Key takeaways
- Acceptance of the structural work and partition walls determines the fitting warranty for the door set.
- Out-of-squareness of up to ten millimetres can be compensated; beyond that the frame no longer fits.
- The two-metre straightedge and the plumb line reveal out-of-plumb and twist.
- A reasoned written refusal releases the joiner from any later rework.
Measuring the masonry opening and checking for twist before unloading
Unloading frames and door leaves involves physical effort and an irreversible technical commitment. Placing a pallet of joinery on a rough slab before checking three sample openings is a methodological error. If the mason or plasterer has narrowed the opening by twenty millimetres or if the reveal shows pronounced warping, the pre-fitted door set cannot be wedged plumb without cutting into the rebate or planing the bottom of the jamb. Checking therefore starts as soon as you reach the floor, tape measure and spirit level in hand.
Measuring the clear passage and opening dimensions is not simply a matter of taking the width at floor level. A rough opening of nine hundred millimetres must provide at least the tolerances required by SIA 343 to allow the frame to be inserted, a perimeter adjustment gap of fifteen to twenty millimetres, and room for the sealing or fixing material. The width is measured at three points: ten centimetres above the theoretical finished floor, at mid-height near the strike plate, and under the lintel. If the top dimension is eight centimetres smaller than the bottom dimension, the trapezoid shape rules out fitting a straight frame.
| Measured item | Deviation found | Technical consequence for fitting | Workshop decision |
|---|---|---|---|
| Opening width | Less than 10 mm from nominal | Insufficient gap for wedging and foaming | Refusal; reveal to be chipped back |
| Squareness of corners | 5 to 10 mm out of square | Can be absorbed under the cover strip | Acceptance with adjusted wedging |
| Plumb of the rough jamb | More than 15 mm over the height | Twisted frame, door that rubs or swings open by itself | Immediate refusal with request for rectification |
| Flatness of the lintel | More than 5 mm of central deflection | Interference with the head of the frame | Refusal; structural work to be rectified |
- Checking the diagonals of the openingStretch the tape measure from an upper corner to the opposite lower corner. A difference between the diagonals of more than ten millimetres indicates a parallelogram that will prevent any adjustment to give even rebate gaps.
- Checking the plumb of both jambsApply a two-metre aluminium straightedge fitted with a calibrated spirit level to each inner face of the reveal. Note the out-of-plumb towards the inside or the outside of the room.
- Measuring the reference level lineLocate the line one metre above the finished floor marked by the surveyors or the structural work. Calculate the height under the lintel relative to this mark to confirm that the door leaf will pass without unauthorised trimming.
- Detecting wall warpingSight along the two edges of the reveal lined up one behind the other, or place two straightedges crosswise. A wall twisted by more than fifteen millimetres will prevent the frames from sitting flat against the plaster.
Serving the reasoned refusal and recording the deviations before any installation
Noting a defective opening on the construction site is not enough: proceeding despite the error immediately transfers the financial responsibility for the defect to the joiner. Under the usual rules of the contract for work and the provisions of SIA 118, the craftsman has a formal duty to examine the preparatory work supplied by other trades and to notify site management without delay as soon as an anomaly compromises correct fitting. Fitting a fire door into an out-of-plumb reveal automatically voids the fire protection approval of the complete element.
The reasoned refusal of an opening must be drawn up on the spot, ideally from the opening concerned. The document states the architectural reference of the door according to the tender plans, the dimensions measured to the nearest millimetre, the comparison with the acceptance tolerances of SIA 343, and the direct impact on the contractual services. A copy of this notice is handed to the site manager of the general contractor with a request to set a date for rectifying the masonry or the plaster lining.
- Explicit mention of the room number, the opening direction and the type of frame concerned.
- Joint inspection record of the widths at three points and of the two diagonals to the millimetre.
- Photograph of the straightedge placed against the jamb showing the deviation of the spirit level bubble.
- Formal reminder that the deviation is incompatible with the requirements of SIA 343.
- Formal request to bring the structural work into compliance before fitting is rescheduled.
Measuring out-of-plumb and out-of-square: the limit of what can be absorbed
On the construction site, the geometric check of a masonry opening or of an opening in a lightweight partition determines whether the work is accepted before the door set is unloaded. SIA 343 defines the functional criteria for doors in buildings, while the execution tolerances for structural work or partitions are governed by Swiss professional rules. On-site adjustment has a physical limit set by the width of the cover strips, the depth of the rebate and the clearance at the bottom of the rebate needed to wedge the frame or the wrap-around frame.
A deviation of ten millimetres over the height of a reveal is compensated by angled wedging under pads, combined with adjustment of the trim boards or a bevel trim at the back of the splay. However, once the out-of-plumb or out-of-square offset reaches or exceeds thirty millimetres, installation becomes impossible. The frame can no longer stay plumb without projecting beyond the plane of the finished wall, which leaves a gaping void behind the cover strip or prevents the leaf from closing against the seal.
| Deviation found | Impact on the door set | Technical feasibility | Action required on the construction site |
|---|---|---|---|
| Up to 5 mm | Even perimeter gap, standard wedging in the fitting space | Within usual tolerances | Direct fitting without additional machining |
| 6 to 12 mm | Cover strip hiding the gap, asymmetric wedging required | Adjustment possible in the workshop or on site | Tapering the frame or adjusting the hinges |
| 13 to 25 mm | Insufficient overlap of the frame, unstable wedging | Critical and outside tolerance | Visible compensating filler strip or refusal pending making good |
| 30 mm and more | Leaf striking the reveal or frame projecting from the wall face | Technically impossible | Immediate refusal of the opening and rework by the mason |
To check the squareness of the jambs relative to the lintel, use the trigonometric method or compare the inner diagonals of the opening. A diagonal difference of more than ten millimetres indicates a distorted parallelogram that will prevent an even gap between the door and the frame, causing the latch bolt to rub or the leaf to jam at the head.
Instrumental checking of the reveal and drawing up the reasoned refusal
- Checking the level lineMeasure the exact distance between the official level line one metre above the finished floor and the underside of the lintel at two points, as well as at the rough floor, to anticipate the gap under the leaf.
- Checking the plumb of the revealPlace a two-metre aluminium straightedge fitted with a calibrated tubular level, or project a cross-line laser, against the two inner cheeks of the reveal to measure the out-of-plumb in the plane and out of the plane.
- Measuring the diagonals and checking squarenessTake both diagonals of the opening with a workshop tape measure; a difference exceeding twice the permitted tolerance indicates a major misalignment of the lintel.
- Checking the wall thickness and warpingMeasure the finished thickness of the wall at the bottom, at mid-height and under the lintel to ensure that the ordered splay matches the accepted wall without twist.
When the measurements show a non-compliant opening, the joinery foreman must on no account store the joinery in the rooms or attempt a makeshift wedging that would engage his liability as contractor. The finding must be the subject of a notice of interruption and of defects recorded in writing to site management, under the duty of care obligations of the Code of Obligations (CO) and the contractual provisions of SIA 118 governing defects in the preparatory substrate.
- Precise identification of the axis, the floor and the door number according to the joinery marking plans.
- Numerical millimetre record of the out-of-plumb, out-of-level and diagonal differences found compared with the execution plans.
- Technical demonstration showing that fitting is impossible under the requirements of SIA 343 and the fire protection test reports.
- Formal request for the masonry or partition to be rectified by the responsible trade before delivery is rescheduled.
Immediate transmission of this measurement record with joint photographs protects the company against late-delivery penalties and clearly sets out the duties of the other trades to act on the construction site before deliveries resume.
Dealing with non-conformities and the rework protocol for the structural work
When the out-of-plumb or out-of-square deviation exceeds the adjustment margin of the hardware and the overlap of the splays, the leaves and frames must remain on their transport pallets. A deviation of 10 mm over the height is compensated by careful wedging of the frame and a controlled connection joint. However, a deviation of 30 mm rules out the geometry of the work: forcing the installation under these conditions causes twisting of the jambs, rubbing of the leaf on the strike plate, or the impossibility of guaranteeing airtightness and fire resistance.
- Instrumented joint inspection recordThe lead fitter draws up an opening sketch recording the diagonals, laser level measurements and plumb checks with the two-metre straightedge. These measurements establish the excess over the tolerances set by SIA 343.
- Written notification as notice of defectsA formal reasoned notice is sent the same day to site management, in accordance with the rules of the Code of Obligations (CO) and SIA 118. The document records the halt of unloading operations and the formal notice to rectify the substrate.
- Remediation by the responsible companyRectification is the exclusive responsibility of the mason or plasterer: chipping back the concrete with a chisel hammer, fibre-reinforced plumb screeding, or realigning the dry-lining studs to restore the contractual rough dimensions.
- Release check and fittingThe joiner returns to the construction site only after a rework slip validated by site management has been issued and the perfect straightness of the reveal has been verified on the spot.
This strict protocol protects the profitability of the joinery workshop. An opening rectified to the execution tolerances allows immediate plumb fixing, respects the regulatory rebate gaps and ensures the work warranty is issued without technical reservation.
Frequently asked questions
How can you quickly check for twist in a door opening on the construction site?
The most direct method is to cross two nylon strings stretched between the four opposite corners of the rough opening. If the strings touch exactly at their central intersection, the plane is true. A visible gap between the strings immediately reveals warping of the wall. With a cross-line laser, a vertical plane is projected into the reveal to measure millimetre deviations at the four rebate corners.
What should you do if site management orders fitting despite 25 mm of out-of-plumb?
The team leader immediately makes detailed written reservations, sent by registered letter or official email to site management. Under the Code of Obligations (CO) and SIA 118, the contractor points out that this out-of-plumb prevents the leaf from closing correctly and voids the sealing warranty. If the client maintains the written order, fitting is carried out under the sole responsibility of site management.
Does SIA 343 permit tapering a frame to make up for an out-of-square reveal?
SIA 343 does not permit structural alteration of a prefabricated frame to hide a defect in the structural work. Planing the back of a jamb weakens the mechanical strength of the frame, destroys the factory finish and compromises the holding power of the mechanical fixings. On certified fire door sets, any dimensional modification of the timber or of the frame section is strictly prohibited, as it would render the fire conformity certificate completely void.
Who pays for storage and the extra trip following the reasoned refusal of a non-compliant opening?
Where the refusal is properly supported by measurements outside the tolerances of SIA 343, the extra costs are borne by the client or by the company that built the defective masonry. The joiner invoices the unproductive travel hours, the return unloading at the workshop and the costs of extended storage of the door sets. These financial claims rely on the notice of defects drawn up before any fitting work begins.
Texts and standards cited
- SIA 343Doors and gates: dimensional tolerances, plumb and functional criteria
- SIA 118General conditions for the execution of construction work and handling of notices of defects
- Code des obligationsGeneral rules on the contract for work and the contractor's duty to give notice