🧱 CFC 411Low walls, retaining structures and external stairsChapter 3 of 10 in the section

Dry-stone wall: batter of the wall, courses, through-stones and wall holding without mortar

This chapter details the rules of good workmanship for building a dry-stone retaining wall without any hydraulic binder. You will learn to set the face batter, arrange the tie through-stones in accordance with the SIA 318 standard and ensure gravity drainage to guarantee the final stability of the structure.

Key takeaways

  • The face batter inclines the wall from ten to twenty percent towards the slope.
  • The foundation course is laid on a formation level that is itself inclined backwards.
  • Through-stones anchor the face into the core and lock the successive courses together.
  • The crushed stone rear backing prevents any hydrostatic pressure without any perforated drain.

Face batter and inclined foundation according to the SIA 318 standard

A dry-stone wall derives its strength from neither glue nor steel. Its stability relies exclusively on gravity, the inter-granular friction of the blocks and the transfer of loads to the uphill ground. The SIA 318 standard governs these external works, reminding us that any gravity retaining structure must compensate for earth pressure through appropriate geometry. This geometry begins as soon as the foundation excavation is opened.

Wall batter
Inclination of the visible face of the masonry relative to the vertical, expressed as a percentage or in centimetres of setback per metre of height, directed towards the retained slope.

For a landscape retaining wall, the batter is usually between 10% and 20%, i.e., a setback of 10 to 20 centimetres per metre of height. The stronger the ground pressure or the rougher the material, the more pronounced the batter must be. To set out this slope on the construction site, the team installs timber profile gauges at each end of the section, supplemented by string lines that can be moved course by course. Working by eye without a rigid gauge creates bulges and directly compromises mechanical performance under winter pressures.

The first row receives the most voluminous and densest blocks of the batch, commonly called foundation or bedding stones. These elements are laid level in the longitudinal direction but tilted upstream perpendicular to the layout, faithfully following the dip of the excavation base. Frost-free anchorage must be complied with in accordance with current regional practices on the Swiss Plateau or in pre-alpine areas.

Through-stone bonding, internal packing and natural drainage

Raising the wall requires rigorous bonding combining stretchers and through-stones. A classic mistake is to favour facing aesthetics by laying the stones lengthwise along the string line: the wall then behaves like an unstable veneer. Good workmanship requires crossing the vertical joints from one course to the next and systematically interspersing through-stones, i.e., blocks laid deeply, perpendicular to the visible face.

  • Stretchers: stones oriented parallel to the face, forming the continuous visible surface.
  • Ordinary through-stones: elongated stones whose tail penetrates deeply into the packing mass.
  • Full through-stones: elements crossing the complete thickness of the wall to tie together the face and the rear backfill.
  • Backing: clean crushed stone of intermediate grading filling the interior voids and the back of the wall.

An average of two to three through-stones are implemented per square metre of facing, arranged in a staggered pattern. These elements act as genuine mechanical anchors. Each laid stone must find its own stability on at least three solid bearing points before any secondary packing. The packing of the blocks is carried out from the rear or underneath using hard, angular rock chips, ruling out facade shims which risk slipping over time.

Rules for assembling the dry-stone wall body
Structural elementMechanical functionSite installation requirement
Base courseLoad distribution to the groundLarge modules laid with an upstream counter-slope
Anchoring through-stonesTransverse face-backfill tieMinimum penetration of two thirds of the wall thickness
Rear backingFiltration and water dispersionCrushed material free from topsoil and fines
CopingTop locking and protectionLarge flat slabs tilted or laid on edge

The drainage of a dry-stone wall is immediate and permanent by nature: the absence of mortar provides open gaps across the entire surface. Behind the masonry, the space between the face and the excavated natural ground receives clean, frost-resistant and fines-free gravel backing. This draining mass filters infiltration water and instantly eliminates any hydrostatic pressure, the main cause of failure in mortared retaining structures. A separation geotextile is inserted between this draining crushed stone and the natural ground to prevent clogging through the migration of fine particles.

Raising the face, toothing courses and laying through-stones

Raising a dry-stone wall tolerates no geometric improvisation. Unlike mortared masonry where mortar compensates for voids and distributes stresses, dry construction relies exclusively on the dead weight of the elements, contact friction and the perfect transmission of loads to the foundation course. Each course must be built horizontally or slightly tilted towards the slope, with stones laid on their widest quarry bed to avoid toppling. The mason uses the masonry hammer and broad axe to trim awkward edges and ensure direct rock-to-rock contact. The crossing of vertical joints constitutes the master structural rule: no vertical joint must overlap across two successive courses, under penalty of creating a vertical failure plane known as a hinge joint.

  1. Sorting and grading ashlar stonesArrange the stones along the excavation, separating massive blocks for the base, long stones for through-through stones, regular facing ashlars for intermediate courses and angular chips for interior packing.
  2. Setting the batter gaugeStretch alignment string lines on wooden or metal gauges adjusted to the required batter angle. Check the regularity of the inclined plane at each course to ensure that the face leans back towards the earth as it goes up.
  3. Stone-on-stone laying and packingLay the facade stretchers ensuring intimate contact between the bearing faces. Introduce the rear backing with clean crushed stones, tamped down with the hammer as you go to tighten the core of the wall without moving the sightline.
  4. Inserting anchoring through-stonesRegularly place deep stones penetrating at least two thirds into the total thickness of the structure or crossing it entirely, locking the face with the draining backfill.

Coping, filtering protection and drainage durability

Natural drainage represents the major mechanical strength of dry-stone masonry. The complete absence of hydraulic binder gives the structure integral permeability: infiltration and percolation water circulate freely between the rock interstices without generating the slightest hydrostatic pressure behind the face, thereby avoiding the use of traditional weep holes. However, the SIA 318 standard prescribes interposing a rot-proof non-woven geotextile felt between the rear draining backing and the topsoil of the uphill slope. This geotextile effectively retains fine particles, sands and silts which, over rainy seasons, would migrate inside the structure, clog the interstitial voids and irreparably destroy the draining balance of the external works.

Common defects in a dry-stone wall and remedial execution measures
Installation defectStructural consequenceCorrective site measure
Overlapping vertical joints (hinge joint)Vertical cracking and decohesion under earth pressureOffset joints by at least one third of the length of the lower ashlar
Insufficient batter or strict verticalityForward toppling of the face during backfill settlementBuild using gauges with a strict batter between ten and fifteen percent
Omission of anchoring through-stonesDetachment of the face separating from the internal massSystematically place one through-stone per square metre of elevation
Backfill soil in direct contact with the stonesClogging of voids and creation of hydrostatic pressure in rainy weatherInterpose a non-woven geotextile felt behind the clean gravel backing

The terminal capping guarantees the overall stability of the structure against operational overloads and weather runoff. The coping stones must be the most massive of the available batch, selected for their density and laid on edge or flat across the entire upper width to encircle the entire crest. Regular and thick slabs are arranged and tightly squeezed against one another with careful packing in the core. Their dead weight locks the final course and internal backing against vibrations, pedestrian traffic and superficial scouring. The natural ground upstream is then connected with a gentle vegetated slope guiding surface water away from the top of the wall.

Distortions, bulges and deformations: diagnosis and repair of an unstable wall

On external works sites executed in accordance with the SIA 318 standard, defects affecting a dry-stone retaining wall almost always manifest through two symptoms: a bulging face or forward toppling. A localized bulge signals a breakdown in internal mechanical bonding. This defect results from a shortage of through-stones on the concerned course or the use of earthy run-of-mine material in the rear backing instead of clean crushed aggregate. Under the combined pressure of earth and frost, unanchored facing ashlars slide on their bedding joint. The general toppling of the structure betrays an unstable foundation, a footing insufficiently tilted towards the slope or a progressive loss of assembly batter.

  1. Relief and excavationExcavate the soil surcharge behind the deformed zone using a mini-excavator, respecting the slope angles prescribed by the construction work ordinance to secure the workstation.
  2. Methodical dismantlingDismantle the face stone by stone from the coping down to a perfectly flat, stable foundation anchored in the ground. Number and store the sorted ashlars to the side.
  3. Reconstruction of the draining backingRemove all materials clogged or polluted by soil. Lay an anti-contamination geotextile against the natural ground and supply clean crushed gravel without fine elements.
  4. Rebuilding with accentuated batterRebuild the courses, firmly packing each ashlar until refusal. Lay a through-stone every running metre, tilted slightly backwards, then pack the drain stone by stone.

Final stability relies on the exact restoration of rock-to-rock contacts. Each reinstalled ashlar must present a stable bed even before laying the upper element, without toppling under a worker's weight. Rear packing with stone chips is carried out progressively as elevation proceeds, never all at once at the end of the day, to guarantee the wedging of the courses and the total permeability of the structure.

Frequently asked questions

Why must mortar never be poured to stabilize a bulging dry-stone wall?

Mortar clogs the voids that ensure the continuous evacuation of runoff and groundwater. A dry-stone wall naturally dissipates hydrostatic pressures. By injecting binder, you create a waterproof mask: water accumulates behind the stones, fines become waterlogged and pressure increases. At the first frost, the trapped water freezes, swells and brutally expels the entire face. Local deconstruction remains the only compliant method to restore structural equilibrium.

How to correct a face that begins to lose its batter during elevation?

As soon as the level or gauge signals unintended vertical straightening, immediately stop assembly. You must never cheat by laying a stone with an reverse overhang. Dismantle the last two incriminated courses. Rectify the inclination of the bedding joints with a masonry hammer or using hard stone bedding shims driven under the rear of the blocks. Restart laying while systematically checking the slope towards the slope for each positioned element.

What anchorage length must a through-stone have relative to the wall thickness?

A through-stone must penetrate at least two thirds of the total thickness of the structure, including the draining backing, or cross the entire mass to act as a key. For a wall sixty centimetres thick at the base, choose rock elements fifty to sixty centimetres long. The tail of the through-stone must plunge into the rear crushed stone to transfer the face pressure to the compacted backfill and bind the assembly together.

What to do in the presence of a localized water inflow behind the wall without a perforated drain?

Dry stone naturally absorbs diffuse water inflows, but concentrated resurgences require an adaptation of the rear backing. At the precise location of the water inflow, increase the grading of the draining crushed stone with non-friable, large-calibre blocks. Arrange dry weep holes by reserving open cross-passing spaces in the lower courses of the face, protected at the rear by a geotextile membrane to prevent the entrainment of topsoil particles.

Texts and standards cited

  • SIA 318External works - Design and execution of dry masonry and retaining structures