Key takeaways
- Dome lifting always results from mechanical restraint at the edges when the floor swells in summer.
- Remedial work is carried out exclusively at the perimeter by creating an expansion gap suited to oak.
- Perimeter cutting with a plunge saw mounted on a guide rail ensures a clean, straight cut.
- The parquet needs several weeks to settle naturally back flat onto its screed.
Diagnosing dome lifting and identifying mechanical restraints
During the summer period in French-speaking Switzerland, the relative humidity of the ambient air in dwellings without air conditioning frequently exceeds 65 to 70 %. Solid oak, a hardwood with a high tangential shrinkage and swelling coefficient, absorbs this high relative humidity and naturally increases in volume across the grain. When a wide room does not have the expansion gaps required by SIA 253, the restrained expansion generates considerable axial compressive stresses. Unable to expand horizontally against the masonry, the boards buckle upwards, creating a characteristic dome in the middle of the room with a hollow sound underfoot.
Diagnosis on the construction site begins with a visual and tactile inspection of the entire perimeter. The joiner looks for hard contacts where the wood physically touches the masonry, lightweight partitions, metal door thresholds or heating pipe sleeves. A utility knife blade or a thin metal shim slid under the skirting board immediately shows whether there is no gap. Often, the floor was laid in direct contact with the plasterboard lining without respecting the clearance tolerances.
| Perimeter element | Restraint symptom | Joinery action required |
|---|---|---|
| Door frame bases | Board cut tight against the door frame | Recut the mitre on the underside of the jamb |
| Radiator pipe penetrations | Hole drilled to size with no radial clearance | Enlarge into a slot with a mortise chisel or oscillating tool |
| Longitudinal perimeter partitions | Last row jammed under the wall plaster | Rip the edge completely along its whole length |
Skirting board removal, perimeter machining and stabilisation process
The remedial work requires careful removal of the skirting boards in order to protect the wall finishes and to reuse the existing profiles if the client so wishes. The work follows a strict sequence to avoid tearing off the plasterboard or damaging recent paintwork.
- Score the upper acrylic jointCut the flexible joint at the top of the skirting board with a workshop knife along the whole length of the room to avoid tearing off the paint or wallpaper when it is removed.
- Free the skirting board with gentle leverageSlide a wide spatula or a joiner's crowbar protected by a sacrificial shim behind the skirting board, in line with the fixings or glue points, then pull perpendicular to the wall.
- Number and store the boardsWrite the removal order on the back of each skirting board with a grease pencil to make refitting easier later without recutting the mitres.
- Machine the perimeter expansion gapSet the plunge circular saw on its guide rail with the depth stop adjusted to the board thickness minus one millimetre, supplemented by an oscillating cutter in the dead corners.
The expansion space created at the edge must be calculated according to the overall dimension of the room. SIA 253 recommends perimeter gaps suited to the foreseeable dimensional changes of timber parquet floors, generally 10 to 15 millimetres depending on the span perpendicular to the boards. Once the milling is done and the surplus wood vacuumed up, the parquet does not drop back immediately. Solid oak has a shape memory and the friction of the tongue-and-groove joints temporarily keeps the lifting in place.
From a legal and contractual standpoint, who bears the cost of this remedial work depends on the agreements governed by SIA 118 or the Code of Obligations (CO). If the joiner failed to allow for the required hygrothermal gap during the initial installation, the work falls under the works warranty for defective installation. If, however, the restraint comes from skirting boards nailed through the boards later by another trade or from abnormal ambient humidity caused by a concealed water leak, a formal technical report clears the joinery firm of responsibility.
Kinetics of the dome settling and readjustment of the perimeters
After the remedial milling around the room, solid oak does not drop back onto the screed instantly. The wood fibres compressed laterally during the restraint retain a residual deformation due to creep under hygrometric stress. Trying to flatten the dome immediately with a static load or mechanical blows would destroy the tongue-and-groove profile. The relaxation of the network of glued or floating boards requires a gradual balancing period, depending on the ambient moisture content and the thickness of the oak.
During the relaxation phase, the room must be kept in strictly stabilised climatic conditions, in accordance with the requirements of SIA 253 on bonded and floating floor coverings. The relative humidity of the air must be regulated between 40 % and 60 % at a temperature of around 20 °C. If the remedial work takes place during a humid summer heatwave, using a site dehumidifier lowers the water vapour pressure without causing abrupt shrinkage. The joiner checks that there are no secondary hard points: door reveals, radiator pipes passing through or internal corners where a board can slip at an angle and recreate a parasitic stop.
| Check stage | Technical measurement | Checking tool | Tolerance permitted under SIA 253 |
|---|---|---|---|
| After machining (D+0) | Checking the residual gap under the edges | Thickness gauge or depth gauge | Gap of at least 12 mm around the entire perimeter |
| Stabilisation (W+2 to W+4) | Monitoring the residual deflection of the dome | 2 m straightedge and graduated wedge | Continuous decrease in height under the straightedge |
| Final equilibrium (W+6 to W+8) | Final flatness before refitting the skirting boards | 2 m straightedge laid diagonally | Deviation of no more than 2 mm under the 2 m straightedge |
| Moisture check | Residual moisture content of the oak | Calibrated contact moisture meter | Moisture content between 7 % and 11 % |
Once the floor has settled back completely and the tolerances of SIA 253 have been met, the joiner adjusts the trims. If the expansion gap created exceeds the thickness of the original skirting board, it can no longer cover the gap by at least 5 mm as required. Two workshop solutions apply: making bespoke skirting boards of increased thickness with a discreet upper chamfer, or adding a counter-profile fixed to the bottom of the existing skirting board. The skirting boards are then nailed or screwed mechanically to the load-bearing wall or partition, without any gluing or clamping that would bear on the parquet boards.
Contractual warranty, remedial work and acceptance of joinery works
The absence of a perimeter gap is an original execution defect. Even if the problem only appears after several months, with the first humid summer heat, the technical cause predates handover. Dome lifting therefore falls under the responsibility of the firm that carried out the installation. The legal framework of the Code of Obligations (CO) requires the contractor to guarantee their work against defects that impair the value or the agreed use of the work, with a five-year limitation period for building construction. Where the works contract is subject to SIA 118, the client may notify the defect at any time during the two-year warranty period.
- Joint inspection record of the extent of the dome and of the crushing of the edges before any work on site.
- Official record of the building's thermo-hygrometric conditions at the time the claim file is opened.
- Formal check of the presence or absence of installation wedges left behind at the initial acceptance.
- Deciding on the repair solution: protective perimeter machining versus complete removal of the floor.
- Joint signature of the remedial work record after the floor has returned to flat and the wall trims have been refitted.
Remedial work by perimeter sawing restores the conformity of the work without affecting the longevity of the parquet, provided the deformation has not caused the adhesive to debond from the screed or torn off the surface layer of the mineral substrate. The joiner must record in writing, in the remedial report, the final gaps obtained under each skirting board and door threshold. This document attests compliance with the technical directives of SIA 253 and is a condition for closing the dispute with the client or site management.
Escalation protocol if the return to flat fails and heavy remedial work
When the edge milling that frees the perimeter gaps prescribed by SIA 253 does not allow the buckling to subside after several weeks of climatic stabilisation, the joiner is faced with irreversible plastic deformation of the material or a structural failure of the floor build-up. During prolonged mechanical restraint under high humidity, the transverse fibres of solid oak undergo permanent cell crushing. Even after re-cutting a free space of ten to fifteen millimetres along the skirting boards, the compressed boards refuse to settle under their own weight and keep a marked bulge in the centre of the room.
- Shear failure of the adhesive bed or surface debonding of the cement screed, causing outright detachment and a hollow sound underfoot.
- Splitting, breaking or forced jamming of the tongue-and-groove joints, mechanically locking neighbouring boards in their curved geometry.
- Presence of hidden residual hard points: risers passing through without a compressible sleeve, installation wedges left under a door frame or fixings of built-in furniture passing through the parquet to the structural work.
Faced with this mechanical damage, perimeter remedial work is no longer enough and zone-by-zone repair is required. The team makes a splitting cut with a plunge circular saw guided on a rail directly along the axis of the crown board, to relieve the residual stresses instantly. Boards whose edges are crushed are removed with care. The joiner then inserts stabilised solid oak boards, whose lower groove lip has been carefully planed, glued over the full surface onto the dust-free substrate with a loose tongue added to restore the mechanical continuity of the floor.
Frequently asked questions
How long must you wait to see the floor return completely flat after milling the perimeter?
After the edges have been machined with the trimming saw, the downward settling is never instantaneous. Allow generally between two and four weeks for the solid oak to release its residual stresses and for its moisture content to balance with the ambient air. During this observation period, the skirting boards must not be refitted. If the boards remain raised beyond a month despite humidity conditions having returned to compliance, work in the centre becomes mandatory.
Can the original skirting boards be reused after removal during a remedial intervention?
Reuse depends on the original method of fixing and on the size of the new expansion gap. If the skirting boards were nailed or screwed onto battens, careful removal with a flat crowbar often allows them to be recovered intact. If, however, the compensating milling has widened the perimeter gap beyond their covering thickness, you must fit new, thicker skirting boards or add a suitable counter-profile to guarantee compliant concealment under SIA 253.
Should the dome be weighted with heavy loads to force the parquet back down?
Weighting the centre of the dome with cement bags or concrete blocks is a common mistake to be avoided. This artificial vertical pressure on compressed oak boards risks permanently breaking the tongues and grooves, and even shearing the adhesive bed beneath. The return to flat must happen naturally and gradually, solely through restoring the perimeter expansion gap and regulating the indoor climate.
Who bears the cost of repairing the parquet, the installing joiner or site management?
If the absence or insufficiency of the perimeter edge gap is formally established under the skirting boards, the defect is the joiner's responsibility under the contractual warranty according to SIA 118. The craftsman then bears the cost of removal, machining and remedial work. However, if the lifting results from excessive building humidity caused by late plastering work without ventilation, a sharing of responsibility may be negotiated.
Texts and standards cited
- SIA 253Resilient, textile and wood floor coverings and parquet - Requirements and execution
- SIA 118General conditions for the execution of construction works