Key takeaways
- Fitting a tarpaulin immediately turns the metal frame into a genuine sail exposed to the wind.
- The wind overload requires the anchor grid on the load-bearing façade to be tightened drastically.
- Any modification to the enclosure requires instructions adapted to sheeting or a specific engineering calculation.
- Art. 3 OPA requires protective measures that comply with the recognised rules of technology.
Sail effect and wind overload according to standard SN EN 12811
Erecting unclad working scaffolding allows most of the airflow to pass through the tubular standards, ledgers and decks. As soon as a general contractor, a plasterer-painter or an asbestos removal team installs impermeable sheeting to protect the environment or maintain a working temperature, the façade's permeability drops to zero. The temporary works then behave like a huge rigid sail secured against the structural work. Peak dynamic pressure acts over the entire covered area, tenfold increasing the horizontal tensile and compressive stresses transmitted to the ties.
Scaffolding must be designed, erected and protected to resist foreseeable combinations of actions, specifically including dynamic wind loads acting on impermeable or permeable coverings.
SN EN 12811
Standard SN EN 12811 defines the aerodynamic coefficients to be used when calculating temporary structures. For solid reinforced polyethylene sheeting, the drag coefficient approaches the maximum value of a continuous solid wall, whereas micro-perforated netting retains partial permeability that must be justified. This wind overload due to sheeting does not merely generate a force perpendicular to the façade: it also generates significant shear forces parallel to the walls under grazing winds, which can twist the end bays or cause local buckling of the standards.
| Structure configuration | Aerodynamic behaviour | Main impact on anchors |
|---|---|---|
| Bare structure (tubes and decks) | Virtually total permeability to airflow | Wind loads limited to tubular sections |
| Micro-perforated debris netting | Permeability reduced by 30% to 50% | Moderate increase in tie tensile forces |
| Solid impermeable or heat-shrink sheeting | Full sail effect with no permeability | Tensile and compressive forces quadrupled |
Densification of anchors and compliance with instructions adapted to sheeting
On conventional unclad scaffolding, the standard tying grid is generally spaced vertically every four metres and horizontally every two bays, with systematic placement on edge standards. Adding solid sheeting renders this arrangement immediately obsolete. Densification of anchors becomes essential to prevent façade wall plugs pulling out or scaffolding couplers failing. In most sheeted configurations, the anchor grid must be doubled, or even installed on every standard at every platform level in exposed zones.
- Instructions adapted to sheeting
- Official technical document provided by the scaffolding system manufacturer or drafted by a qualified civil engineer, detailing precisely the anchor pattern, type of plugs, and geometric restrictions applicable when tarpaulins or nets are installed.
- Review of the requested configurationCheck the total height of the structure, geographical exposure within the meaning of load standards, and the nature of the masonry or concrete substrate before starting any sheeting installation.
- Consultation of the manufacturer's technical instructionsCheck the anchor grid permitted by the instructions adapted to sheeting. If the situation exceeds standard limits set out in the technical manual, have a structural calculation note produced by an engineer.
- Installation of supplementary anchorsDrill and install the additional eye bolts and mechanical or chemical anchors to complete the required grid, ensuring compliance with edge distances in the concrete.
- Site pull-out testingCarry out pull-out tests using an extraction dynamometer on a representative sample of fixings to validate the load-bearing capacity of the façade material.
- Progressive installation and fixing of the fabricSecure the sheets of tarpaulin in an orderly manner using bungee cords or sacrificial ties designed to fail in extreme storm conditions without destroying the metal frame.
Anchor dimensioning does not only concern the number of attachment points, but also their mechanical typology. On sheeted scaffolding, tie tubes must systematically be connected to both standards (inner and outer) using right-angle couplers to form a rigid triangulation, preventing frame overturning under wind suction. Any connection failure results in eccentric loads that invalidate the load-bearing calculations defined by standard SN EN 12811. Without the formal validated diagram of instructions adapted to sheeting, no scaffolder must authorise the textile enclosure of a structure.
Transmission of forces to façades and strengthening of connections
Fitting impermeable or micro-perforated sheeting transfers all aerodynamic pressures and suctions directly into the scaffolding standards. When the wind hits the structure, the force no longer passes through bare mesh: the structure undergoes a perpendicular horizontal thrust that tends to crush the tie tubes against the masonry, combined with a leeward pull-out force capable of extracting anchors. A standard single-tube tie fitted to the inner standard is then insufficient to stabilise the entire bay.
To prevent racking distortions induced by gusts, the scaffolder must systematically link inner and outer standards using V-ties or double anchors. If the fixing only holds the wall-side standard, the sheeted outer standard deflects under pressure, twists the frames, and dislodges the working platforms. The mechanical connection must therefore form an undeformable triangle linking the outer node to the anchor point in the load-bearing substrate.
| Connection type | Load resistance | Primary risk in high winds | Recommended installation |
|---|---|---|---|
| Single tube on inner standard | Direct tension only | Outer frame buckling and local pull-out | To be avoided on fully enclosed scaffolding |
| V-tie (two diagonal tubes) | Tension, compression and lateral thrust | Coupler distortion in case of insufficient tightening torque | Mandatory at scaffolding ends and every two levels |
| Short tie with façade stop | Pressure towards façade and axial tension | Crushing of render or slippage on smooth base | Must be wedged against reinforced concrete or bare reveal return |
| Double coupler on through transverse tube | Tension and compression distributed over both standards | Shear failure of anchor rods in case of excessive overhang | Preferred for exposed areas or roof corners |
The type of masonry substrate dictates the fixing method. In a reinforced concrete wall, expansion anchors with forged eyes or concrete screws provide the axial resistance required to absorb gust surges. In hollow clay brick or aerated concrete, however, mechanical expansion bursts internal walls under cyclic load: the use of chemical anchoring with injection sleeves is essential to distribute the stress over several cavities without cracking the material.
Operational measures, tension control and storm management
Installing tarpaulins requires a strict tying protocol to prevent repeated flapping of the fabric. Slack sheeting generates repeated dynamic shocks that destroy couplers and prematurely fatigue anchor plugs. The scaffolder uses elastic quick-ties or calibrated plastic cable ties, fitted to every perimeter eyelet along guardrails and vertical standards, maintaining uniform tension across the entire surface.
- Visual and mechanical check of anchors before installationCheck coupler tightening torque (approximately 50 Nm) with a torque wrench and verify proper holding of plugs in masonry by proof-load testing on a representative sample of the reinforced grid.
- Deployment and progressive securing of the fabricUnroll the tarpaulin from top to bottom, bay by bay, immediately securing upper and lower edges to structural tubes to prevent any uncontrolled wind catch during intermediate erection phases.
- Inspection of overlap areasOverlap fabric sheets by at least one standard width (approx. 30 cm) and securely tie twin eyelets together to prevent wind from rushing behind the protection and billowing the structure outwards.
- Installation of emergency pressure-relief devicesEnsure that safety fixings or pre-slit tear strips designed to release under extreme gusts are not obstructed by stray tubes or guardrail extensions.
On construction sites subject to level 3 or 4 weather warnings, sheeted scaffolding becomes a critical zone. If the calculations in the technical manual do not allow for exceptional wind speeds, the foreman must order the preventive roll-up or opening of the sheeting. Tarpaulins are then rolled up vertically and secured against the standards to restore the structure's original porosity and relieve the façade instantly.
Managing access during strong wind events also requires locking hatch covers and prohibiting access to upper levels. A tarpaulin torn by a storm must never be repaired or reattached during high winds: personnel wait for calm conditions to return before intervening, using a fall-arrest harness connected to verified anchor points.
Wind damage management and emergency securing
When a wind gust tears away tarpaulin fixings or loosens a façade tie, the structural behaviour changes instantly. The fabric flaps in the wind, induces repeated dynamic loads, and stresses the remaining anchors far beyond their static regime. In accordance with OTConst, at workplaces and passageways, measures must be taken so that workers are not endangered. The scaffolder intervenes to stop the failure without being exposed to the sudden breakage of a tie.
- Immediate cordoning off and closure of the zoneClose pedestrian access at the foot of the façade and prohibit movement on decks. Deploy warning tape and inform site management to evacuate finishing work trades.
- Pressure relief of the fabric from the undersideSlit or slash the tarpaulin using a safety knife from inside the secured bays to eliminate the air-pocket effect and immediately remove tensile stress on the structure.
- Installation of replacement anchorsDrill new anchor points into sound concrete substrate in the immediate vicinity of pulled-out eye bolts, observing edge distances specified by anchor manufacturers.
- Structural check and re-armingCheck the tightness of right-angle couplers on standards, verify the straightness of tubular standards, and re-lace a new net or tarpaulin according to the approved layout plan.
Every remedial intervention following a wind event must be recorded in written minutes submitted to the site manager. This document confirms the reinstatement of the tying grid prescribed by the manufacturer and the condition of the mechanical connections before reopening the scaffolding to façade trades.
Frequently asked questions
Can a painter fit protective sheeting without notifying the scaffolder?
No. Adding a tarpaulin turns permeable scaffolding into an impermeable surface subjected to heavy wind overloads. The façade craftsman alters the equilibrium conditions of the structure without calculation notes. The initial anchor grid designed for a bare structure becomes insufficient. Any installation of containment fabric requires prior adaptation of the fixing network by the scaffolder holding the work package, in accordance with the equipment manufacturer's technical specifications.
What should be done when severe winds pick up on scaffolding that is already sheeted?
If gusts exceed the values permitted by the system design, the scaffolder must open the surface to shed load from the structure. The intervention involves releasing perimeter ties or methodically slitting tarpaulin lengths to let airflow through. This emergency action eliminates the uplift and overturning forces exerted on the standards before façade anchor studs pull out of the masonry.
How do you densify anchors on a hollow clay brick façade?
Hollow bricks provide much lower pull-out resistance than in-situ concrete. To offset the overload transmitted by sheeting, the scaffolder replaces mechanical expansion plugs with chemical injection sleeves and threaded rods. They also increase the number of ties by doubling short links with horizontal tubes spanning two consecutive bays, thereby distributing perpendicular tensile loads across fragile masonry.
Why do manufacturer instructions often require double couplers under sheeting?
The wind load on sheeting generates slipping forces along vertical standards that are much higher than on a bare structure. To prevent anchor ledgers secured by right-angle couplers from slipping vertically under dynamic gust thrust, manufacturers prescribe check couplers fitted directly below the main fittings. This mechanical arrangement locks the position of tie bars and ensures frames remain level.
Texts and standards cited
- SN EN 12811Temporary works equipment - Scaffolds: Performance requirements and general design
- OTConstprotection against collapse of construction elements or falling objects and materials: at workplaces and passageways, measures must be taken so that workers are not endangered
- CP art. 229breach of the rules of the art of construction: whoever, in directing or executing a construction or demolition, intentionally breaches the rules of the art and knowingly endangers the life or physical integrity of persons is liable to a custodial sentence of up to five years or a monetary penalty; in the case of negligence, to up to three years or a monetary penalty
