🧱 CFC 273Claddings, skirting boards and parquet installationChapter 7 of 10 in the section

Cladding a staircase: step-by-step survey, consistent riser height and stair nosing

This chapter guides you step by step through the timber cladding of a raw concrete staircase. You will learn to carry out a complete step-by-step survey, to recalculate a strictly constant walking line in order to compensate for defects in the structural work, and to fix stair nosings that meet Swiss safety requirements.

Key takeaways

  • An individual survey with a profile gauge compensates for out-of-square steps and variations in the concrete pour.
  • The starting and finishing level references dictate the overall recalculation of each finished riser height.
  • The SIA 343 standard governs the permissible deviations in order to ensure a walking rhythm without tripping.
  • The stair nosing must combine a controlled projection with an effective and durable anti-slip treatment.

Surveying the concrete substrate and recalculating the walking line

On a building construction site, a reinforced concrete flight of stairs never has strictly identical dimensions from one step to the next. Formwork deformation, settlement of the fresh concrete and structural-work tolerances create frequent deviations of 5 to 20 millimetres in riser heights, as well as twisted treads and out-of-square angles along masonry strings or wall strings. Cladding in interior joinery is not about copying these irregularities, but about creating a new, perfectly continuous geometry.

Before any cutting in the workshop, the joiner carries out the survey from the official level mark transferred by the masons at one metre above finished floor. Measuring the steps one after another with a tape measure is out of the question, as reading errors would accumulate. The survey is carried out by laser levelling between the finished starting slab (including liquid screed and floor covering) and the finished arrival landing. This total height, divided by the actual number of steps, gives the exact theoretical height that each finished step must respect.

  1. Marking out the reference level lineProject the laser level onto the string walls to establish the actual finished level of the lower landing and the upper landing. Measure the raw vertical dimension of each step in relation to this horizontal reference plane.
  2. Individual template taking with a profile gaugePlace a stair gauge with articulated arms on each raw step. Record the usable depth, the stair width and the out-of-square angles against the side walls for each tread and riser.
  3. Calculating the compensation thicknessesCompare the surveyed raw dimension with the calculated finished theoretical dimension. Deduct the thickness of the solid timber or plywood tread panel to obtain the exact thickness of the shimming or levelling mortar to be added under each step.

Ensuring consistent riser heights and securing the stair nosings

For user safety, consistent step riser heights are an absolute ergonomic rule. The human stride unconsciously memorises the first step taken; a variation of only a few millimetres in the middle of the flight causes a misstep or a fall. The requirements of the SIA 343 standard for interior joinery work require manufacturing and installation tolerances to be kept within very strict limits, in order to maintain a constant walking rhythm.

Dimensional criteria and tolerances for staircase cladding
Technical parameterExecution requirementPermissible tolerance
Height variation between successive stepsCalculated height constant over the whole flightMaximum deviation of 2 mm
Stride formula (Blondel's rule: 2H + G)Target between 620 mm and 640 mmPermitted range of 600 mm to 650 mm
Projection of the stair nosing over the riserRegular overhang to support the foot15 mm to 25 mm depending on profile
Flatness of timber tread bearing surfaceLevelled or shimmed substrate under the treadMaximum deviation of 1 mm under a 1 m straightedge

Height adjustment is achieved on the construction site by a combination of calibrated rot-proof shims and polymer adhesive with high gap-filling capacity, or by a preparatory self-levelling compound if the deviations exceed 15 millimetres. The timber riser is cut to size in the workshop or planed to fit on site: it rests on the lower tread and supports the rear underside of the upper tread, thus locking the vertical dimension.

The stair nosing is the element most exposed to mechanical wear and the direct guarantor of safety against slipping. A rounded nosing with a radius of 4 to 6 millimetres withstands impacts better than a sharp edge liable to chip under foot traffic. According to Swiss accident prevention recommendations of the Accident Prevention Bureau, the walking surface must incorporate an effective anti-slip device located less than 20 millimetres from the front edge.

  • Workshop grooving of two or three longitudinal saw cuts fitted with a flexible rubber profile inserted by force.
  • Flush inlay of a ribbed or anodised metal profile, screwed or glued into a rebate machined in the face.
  • Pouring of a polyurethane or epoxy resin loaded with carborundum grit into milled grooves at least 3 mm deep.
  • Creation of a visual contrast on the stair nosing to clearly delineate the step when descending, particularly in poorly lit stairwells.

Step-by-step template survey and compensation of structural-work irregularities

On a building construction site, a staircase cast in place in concrete or made of precast elements never has two strictly identical steps. Concrete shrinkage, formwork inaccuracies and the tolerances accepted during casting generate frequent deviations of 5 to 15 millimetres in the tread, the riser height or the squareness relative to the wall strings. Installing timber cladding without individual adjustment exposes the joiner to visible misalignments and to an irregular walking rhythm that is dangerous for users.

Interior joinery elements and their connections to the structural work must absorb the permissible dimensional deviations of the load-bearing structure while ensuring functional consistency, safety in use and durability of the joints.

norme SIA 343

Taking measurements on raw concrete rules out simply using a tape measure from one step to the next. The joiner carries out an individual survey of each step using an articulated-arm stair marking gauge, a rigid template cut to size from fibreboard or a 3D laser theodolite. This method precisely captures the out-of-plumb faces of the concrete strings, the depth variations between the left and right of the tread, and the bowing of the underside.

To comply with absolutely consistent heights after cladding, the joiner establishes a recalibrated theoretical walking line. The total height to be climbed between the two finished floors is divided by the actual number of risers to set the step constant. Concrete steps that are too low are raised with rot-proof adjustment shims in high-density polypropylene, bedded in a resin mortar or an elastomer polymer mounting adhesive with high gap-filling capacity. High points in the concrete are marked or removed by localised chiselling before fixing.

Nosing profiling, grooving and anti-slip devices

Cladding a solid step is not limited to a board cut square and glued onto a levelled base. The design of the front face determines the mechanical resistance to repeated use and the service life of the work. The stair nosing directly receives the shear stresses under the sole when descending. It must have a balanced projection, machined with a regular rounding or chamfer avoiding longitudinal splitting along the timber grain.

Comparison of stair nosing and grip treatment systems in interior joinery
SystemMachining and installationBehaviour under trafficMaintenance in use
Solid timber nosing with softened rounding (R3 to R5)Workshop machining with router, 15 to 20 mm overhang, groove under nosing for riserSensitive to point impacts, edge protected by the radius of curvatureRequires a very durable workshop oiled or varnished finish
Recessed metal profile with aluminium grooveCalibrated groove in edge rebate, invisible mechanical fixing or gluedAbsolute protection of the timber edge, excellent mechanical resistanceEasy replacement of the flexible elastomer strip without touching the tread
Poured mineral resin anti-slip stripTwo grooves 8 to 10 mm wide on the front third, pouring of abrasive epoxy resinMaximum grip barefoot or shod, set flush without a stepCleaning by gentle brushing, repair by localised re-injection
Ribbed machining directly in the solid timberRouting of 3 to 4 parallel flutes at the end of the treadDrainage of residual water, moderate grip on dry timberProgressive clogging of the grooves, regular cleaning required

The overhang of the stair nosing relative to the riser must not exceed 25 millimetres so as not to create a leverage effect liable to lift the panel under heel pressure. In the joinery workshop, the underside of the tread is grooved across its whole width about 15 millimetres back from the nosing in order to receive the top edge of the riser. This rebated or tongue-and-groove joint guarantees a durably closed joint, even during the seasonal humidity variations of the structure.

Installation is traditionally carried out from the bottom upwards. The first riser is adjusted on the starting screed, then the first tread is glued and checked with a spirit level in both axes. The use of a polyurethane hybrid adhesive with progressive setting allows the shimming to be fine-tuned during polymerisation without resorting to visible screws on the wearing surface. Each following tread fits onto the lower riser, thus ensuring perfect continuity of the walking line over the whole flight.

Managing major structural-work deviations and recourse on the work

On the construction site, the confrontation between the raw concrete staircase and the joinery pieces frequently reveals deviations incompatible with direct installation. If the structural-work tolerance exceeds the allowance provided under the first riser or at the arrival landing, installation must not begin. Consistency of heights after cladding is a strict functional requirement: a variation of more than a few millimetres between two consecutive steps creates an immediate tripping risk for users.

When the individual survey of each step reveals a cumulative drift in the flight, the joiner must send a written notice of non-compliant substrate to the site management, in accordance with the rules of the Code of Obligations (CO). Rectification is the mason's responsibility: chiselling of bumps, grinding of the concrete or fibre-reinforced rapid-setting levelling to restore a sound geometric bearing surface. The minimum thickness under the timber tread must remain sufficient to accommodate the elastomer adhesive bead or the recommended adhesive mortar bed.

In the event of a dispute concerning the edges, compliance is assessed on the alignment of the strings and the safety treatment of the projections. The SIA 343 standard governs the provisions relating to finishing work elements and to adjacent door openings or access. The stair nosing and anti-slip treatment tolerate no compromise: an added profile that is not flush, a groove filled with poorly polymerised resin or an excessive projection create a non-conformity engaging the liability of the installation company.

Frequently asked questions

How to react if the first concrete step is two centimetres too high?

The allowance for the lower finished floor must be checked immediately. If the screed and tiling do not compensate for this level error, the tradesperson sends a written notice to the site management. The technical solution is to have the concrete ground down by the masonry contractor before the joiner's intervention, in order to preserve the nominal thickness of the timber tread and ensure a first riser strictly equal to the following ones.

Which adhesive should be preferred for fixing solid timber treads onto concrete?

Installation is carried out using a one-component hybrid polymer or polyurethane adhesive with high elastic resistance. This material absorbs the differential expansion between the mineral concrete and the timber while providing acoustic insulation against impact noise. The concrete must first be dusted off, dry, free of surface cement laitance and treated with a suitable bonding primer if the substrate is porous or powdery.

How to treat the anti-slip on a new solid stair nosing?

Two techniques prevail: machining one or two grooves fitted with a flexible recessed elastomer profile, or inserting a corundum strip cast in a dedicated recess. The anti-slip must be located between ten and fifteen millimetres from the leading edge. It must lie perfectly flush with the timber surface with a maximum projection of one millimetre, to secure the foothold without forming a rigid stop that causes a fall when descending.

Can an out-of-plumb riser be corrected by spot shimming?

Spot shimming remains prohibited if it leaves a clear void behind the riser. A push from the foot when climbing would eventually deform or split the timber. Continuous plywood furring strips adjusted to the template are used, secured to the concrete by plugging or direct gluing. The whole thus forms a continuous, solid bearing surface that guarantees the mechanical rigidity required by Swiss professional finishing-work standards.

Texts and standards cited

  • norme SIA 343Requirements applicable to finishing work elements, passages and adjacent doors
  • code des obligationsContractor's duty to notify in the case of a defective substrate or one compromising proper execution