Key takeaways
- Timber sole plates distributed under adjustable base plates prevent punch-through and stabilise each standard.
- Compensating for steps requires offset frames or modular structures erected in a stepped configuration.
- The stair eye requires immediate flush decking or complete edge protection.
- The clearance profile and emergency evacuation routes must remain clear throughout the operation.
Securing supports on flights and compensating for step height differences
Setting up a tubular structure in a stairwell confronts the scaffolder with irregular geometry. Each support point rests on a step whose nosing, tread, and material vary depending on the stage of the construction site. Placing a standard base directly on the edge of a step is strictly forbidden due to the immediate risk of spalling concrete, fracturing a stone step, or having the metal base plate slip on tiled or timber finishes.
The vertical load of a scaffolding standard must always be transferred to the centre of the tread, well away from the open edge. For bare concrete flights, using softwood balks or planks without through-knots, at least 45 millimetres thick, allows bridging over two to three consecutive steps. This distribution converts point loads into permissible linear reactions and prevents any lateral movement of the base plate.
- Checking the substrate and setting outCheck the mechanical strength of the steps and mark the vertical axis of the standards relative to the spandrel walls and temporary edge protection.
- Placing spreader planksLay bevelled wedges and continuous planks at least 45 millimetres thick on the treads, never overhanging the step nosing.
- Positioning adjustable base platesCentre the screw jacks with threaded collars on the timber sole plates and nail them through the holes in the steel base plate.
- Compensating for step risesAdjust the height of the jacks or insert standards of asymmetric lengths to achieve a first transom that is perfectly level with a spirit level.
Differences in height are compensated for using drop-forged steel collar adjustable base plates, combined with offset walk-through frames or modular standards of varying heights. The extension of the screw jacks must never exceed the maximum travel defined in the manufacturer's technical instructions, which is generally limited by a visible safety stop on the thread. As soon as the height difference exceeds the effective travel of a jack, the team uses short modular standards of 0.50 or 1.00 metre, secured with automatic wedge locks or right-angle couplers conforming to good trade practice.
Securing the stair eye and keeping the evacuation route clear
The central void of the stairwell forms a continuous shaft over the entire height of the building. As soon as a working platform or flight is bypassed, this stair eye creates a fall hazard of several metres. In accordance with art. 25 OTConst, openings in floors that present a fall hazard must be fitted with edge protection or a break-resistant, securely fixed cover.
- Stair eye
- Vertical open space between parallel flights of a stairwell, forming a continuous opening from floor to floor that requires partitioning or complete closing off during finishing work.
To neutralise this hazardous zone, two operational methods are available to the scaffolder depending on the space configuration. The first consists of fully closing off the stair opening at each half-pace landing by placing scaffolding decks with safety claws on short transoms, secured by lift-off retainers. The second option, used when the void is too wide to be bridged without obstructing work, requires the installation of rigid collective protection along every exposed edge.
Art. 22 OTConst sets out the requirements for edge protection with a top guard rail whose upper edge is at least 100 cm above the passable surface, at least one intermediate guard rail, a toeboard of at least 15 cm, and a maximum gap of 47 cm between elements. Assembling metal components in these awkward corners requires systematic tying into stringers or concrete shear walls to make up for the lack of diagonal cross-bracing in the narrow footprint of the structure.
| Work area | Main hazard | Required safety measure |
|---|---|---|
| Continuous stair eye | Falls from height across several storeys | Full flush decking or edge protection according to art. 22 OTConst |
| Step with narrow tread | Base instability and slipping | Continuous spliced plank beneath two jacks, fixed with wood screws |
| Rest landing | Obstruction of the evacuation corridor | Use of open walk-through frames leaving a clear passage |
| Soffit of flight | Impact injuries while moving around | High-visibility protective foam sleeves on low transoms |
Under no circumstances may the erection of stairwell scaffolding turn the main escape route into a dead end. Other trades must still bring materials up, and emergency services must be able to evacuate an injured person on a stretcher. The internal structure therefore incorporates purpose-built walk-through frames with a raised top transom, or cantilevers its outer standards against the spandrel wall using brackets fixed with pull-tested mechanical expansion anchors. The minimum clearance profile must be kept clear, free of diagonal tubular braces in the pedestrian path.
Erection method in confined spaces and bridging flights
Setting up a tube-and-fitting or modular structure in a stairwell demands meticulous execution due to the cramped layout, geometric variations, and lack of run-up space. The scaffolder systematically starts at the lowest point of the flight to set the first reference bay. Vertical standards never rest directly on concrete or tiling: timber sole plates at least 50 mm thick and with sufficient minimum surface area ensure load distribution across the step treads or storey landing. Screw adjustment jacks compensate for the height of successive risers, enabling exact levelling to receive the first frames or ledgers.
- Inspection and zero-level setting outMeasure the tread, riser height, and clear passage width. Place spreader planks across at least two consecutive steps to prevent point shear of the step nosing, then position the adjustable screw jacks.
- Erecting the first tower on the flightErect the vertical standards and tie them immediately with base ledgers and plan braces to ensure squareness. Lock the adjustment jacks using the wing nuts while checking levels on both axes with a spirit level.
- Laying the first temporary working platformInstall full decking with an access hatch and integrated ladder. This intermediate level serves as a safety platform for continuing erection towards upper flights.
- Tying-in and lateral stabilizationBrace the structure against spandrel walls or concrete shear walls using butt-tubes fitted with protective pads or mechanical anchors suited to the base material to prevent any overturning into the stair eye.
Three-dimensional stabilisation, ties, and maintaining clearances
The compactness of a stairwell prevents conventional external bracing with large façade crosses. The overall stability of the frame therefore relies exclusively on ties to the surrounding masonry and locking the standards between landings. Horizontal forces generated by trade activities (painters, plasterers, electricians) must be transferred directly to load-bearing walls. Scaffolders install transverse thrust jacks between opposite walls or drill for anchor eyebolts with expansion anchors, taking care not to damage step nosings or embedded services.
| Stairwell layout | Main constraint | Required support arrangement | Pre-commissioning check |
|---|---|---|---|
| Straight flight between two walls | Constant slope and narrow passageway | Continuous timber sole plates on steps and offset jacks | Slip resistance and transom horizontality |
| Wreathed or winder staircase | Variable treads and very narrow waist | Suspended transfer tubes or tube-and-coupler bridging beams | Tightness of right-angle couplers and locking of wedges |
| Open, tall stair eye | Fall from height hazard and chimney effect | Freestanding central tower with continuous sealed platforms | No gap exceeding 25 mm and presence of toeboards |
| Half-pace landing with access doors | Compulsory pedestrian route and clearance | Bridging portal using beams or cantilever brackets | Clear height under transom of at least 2.00 m |
Site coordination requires that foot traffic by other trades and emergency evacuation remain possible throughout the entire duration of the work. In accordance with Association of Cantonal Fire Insurance guidelines, the minimum passage width must never be critically obstructed. Where scaffolding partially obstructs the flight, the scaffolder must provide a protected walkway beneath a frame with protective debris decking above to prevent risks from falling tools, whilst maintaining access to floor isolation valves and distribution boards.
Actions to take in the event of structural failure or incident in a stairwell
Unexpected deflection under load, slip of a jack on a winder, or cracking of a step nosing requires a strict protocol. In confined spaces, the risk of structural collapse is immediately compounded by blocking the building's evacuation route. All work on the scaffolding must stop automatically: access to platforms and the flight is immediately barricaded with rigid guard rails and signposted.
- Immediate evacuation of the tubular structure and cordoning off the lower access at landing level.
- Visual inspection of standard plumbness and measurement of settlements at the distributed timber sole plates.
- Check tightening torque on right-angle couplers and inspect anchor drill-holes in concrete walls.
- Installation of emergency steel props to relieve the subsided standard before any readjustment of screw jacks.
According to art. 25 OTConst, openings in floors presenting a fall hazard must be fitted with edge protection or a break-resistant, securely fixed cover. This requirement applies especially to the stair eye should the temporary structure shift out of alignment. In the event of a serious non-conformity compromising stability, scaffolders must install temporary tube-and-coupler rakers anchored to opposing load-bearing walls before any load is reapplied.
If the prefabricated or masonry substrate shows structural defects, the team notes the damage in the site log and forwards the report to the engineering office. Work must not resume without a joint inspection of the load distribution setup and formal requalification of the working structure.
Frequently asked questions
How should adjustable jacks be positioned on very narrow winder treads?
On winder treads, the geometric constraints require bespoke packing. Whole-timber balks tied together are laid to compensate for slopes and spread the load over several treads. Base plates must rest centred on this timber platform, without overhanging the step nosing. A tubular tie ties the base together to prevent any slip.
What minimum clear width must be kept for emergency services on the stairs?
The flight must maintain a continuous clear opening sufficient to allow user evacuation and access by firefighters with their equipment. Unless an exemption is granted by the fire protection authority, a clear profile of at least 80 centimetres to 1 metre must be maintained along the standards. Diagonal and ledger bracing must never obstruct this emergency route.
Can scaffolding jacks bear directly onto floor tiles or natural stone?
Direct bearing is prohibited because the concentrated point load from the screw will fracture the floor finish. The scaffolder must insert a timber spreader sole plate, often backed with a neoprene elastomeric pad at least 5 millimetres thick to absorb surface roughness, prevent punch-through, and stop any sideways slippage on smooth finishes.
How can the stair eye between stringers be effectively closed off during work?
The stair eye acts as a continuous fall opening through the entire height of the building. It must be covered at each floor level with flush, secured scaffolding decks, or fully enclosed by rigid protection including a 15-centimetre toeboard, intermediate guard rail, and top guard rail at 100 centimetres, preventing tools or workers from falling through.
Texts and standards cited
- OTConst art. 25openings in floors: those that present a fall hazard must be fitted with edge protection or a break-resistant, securely fixed cover.
- CPbreach of the rules of the building trade: whoever, in managing or executing a building structure or demolition, intentionally breaches the recognised rules of the trade and knowingly endangers the life or limb of persons shall be liable to a custodial sentence not exceeding five years or a monetary penalty; if through negligence, to a custodial sentence not exceeding three years or a monetary penalty.