Key takeaways
- The use of netting is required when installing peripheral edge protection proves technically impossible.
- The free-fall height into the net must never exceed the maximum permitted value.
- Every anchor point on the framework must withstand the dynamic forces transmitted during an impact.
- The overlap between net panels requires lacing or rigorously measured overlapping.
Fall height and calculation of deflection under impact
During framework or roofing work, the installation of temporary peripheral edge protection is sometimes impracticable due to the geometry of the structure or the excessive risks incurred during its erection. In accordance with OTConst art. 29, when peripheral edge protection or facade scaffolding cannot be implemented, equivalent protective measures must be defined in writing with the support of a specialist. The safety net suspended from the underside is then the solution chosen to intercept workers in the event of a fall.
The vertical distance between the working level and the net must be reduced to the strict minimum. The allowable free-fall height must under no circumstances exceed 6.00 m, the ideal value remaining under 3.00 m to limit impact velocity and the severity of injuries. The further the net is from the working plane, the higher the kinetic energy developed by the falling body, thus increasing the elastic deformation of the mesh network.
- Net deflection under impact
- Maximum vertical deformation undergone by the net panel when absorbing the energy of a falling person. It includes the net's own deformation and any slippage of the connections.
It is crucial to anticipate the clear headroom available under the net. When arresting a body, dynamic deflection can reach several metres depending on the span width. No rigid obstacle (structural member, technical installation, material stored on the ground) must be located within the zone of maximum deflection of the net, otherwise a severe collision will occur along the arrest path.
Attachment points on roof frameworks and overlap of panels
Attaching a safety net places heavy demands on the supporting structure. Attachment straps or suspension ropes must be fixed exclusively to structural timber or steel members capable of taking substantial dynamic loads. Purlins, trusses or steel lattice nodes constitute valid anchor points, unlike battens, sarking boards or light building services conduits.
| Inspection item | Target value / Rule | Critical check point |
|---|---|---|
| Spacing of anchor points | 2.50 m maximum | Continuous fixing of the border cable or rope |
| Minimum strength per anchorage | According to manufacturer's instructions | Visual inspection of the condition of the supporting framework |
| Overlap between panels | 2.00 m minimum (without lacing) | No spreading possible under load |
| Lacing between panels | Continuous lacing rope | No opening greater than 10 cm between meshes |
Art. 82 LAA requires the employer to apply the necessary preventive measures recognised by technical standards. For the scaffolder, this involves rigorous assembly when several panels are juxtaposed to cover the area under the framework. Simple overlap without connection must reach at least 2.00 m. If the available space does not allow this overlap, the panels must be joined by a lacing rope threaded through each border mesh, ensuring perfect mechanical continuity without risk of separation under load.
- Support inspectionCheck the soundness of the purlins or framework members intended to receive the attachment straps.
- Perimeter fixingAttach the border rope every 2.50 m at most, ensuring uniform tension.
- Panel junctionProvide the 2.00 m overlap or carry out continuous mesh-by-mesh lacing between the elements.
- Acceptance of the installationRecord the verification on the record of acceptance of the work for the temporary structure before carpenters access it.
Installation of netting under roof frameworks and checking attachment points
When the installation of peripheral edge protection or facade scaffolding proves impossible or too dangerous due to the geometry of the framework, the use of collective secondary protective measures is prescribed. In these situations, the requirements relating to other fall protection measures set out in OTConst art. 29 mandate the implementation of a system selected by a safety specialist, such as underside safety netting.
The maximum free-fall height down to the net must not exceed the regulatory limit of 3 m. The deflection of the net under the impact of a person varies according to the span of the panel and the initial tension: a minimum clear zone must be maintained under the net to prevent any impact with structural members or equipment located beneath it.
| Installation parameter | Technical requirement | Construction site check point |
|---|---|---|
| Attachment points | Sized anchorage on load-bearing element | Validation of the timber/steel load-bearing capacity |
| Fall height | Less than or equal to 3 m 00 | Direct measurement from the working plane |
| Net tension | Limited initial sag | Checking the pull on the tie ropes |
Joining of panels and acceptance procedure on the construction site
To ensure seamless continuity of protection beneath the entire open area of the framework, the overlap of adjacent panels must comply with strict connection rules. Overlapping net strips are assembled using a continuous lacing rope or regularly spaced assembly karabiners to prevent any opening during an impact.
- Checking the supporting structureCheck the soundness of the purlins and principal rafters intended to receive the attachment straps or ropes.
- Installation and tensioning of panelsDeploy the net without damaging the meshes, secure the corners, then complete the perimeter connection on the framework.
- Connection and overlapOverlap adjacent panels and lace continuously along the overlapping borders.
In accordance with art. 82 LAA, the employer's liability entails implementing suitable equipment to safeguard the health of scaffolders and construction site users. For detailed pricing of safety net erection and hire services, refer to the tenders section.
Management of anomalies, excessive deformations and compliance procedures
When erecting a safety net on the underside of a roof framework, installation compliance relies on strict adherence to allowable fall heights and on the energy absorption capacity of the temporary structure. If, during visual inspection or after the fall of a heavy object, significant residual deflection is observed, the net must be immediately taken out of service. Permanent deformation indicates that the meshes or border ropes have exceeded their elastic limit. The scaffolder must then replace the damaged panels entirely, as the minimum energy absorption capacity required by technical standards is no longer guaranteed for a subsequent impact.
Anchoring to timber or steel frameworks constitutes a critical point. When sized attachment points exhibit play, localised corrosion on steel clamps, or a split in a timber purlin, the anchorage must be moved to a sound structural element. If it is technically impossible to position fixings according to the spacings specified by the manufacturer, the site safety officer intervenes to adapt the system. In accordance with OTConst art. 29, when the installation of peripheral protection or a standard net is technically impossible or proves too dangerous, equivalent protective measures must be defined and established in writing, involving an occupational safety specialist.
Another recurring defect concerns the parting of panels at junctions. If the minimum overlap is not maintained or if the lacing rope has slackened due to wind action, an opening is created, destroying the continuity of the protection. Scaffolders must then redo the lacing mesh by mesh with a compliant assembly rope, ensuring that no gap exceeding the permitted tolerances remains between the two elements.
| Observed anomaly | Main cause | Required corrective action |
|---|---|---|
| Significant residual deflection | Dropped load or plastic wear of meshes | Immediate dismantling and complete replacement of the panel |
| Slippage of the junction | Poorly tensioned lacing rope or excessive gap | Redoing of mesh-by-mesh lacing and overlap check |
| Cracking of the anchoring purlin | Overload on the timber structure or incorrect screw fastening | Relocating the fixing and validating the structural point |
| Insufficient ground clearance under the net | Low initial tension or excessive fall height | Retensioning of border ropes and revision of the layout plan |
Frequently asked questions
What should be done if the net deflection under impact risks hitting an obstacle under the framework?
If clearance under the framework is limited, the maximum fall height must be reduced by raising the level of the net or increasing the initial tension of the border ropes. If clear headroom remains insufficient to absorb the calculated deflection during an impact, access to the lower zone must be barred or a temporary rigid structure must be preferred.
How should an attachment point on a steel framework be handled without drilling?
On a steel framework where drilling is prohibited, attachment is carried out using certified textile tie-down straps or metallic beam clamps sized for the transmitted forces. The anchoring sling must wrap around the section in such a way as to avoid any longitudinal slipping or sharp edges that would damage the anchoring component.
What is the minimum overlap required between two underside net panels?
When two safety net panels overlap without continuous lacing, the minimum overlap must be respected in accordance with the manufacturer's instructions and trade rules, generally at least 2 metres. If the panels are joined by a mesh-by-mesh assembly rope, the overlap may be reduced, provided the joint offers equivalent strength to the panel.
Who must log the periodic inspections of nets erected under roof frameworks?
The competent person appointed by the employer for safety on the construction site inspects the visual condition of the net, the rope tension, and the soundness of anchorages. These checks must be recorded in writing in the construction site inspection report after every episode of bad weather, modification to the structure, or abnormal loading of the temporary structure.
Texts and standards cited
- OTConst art. art. 29 OTConstequivalent protective measures established in writing by calling upon a specialist when standard protections cannot be applied