Key takeaways
- Door leaves must be installed only after screeds and painting are complete.
- Always protect frames and edges with impact-absorbing profiles made of dense cardboard or polyethylene.
- The joint inspection record at installation releases the joiner from liability for any damage caused by third parties.
- Any damage not attributed to a specific trade falls by default on the contractor awarded the work.
Time the order of work so as to refuse the role of service door
As soon as a door leaf is hung on its hinges, it becomes the prime target of the construction site. For electricians, plumbers or plasterers, an opening fitted with a door is a handy draught stopper or a mandatory passage to be crossed with bulky loads. Handles serve as coat hooks, panels receive plaster splashes and edges end up chipped by tool boxes. For the joiner, the first line of defence is not adhesive tape but strict control of the sequence of work.
The reveal and the frame may be installed as soon as the light or masonry partitions have dried and the liquid screed has finished its moisture off-gassing. On the other hand, the hanging of the door leaves, particularly if they are workshop-lacquered or veneered with fine species, must be postponed as late as possible in the finishing schedule. Interior doors must be installed after the second coat of paint on ceilings and walls, and immediately before the laying of resilient floor coverings or after the final varnishing of parquet floors.
If the client contractually imposes early installation of landing doors or interior doors, notably for reasons of temporary fire compartmentation, the joiner must immediately neutralise the passage. This means closing off access with a site cylinder whose key remains in the exclusive custody of the foreman or site management, or temporarily removing the lever handles and leaving a formal warning notice.
Protect sensitive edges, draw up the record and allocate damage
Once the door leaf is installed and adjusted, passive protection tolerates no makeshift improvisation. The sharp edges of the frame, the meeting edge and the bottom rebate are the most vulnerable areas. Standard stretch film gives no protection whatsoever against mechanical impact; worse, its adhesive can react chemically with water-based varnishes or polyurethane lacquers and tear off the finishing film when removed.
- Mechanical shielding of reveals and framesFit corner protectors made of thick compact recycled cardboard or U-shaped extruded polyethylene foam profiles over the full height of the door frame. Secure these elements by elastic tension or with low-tack adhesive tapes applied exclusively on the non-visible edge.
- Full covering of door leavesWrap both faces of the door leaf with lightweight fluted corrugated polypropylene sheets, cut to exact dimensions and taped edge to edge with no adhesive contact on the wood. Leave clear only the lock area to allow locking.
- Protection of the threshold and bottom rebateProtect the automatic drop seal on the floor or the bottom rebate against abrasive screed-sanding dust using a removable metal profile or a thick protective felt taped to the floor.
Physical protection remains insufficient without legal safeguards. As soon as the doors of a section are installed, adjusted and protected, the site manager must call site management to a formal joint inspection record. Under the usual rules of contracting agreements and the standards of the Swiss Society of Engineers and Architects, notably SIA 118, the contractor is liable for his work until acceptance, unless he proves wrongful intervention by a third party or abnormal use authorised by site management.
| Key step | Technical action required | Evidential document | Financial consequence |
|---|---|---|---|
| End of installation of a lot | Check plumb, 3 to 4 mm clearances, intact surfaces | Partial inspection record signed, with photos | Certifies the initial conformity of the installed work |
| Use as a thoroughfare | Record of damaged protection or traces of passage | Written notice of damage sent the same day to site management | Immediate transfer of the risk of deterioration to the client |
| Record of breakage by a third party | Identification of the responsible company (materials, witnesses) | Non-conformity sheet with costing of rework on a daywork basis | Direct invoicing to the third party or allocation to the pro-rata account |
| Final handover of the work | Careful removal of shielding, gentle cleaning, functional test | Final acceptance record without reservations | Release of retention money and end of custody |
Physical protection devices: frame sleeves and shielding of door leaves
As soon as an interior door set or a landing closure is adjusted in its opening, the work becomes the main target of logistics flows. The repeated passage of trolleys, painters' ladders or electricians' cable reels immediately exposes frame uprights and door leaf edges to violent mechanical impacts. Fitting rudimentary protection is not enough; the device must absorb friction without transmitting the energy to the wood or the finishing lacquer.
For reveals and frames mounted surface-fixed or in a tunnel arrangement, edge protection is provided by rigid compressed cardboard corner profiles at least three millimetres thick or corrugated polypropylene corner pieces. These shells wrap the uprights from the raw floor up to a minimum height of one metre twenty. Standard packing tapes must absolutely be excluded for fixing these protections: their acrylic or solvent-based adhesives migrate into the varnishes within a few weeks and tear off the finishing film when removed. The joiner uses fabric straps with quick-release buckles, spring clamps lined with felt, or low-tack adhesive tapes specifically formulated for lacquers and removed within the deadlines prescribed by the manufacturer.
| Exposed element | Recommended technical device | Mechanical hold | Risk prevented |
|---|---|---|---|
| Frame and splayed reveal frame | Corner profiles in dense cardboard (3 mm) or impact-absorbing foam sleeves | Elastic straps or special residue-free lacquer-safe adhesive tape | Chipped edges, veneer splinters, crushing by wheelbarrows |
| Painted or veneered door leaf face | Corrugated polypropylene sheets or hardboard panels | Complete wrapping under breathable micro-perforated polyethylene film | Surface scratches, paint stains, plaster splashes |
| Door leaf in a busy passageway | Complete unhanging and storage on edge in a secure buffer room | Temporary replacement by an OSB site panel or tarpaulin | Bowing from draughts, deformation of hinges, axial impacts |
| Swiss threshold and floor fittings | Bridging profile in folded sheet metal or chamfered solid-wood bridge piece | Removable wedge fixed to the slab without drilling through the waterproof profile | Crushing of the acoustic seal, deformation of the sealing strip |
Joint inspection record and legal allocation of damage
As long as the work has not been the subject of a formal handover or acceptance under the rules of the contracting agreement, the joiner bears the presumption of liability for any visible damage. To protect against damage caused by third parties to a door installed before the other secondary trades have finished, the company must formalise two key steps: the joint inspection record of completed installation and the final handover protocol.
- Geometric and visual check at installationCheck the flatness of the door leaf, the plumb of the frame, squareness, constant perimeter clearance and the complete absence of chips or scratches on lacquers and veneers.
- Drawing up the interim recordDraw up a work order or a joint inspection record signed on site by site management, certifying the compliant installation and the aesthetic integrity of the element.
- Setting up the photographic coverageTake timestamped high-definition digital photographs showing the whole door set, details of the edges, the site handle and the protections installed.
- Formal transfer of custody of the workNotify site management in writing that the finished work is placed under its custody for site use, any breaking of seals or removal of protection now being its responsibility.
If an interior door is damaged before the final handover of the work, the Code of Obligations (CO) and standard SIA 118 define the procedures for reporting and repairing the damage. As soon as a deep scratch, a stop impact or a bent hinge is discovered, the joiner foreman immediately sends a written anomaly notice to site management, backed by dated photos. This document recalls the date of the initial joint inspection record in which the door was validated as intact.
The financial allocation of the damage follows a strict process. When the person who caused the impact is formally identified on the construction site — for example a tradesman manoeuvring scaffolding —, site management charges the cost of restoration to the account statement of that third-party company. If the person remains unknown, the loss falls either under the construction site's pro-rata account if the contract expressly so provides, or under the construction all-risks insurance taken out by the client, provided that the joiner proved the impeccable condition of his supply during the interim joint inspection.
Handling disputes and allocating damage before acceptance
When the construction site schedule slips and forces joinery to be installed before the heavy finishing work is complete, the door set inevitably suffers from the logistics flows of the other trades. If a veneered door leaf or a lacquered frame shows chipped edges, deep scratches or deformation resulting from the forced wedging of a cable passage, the joiner must act methodically to clear his contractual liability.
- Formal notification of the damageAs soon as the damage is discovered, the foreman records the anomaly in the site diary with timestamped photos, precise location on the plan and description of the impacts on the edges or faces. A written notice of defects is sent to site management, recalling the initial installation date and the conformity recorded in the interim condition record.
- Summoning on site for a joint inspectionThe joiner requests an immediate joint visit with site management and the companies working in the area concerned. The purpose of this meeting is to record the nature of the impact, the tool or equipment presumed responsible (mobile scaffolding, pallet truck, spraying hose) and to draw up the signed record required under the principles of standard SIA 118.
- Costing and financial allocationThe cost of rework is the subject of a separate supplementary quote, sent to site management for prior approval. The amount distinguishes spot repair by touch-up with resin tinted throughout from full replacement of the door leaf, notably required for certified fire doors whose internal structure is compromised. In the absence of an identified responsible party in the joint inspection record, the amount is charged to the construction site's pro-rata account.
Frequently asked questions
How should you react if site management refuses to sign the interim condition record at installation?
The team leader records this refusal in the daily installation report and immediately sends the complete condition report by registered letter or traceable email. He attaches all the detailed photographs of the faces, edges and frames under protection. Under standard SIA 118, this notified step fixes the condition of the elements delivered and transfers the risk of mechanical damage to the companies that continue to use the premises as thoroughfares.
Who bears the cost of replacing a fire door damaged by an unidentified trade?
If the joiner drew up a joint inspection record at installation certifying the integrity of the element, the damage falls under anonymous construction site damage. According to Swiss building practice governed by standard SIA 118, these restoration or full replacement costs cannot fall on the installer. The rework invoice validated by site management is then charged directly to the general pro-rata account of the construction site.
Is it possible to forbid other contractors from using a freshly installed interior door as a passage?
Yes, the joiner can secure the work by locking the lock with a key and keeping the site cylinder, in agreement with site management. If the passage remains essential for the logistics flows of the finishing work, the joiner demands in writing that only the frame be kept, or has a formal discharge signed stating that the heavy protections of corners and thresholds are the responsibility of the users.
What level of damage to a frame requires its complete replacement rather than a touch-up?
A local touch-up with hard wax or two-component resin is acceptable for slight surface chips on the edges. On the other hand, a tear-out of material affecting the rebate, a structural deformation of the metal upright or an alteration affecting the intumescent strip of a fire door set requires replacement of the part. The fire-resistance certification prohibits any modification or filling that alters the original geometry.
Texts and standards cited
- norme SIA 118General conditions for the execution of construction work, governing acceptance of the work, notice of defects and the handling of damage on the construction site.
- code des obligationsGeneral rules of the contracting agreement concerning the contractor's liability, the duty to notify and the client's rights in case of defects.