresses. When infiltration occurs at the interface between the paving and the joinery, the landscape contractor must first identify the exact origin of the defect: backflow from the slotted channel due to clogging, local counter-slope caused by paving settlement, or failure to intercept beating rain running down the leaf.
- Control of altimetries and settingCheck the levelling between the channel grating and the edge of the external paving using an optical level or a straightedge. Any step greater than a few millimetres creates standing water retention. Ensure that the paving maintains its minimum falling slope away from the building.
- Removal of edges and foundation repairIn the event of channel subsidence due to inadequate bedding on unconsolidated crushed stone, remove the adjoining edging elements. Rebuild a lean concrete support foundation, taking care not to damage the existing waterproofing upstands fixed to the concrete base.
- Discharge audit and box clearanceRemove the gratings or removable slots to inspect the channel bottom. Empty the sediment basket of the sludge box and check gravity flow towards the outlet to eliminate any backflow under pressure during storm showers.
If the channel proves undersized in the face of water inputs from the façade exposed to prevailing winds, the corrective solution consists of replacing the gratings with models having greater absorption capacity or creating a secondary discharge slot immediately upstream of the threshold, in accordance with the guidelines of standard SIA 318.
Frequently asked questions
Can a threshold channel be installed directly on a conventional sand bed?
No. The channel body requires a rigid and stable foundation. Installation on sand or gravel inevitably leads to differential settlements under repeated traffic, causing the grating to tilt below the threshold level. It is mandatory to construct a support foundation and lateral lean concrete shoulders to guarantee the altimetry of the recovery system over time.
What slope should be given to the paving adjoining the channel in front of the threshold?
Standard SIA 318 recommends a minimum transverse slope falling away from the façade, in principle 1.5% to 2% for modular paved surfaces. This geometry directs runoff water towards the garden infiltration zones or secondary collectors, preventing the entire external surface from saturating the channel placed immediately below the door.
How to prevent clogging of drainage slots in front of an external door?
Narrow slots easily become clogged with plant debris, dead leaves and joint sweeping sands. It is essential to install a channel equipped with removable inspection elements and to provide a sludge box with a removable basket. Regular maintenance by water jet and suction prevents water stagnation at the threshold seal joint.
What to do if the 15 cm clearance height cannot be respected?
To reconcile barrier-free flush accessibility according to standard SIA 500 and water protection, the derogation from the 15 cm clearance requires a grated channel directly juxtaposed with the threshold. The structure must immediately capture beating rain and runoff descending from the door to prevent any submersing of the lower transom.
Texts and standards cited
- SIA 318External works: levelling requirements, surface water management and paving installation
- SIA 500Barrier-free constructions: principles of flush access to building entrances
