🧱 CFC 273Door acoustics: seals and thresholdsChapter 7 of 10 in the section

Measuring in place: element installed versus element tested in the laboratory, and the normal difference

By the end of this chapter, you will be able to interpret the difference between the certified sound reduction index of a door set and its actual performance measured in situ. You will master the margin of degradation accepted by the rules of the trade, the airtightness checks to carry out on your seals before an expert assessment, and the procedure for drawing up an enforceable joint record of findings.

Key takeaways

  • Laboratory measurement isolates the leaf, whereas in situ measurement includes its surroundings.
  • Standard SIA 181 tolerates a foreseeable difference linked to the fixing and to perimeter leaks.
  • A difference exceeding the accepted margin points to a sealing defect or a faulty adjustment.
  • The joint record of findings fixes the measurement conditions and protects the liability of the installing joiner.

Distinguishing test-bench performance from the value measured on the construction site

When a door set manufacturer supplies an acoustic test certificate, the value stated qualifies an element mounted under ideal sealing conditions in an accredited test laboratory. The leaf is fitted into a heavy, perfectly flat and airtight frame, in a massive masonry wall without flanking transmission. On the construction site, the built reality changes these parameters: the door is fixed in a rough opening, often in a plasterboard partition or hollow masonry, whose junctions and sealing directly influence the final result.

Laboratory value and in-place value
The laboratory value quantifies the sound reduction index of the door set itself, sealed without parasitic leaks. The in-place value measures the overall sound insulation between two finished rooms, including the installed element, its junction joints with the structural work and the secondary sound transmissions through adjoining walls or floors.

Standard SIA 181, which governs noise protection in buildings in Switzerland, does not set obligations of means on the isolated product but requirements of result on the finished work. The acoustician does not measure the leaf independently when setting up the sound source and microphone: they quantify the energy passing through the entire separating wall containing the door set. It is therefore technically normal and systematic to find a drop in performance between the manufacturer's test sheet and the on-site measurement report.

Differences in the acoustic behaviour of a door set depending on the measurement environment
Assessment criterionMeasurement in a test laboratory*In situ* measurement according to standard SIA 181
Fixing substrateRigid, massive concrete test frameDoor frame installed in a rough opening or lightweight partition
Flanking transmissionsEliminated or corrected by the test cellPresent via slabs, floating screeds, ceilings and partitions
Frame sealingContinuous heavy bedding without residual voidsElastomeric sealant, backing rod and compressed mineral wool
Threshold and automatic drop sealFull compression on a ground floor that is square and trueCompression depends on the flatness of the finished floor covering

Identifying the permissible difference and formalising checks by joint record of findings

According to the rules of the profession and standard SIA 181, the loss of performance accepted between the element tested in the laboratory and the element mounted on the construction site is generally between two and five decibels. This normal installation difference compensates for the unavoidable verticality tolerances of the openings, the surface porosity of thresholds and the geometry of the ironmongery. A larger difference, on the other hand, indicates a direct physical anomaly: perimeter air leak, poorly engaged automatic drop seal or hollow sealing between the frame and the reveal.

  1. Checking the compression of the rebate sealsClose the leaf on a calibrated sheet of paper along the three sides of the rebate; pulling on the sheet must meet strong, uniform resistance all the way round, confirming that no air passes under the elastomer lips.
  2. Adjusting the descent of the automatic drop sealAdjust the trigger's push screw so that the silicone lip descends squarely and compresses the finished floor along its entire length, without rubbing during rotation or leaving a gap at the lower corners.
  3. Checking the perimeter sealing of the door frameBefore the cover strips are fitted, make sure that the gap between the timber or metal frame and the wall is filled solid with compact fibrous insulation, then closed on both faces with a continuous bead of airtight sealant.
  4. Examining technical penetrations and the lockCheck that there is no through gap at the cylinder entry, the lever handle rose and the cable passage for electric strike plates or position contacts.

When a joint acoustic measurement is ordered by site management or by an appointed expert according to standard SIA 181, the joiner must demand that a joint record of findings be drawn up. This written document records the precise condition of the door set during the test, the actual carrying out of the preliminary check, the presence of the final sealing, the type of floor coverings and the progress of the neighbouring rooms. If the partitions or technical penetrations are not finished, this situation must be explicitly stated in it to rule out any improper attribution of an acoustic defect to the joinery.

In situ diagnosis of acoustic leaks and execution tolerances

On a construction site in French-speaking Switzerland, acoustic acceptance according to standard SIA 181 frequently reveals a drop in performance compared with the records of tests carried out on a fixed test bench. In the laboratory, the door set is inserted into a massive masonry wall without flanking transmission, sealed without any opening constraint or structural-work tolerance, and bedded under controlled conditions. On the works, the joiner installs the door frame in a rough opening that shows variations in flatness, out-of-plumb conditions and heterogeneous interfaces. The difference between the sound reduction index measured in the laboratory and the standardised sound insulation measured in situ includes the behaviour of the receiving room, the secondary paths and the installation itself.

A degradation within this range results from the structural coupling with the surrounding partition and from the unavoidable presence of the small operating clearances necessary for the lock and hinges to function. Beyond such a reduction in insulation, the behaviour is no longer regarded as normal execution scatter but characterises a construction anomaly or a non-compliant installation of the frame or leaf. When the acoustician finds a more pronounced deficit, the search for the leak immediately turns to the critical points of the door set.

Analysis of in-place sound insulation losses according to the origin of the defect
Door set componentMechanical origin of the sound bridgeImpact measured in placeCorrective action by the joiner
Rebate sealUneven compression, continuity broken at the upper cornersModerate to severe localised dropReplace with a continuous tubular elastomer seal, mitred corner glued
Automatic drop sealIncomplete travel, not parallel with the finished floorMajor sound bridge at the foot of the doorAdjust the plunger travel, align precisely with the stop profile
Frame sealingResidual air gap under the cover strip, partial packing without sealantDiffuse perimeter leakRemove the casings, inject a heavy acrylic sealant over a backing rod
Lock and ironmongeryCylinder without airtight escutcheon, excessive play at the latch boltPinpoint penetrating leakFit airtight acoustic roses, adjust the strike plate to compress the leaf

The preliminary paper-sheet test remains the most reliable mechanical diagnostic tool for the installation foreman: a sheet trapped in the closed rebate must resist pulling all the way round the leaf, particularly at the hinges and in the two upper corners. Likewise, the descent of the drop seal at the bottom rail must compress the elastomer lip in a perfectly straight line against the threshold bar or the smoothed floor, without letting the slightest thread of light through under an inspection torch.

Joint acoustic expert assessment and classification of the defect

  1. Notification of the disputed resultOn receipt of the measurement report indicating an abnormal difference from the requirements of the specifications, the site manager requests an on-site meeting with the acoustician and site management.
  2. Experimental neutralisation of the leafTo distinguish the share due to the joinery from that due to the supporting wall, the rebate and the threshold are completely sealed with dense adhesive tape on both faces. A new insulation measurement is taken straight away: if the result does not improve, the joinery is not at fault.
  3. Checking the geometric conditionsJoint check of any warping of the door panel with a precision straightedge, check of the level of the bottom rail and examination of the surface condition of the final floor covering.
  4. Drawing up the joint record of findingsWritten recording of the raw measured values, the details of the adjustments made to the ironmongery and the agreements reached for a resealing or for the formal discharge of the joinery company.

The joint record of findings is authoritative for applying the rules governing defects in the work under standard SIA 118 and the Code of Obligations. This document establishes whether the acoustic difference results from an adjustment negligence attributable to CFC 273 (such as a faulty setting of the lower automatic seal or an absence of silicone under the frame) or whether it stems from external factors: deformation of the structural work after installation, deflection of a concrete slab, or late laying of an uneven floor covering under the travel of the drop seal.

Where the expert assessment establishes that fine adjustment of the three-dimensional hinges and the adjustable strike plate restores the required compression without forcing the key, the intervention is recorded as a normal site fine-tuning. If, on the other hand, the leaf has warped under the effect of a premature hygrothermal gradient on an unheated construction site, the record notes the ambient humidity measured so as to arbitrate responsibility between the site conditions imposed and the intrinsic conformity of the delivered component.

Appeal protocol and dispute resolution in the event of a non-compliant result

When the in situ measurement reveals a result below the contractual requirements set by standard SIA 181, site management frequently blames the door set. Yet the performance certified in the laboratory under ideal installation conditions is never fully reproduced on the finished work. A normal installation difference always exists, usually between two and five decibels, caused by flanking transmissions of the partition, the connection to the structural work or imperfections of the finished floor. Beyond this tolerance accepted on the construction site, the result tips into the category of execution defect, exposing the installer to rectification notices.

  1. Convening a joint counter-measurementBring together the appointed acoustician and site management. The check must take place in the presence of the joiner in order to verify the calibration of the sound level meter and the background noise level of the building.
  2. Diagnosing mechanical airtightnessExamine the closed leaf: measure the rebate clearances with a steel rule, check how a sheet of paper is gripped by the perimeter seal and verify the descent of the automatic drop seal onto the floor.
  3. Carrying out the adhesive tape testThe acoustician applies heavy tape all round the leaf and on the floor. If the measured value does not improve, the acoustic weakness comes from the supporting wall or the neighbouring junctions, discharging the joinery company.
  4. Drawing up the joint record of findingsDraw up on the spot a record signed by the parties involved. The document summarises the decibels measured before and after temporary sealing, the geometric tolerances observed and the formal technical reservations.

Under standard SIA 118, this joint record of findings is the only evidence for distinguishing a joinery intervention (hinge adjustment, rebate compression, threshold setting) from an insulation shortfall specific to the adjoining walls. The craftsman thus protects their technical rights against unfounded financial retentions by the project management.

Frequently asked questions

Why does a door certified at 42 dB in the laboratory reach only 37 dB once installed?

In the laboratory, the element is sealed into a decoupled masonry test opening, without any parasitic transmission. On the construction site, the in situ measurement includes the real environment: structural sound bridges through the slab, flanking transmissions through lightweight walls and microscopic air leaks at the junction between the door frame and the partition. This degradation of three to five decibels represents the normal installation difference taken into account by planners according to standard SIA 181.

How can you prove on site that the acoustic leak comes from the partition and not from the door?

The joiner and the acoustician carry out a temporary sealing test. Heavy acoustic adhesive tape is applied all round the leaves and on the bottom threshold in order to neutralise the air gaps specific to the joinery. If the acoustic measurement improves only marginally, the acoustic energy is passing through the insufficient mass of the partition or through its faulty junctions. The finding is recorded without delay in a joint record of findings.

What must the joint record of findings contain after an acoustic check?

The document states the precise location of the room, the ambient temperature and the measuring equipment used with its calibration date. It records the raw insulation value obtained, the background noise level and the result after any temporary sealing with tape. The parties describe in it the mechanical condition of the door set: seal compression, plumbness of the frame and flatness of the floor under the automatic threshold seal. The document ends with the signatures of the parties.

Which joinery adjustment quickly recovers two to three decibels on site?

Adjusting the automatic guillotine drop seal is the priority intervention. The push rod must be set so that the elastomer seal presses evenly on the floor without bowing the leaf. Next, tightening the adjustable hinges increases the compression of the hollow rebate seal to two or three millimetres all the way round. Finally, injecting a bead of acoustic sealant under the frame removes the remaining micro air infiltrations.

Texts and standards cited

  • SIA 181Protection against noise in buildings
  • SIA 118General conditions for the execution of construction work