Skip to content
Website
🧱 CFC 212Facade scaffolding: components, erection and dismantlingChapter 2 of 10 in the section

Base jacks: setting the plumb of the first lift and negotiating sloping ground

After this chapter, you will know how to set out base jacks, comply with the permitted thread extension, and pack the first lift of frames accurately. You will master transferring levels from the highest ground point, as well as the vertical step method using short frames to negotiate sloping ground safely.

Key takeaways

  • The working travel of the jack must never exceed the value certified by the manufacturer.
  • Setting out always starts from the highest point to ensure downward adjustment.
  • A perfectly level first frame prevents deformations and structural stresses at height.
  • Ground slopes are compensated for using short frames or single-standard offsets.

Setting out base jacks and mastering thread extension in accordance with standard SN EN 12811

The seating of facade scaffolding governs the overall geometry of the structure. A millimetric deviation at the base turns into several centimetres of out-of-plumb at the fifth lift, making the installation of diagonals and decking impossible without forcing the connections. The scaffolder always begins by identifying the bearing ground: on soft ground or compacted gravel, the placement of timber sole plates at least 40 millimetres thick is essential to prevent any punching shear.

Base jacks must be capable of transferring vertical and horizontal loads to the load-bearing structure or the ground, while maintaining adequate guidance inside the vertical standard.

SN EN 12811

The basic rule for setting out is to begin levelling from the highest point of the natural ground or access ramp. The jack positioned on this crest is adjusted to the minimum of its travel, generally between 50 and 80 millimetres above the base plate, thereby leaving the entire adjustment range for the standards located further down.

Inspection of setting-out criteria for base jacks
Inspected itemTechnical requirementRisk in the event of non-compliance
Base plateIn full contact with the sole plateStress concentration and timber failure
Usable threadExtension within the manufacturer's limitBuckling of the stem under axial load
Vertical axisPerpendicular to the setting-out planeParasitic bending stresses on the frames
Collar nutTightened with no residual playSettlement under the load of upper lifts

On the construction site, the responsibility for erecting a stable structure lies in complying with the accepted rules of the trade. Art. 229 CP criminally penalises anyone who intentionally or through negligence violates the accepted rules of building construction and endangers the life or physical integrity of persons. Misjudging jack extension directly weakens the structure against vertical loads and wind effects.

Setting the plumb of the first frame and compensating for sloping ground

The erection of the first scaffolding lift is carried out using a spirit level at least 1.20 metres long or a site laser level. A reference bay is installed first: two base jacks, two initial frames connected by an erection guardrail, and a deck with a trapdoor. This first cell serves as the absolute benchmark for the longitudinal alignment of the facade.

  1. Transferring the reference levelFrom the highest jack screwed down to its minimum, mark the horizontal level on the adjacent wall or structure to project the elevation towards the downslope jacks.
  2. Adjusting the collar nutsTurn the collar nuts on the subsequent jacks to bring the top transom of the first frame exactly onto the horizontal line.
  3. Checking plumb and squarenessCheck the verticality of the standards on both faces (longitudinal and transverse directions) before engaging the bracing diagonals.
  4. Locking the first bayClip in the working decks of lift 1, which secure the squareness of the system before any linear extension.

When the ground slope exceeds the permitted working travel of the base jacks, the scaffolder must carry out a vertical step using modular components. To do this, one-metre half-frames or specific starter standards are used to absorb the break in slope, whilst maintaining the continuity of decks and guardrails.

Every change in level requires specific bracing. The connection between the stepped standard and the main bay is completed with right-angle couplers and steel tubes when standard wedge connections do not align. The final result must provide perfect alignment of the vertical standards, without warping, so that subsequent wall anchors operate purely in tension-compression.

During these packing and adjustment operations, the team remains particularly attentive to posture and falling parts. In all cases, art. 6 OTConst requires safety helmets to be worn during the erection and dismantling of scaffolding, protecting personnel at the foot of the facade against any risk of falling tools or wedges.

Transmission of vertical loads and packing beneath jack base plates

The overall stability of facade scaffolding depends entirely on transferring vertical loads at the base of the standards. The adjusting collar nut of the jack applies a concentrated load to its base plate, which must transfer this pressure to the ground without causing differential settlement. Where the bearing ground is soft, backfilled, or unstabilised, placing metal base plates directly on the ground is prohibited because it causes major issues as soon as the upper lifts are erected: overturning of frames, jamming of decks, and warping of diagonals.

To ensure adequate distribution of point loads, the scaffolder installs timber sole plates under each base jack. Packing timbers must have sufficient dimensions to spread the loads over a wider bearing area. On natural ground or compacted fill, preference is given to continuous heavy timbers connecting at least two consecutive jacks, which binds the seating of the facade plane together and reduces the risk of localised punching under self-weight and live loads.

Selection criteria for sole plates according to bearing substrate type
Substrate typeRequired load-spreading deviceMinimum thicknessMandatory check
Concrete slab or rough raft foundationJack base plate placed directly or on neoprene padNot applicableAbsence of voids under base plate and debris swept clear
Asphalt pavement or compacted pavingSingle hardwood pad (fir/spruce)45 mmCheck for punching shear risk in hot weather
Stripped natural ground or stabilised gravelContinuous timber under standard line50 mmSeating stability following initial settlement
Unconsolidated fill or disturbed slopeCrossed timbers in double layer or sleeper beams2 x 45 mmBearing capacity check and clearing of soft zones

Managing steep slopes: short frames, starter bases, and initial anchors

When the ground exhibits a longitudinal or transverse slope greater than the adjustment capacity of a threaded stem — i.e. a level difference exceeding approximately 300 mm between two adjacent supports —, levelling is achieved by stepping frames. The modular structure absorbs these height variations by inserting short compensation frames (0.50 m or 1.00 m units) or tubular standards connected by right-angle and sleeve couplers, thereby guaranteeing strict horizontality of the main working platform.

  1. Positioning the high starting pointBegin marking out and setting out from the highest point of the run. The jack of this first standard must be adjusted to its lowest position (extension of 50 to 80 mm) in order to retain the full downward adjustment range for subsequent frames.
  2. Integrating compensation framesAs soon as the slope creates a drop exceeding the working travel of the jack, replace the standard 2.00 m frame with a short 1.00 m or 0.50 m frame to pick up the horizontal alignment grid.
  3. Horizontal locking of base railsSystematically install ledgers and diagonals right from the seating level to encircle the base jacks. On sloping ground, this low triangulation prevents lateral sliding of the base downslope.
  4. Installing provisional initial anchorsFix the first facade anchors as soon as the first horizontal lift is formed. In the event of a stepped start further down, the longest standards experience increased buckling, requiring early wall fixing.

On steep slopes or alongside embankments, the scaffolder must ensure jacks are set back from the break in slope. The accepted rules of the trade regarding the stability of temporary works require a sufficient earth berm to be maintained between the packing base and the crest of the earthwork to prevent any slope shear failure under vertical load.

Pursuant to art. 3 OPA, the employer shall take the measures and precautions that correspond to recognised technical safety rules. The scaffolding foreman formalises these checks in the construction site setting-out record before authorising the erection of the upper bays.

Managing setting-out non-conformities: settlement, out-of-plumb, and erection blockages

When the setting-out of the first frame drifts, every metre erected in height magnifies the plumb error or standard twist. Art. 365 CO provides that if the material supplied by the client or the ground designated by them is found to be defective, or if any other circumstance compromises the proper or timely execution of the work, the contractor shall immediately inform the client, failing which they shall bear the consequences. On the construction site, the emergence of unstable ground under a sole plate or discovering a slope greater than erection plans requires halting the alignment process and sending written notification to the site management.

  1. Discovery and immediate halt of erectionStop assembly as soon as a spirit level or laser reveals a deviation exceeding the tolerances of standard SN EN 12811. Secure the bays already erected.
  2. Unloading and partial dismantlingDismantle the upper decks and guardrails to eliminate torsional stresses on the starter frames. Never operate a jack collar nut under full working load.
  3. Re-establishing the seating at the low pointClear softened ground, replace split sole plates, and readjust jacks while observing the minimum thread engagement inside the barrel. Restart from the lowest component.
  4. Joint inspection and resumptionVerify the horizontality of the first working deck using an optical level or a grade laser, then resume erection frame by frame.

If ground settlement exceeds the permitted travel of the jacks, the team replaces the standard frame with a short standard or establishes an intermediate landing. Art. 229 CP punishes anyone who, while directing or executing construction or demolition work, intentionally violates the accepted rules of the trade and knowingly endangers the life or physical integrity of persons with a custodial sentence not exceeding five years or a monetary penalty. Re-levelling the first lift governs all anchors above.

Frequently asked questions

What should be done if a base jack reaches its upper stop without taking up the slope?

It is forbidden to exceed the maximum extension specified by the manufacturer or to compensate with unstable stacks of timber offcuts. The team must insert a short frame or a starter standard to create a clean step. This allows the jack to be lowered back into its nominal adjustment range, while maintaining the thread engagement lengths prescribed by standard SN EN 12811 to ensure stability.

What plumb tolerance is permitted on first-lift standards?

Standard SN EN 12811 requires strict verticality from the outset, with a maximum deviation not exceeding one centimetre over the height of a frame. Any base alignment fault causes abnormal shear stresses in the upper connections and complicates the installation of working decks. Systematic checking with a plumb line or laser level is mandatory before erecting the second lift.

What should be done if soft ground settles under a jack sole plate after erection?

The scaffolder must halt progress, unload the affected bays, and relieve the settled standard using secure temporary propping. The ground bearing area must be widened using compliant, tightly fitted timbers, without loose stacking. Once the seating is stabilised and compacted, the jack is readjusted to bring the transom back to a perfect level, before re-locking all bracing diagonals of the structure.

Can horizontal misalignment be taken up by slightly tilting the base jacks?

No. Base jacks must always be set perpendicular to the base plate on a strictly horizontal surface. Tilting a threaded stem generates shear forces and a risk of ejection under axial load. If the facade leans or has a batter, the offset is compensated for using hop-up brackets or suitable anchoring, never by deflecting vertical standards from their initial axis.

Texts and standards cited

  • SN EN 12811Performance requirements and general design of facade scaffolding
  • COmaterials and ground: the contractor is liable for the sound quality of the materials they supply; if the material supplied by the client or the ground designated by them is found to be defective, or if any other circumstance compromises the proper or timely execution of the work, the contractor shall immediately inform the client, failing which they shall bear the consequences (para. 3).
  • CPviolation of the accepted rules of building construction: anyone who, while directing or executing construction or demolition work, intentionally violates the accepted rules of the trade and knowingly endangers the life or physical integrity of persons is liable to a custodial sentence not exceeding five years or a monetary penalty; in the event of negligence, a custodial sentence not exceeding three years or a monetary penalty.

In the same section