Key takeaways
- Scaffolding netting retains rubble and tools but allows rain to pass through unimpeded.
- Mesh porosity creates aerodynamic drag that increases the forces exerted on the anchorages.
- Fixing to the frame requires fasteners distributed across all standards and outer guardrails.
- A torn net must be logged and replaced without delay to maintain protection on the construction site.
Distinguishing rubble containment from waterproofing and assessing wind drag
On a building construction site, façade netting serves as equipment designed to catch accidental falls of small materials, spalling rubble or hand tools. Pursuant to art. 17 OTConst, measures must be taken at workstations and passageways so that workers are not endangered by falling objects and materials. However, the scaffolder must never treat this permeable knitted fabric like a solid tarpaulin or heat-shrink containment sheeting.
- Micro-perforated protective netting
- High-density polyethylene knitted sheet with regular open mesh, designed to arrest the trajectory of render splinters or falling screws without forming a watertight barrier against rainwater or blocking the natural flow of ambient air.
Netting provides no waterproofing against precipitation: water passes through the mesh driven by wind or runs down the strands without protecting renderers' fresh plaster. Attempting to use dense netting as a rain screen is a common technical error on platforms. Water penetrates beneath work decks and soaks timber or aluminium decking without ever drying out the work area.
The presence of netting directly modifies the static behaviour of the scaffolding. Even when open, the mesh offers significant resistance to air masses. Air passing through the apertures generates friction and aerodynamic head loss, resulting in increased tensile and compressive forces on the anchor points. This lateral force transmitted to the tubular frames depends directly on the permeability coefficient specific to the model used.
| Netting type | Air porosity | Containment capacity | Impact on anchorages |
|---|---|---|---|
| Wide-mesh knit for structural work | Approximately 70% to 80% | Coarse rubble, gravel, chisels | Moderate tensile force |
| Micro-perforated netting for renderers | Approximately 45% to 55% | Render chips, grinding debris, screws | Doubled tensile force |
| Tight dust-control fabric | Approximately 25% to 35% | Fine dust, sandblasting grit | Very high tensile force |
| Solid polyethylene tarpaulin | Zero (airtight) | Retains water and all debris | Maximum force, engineering calculation required |
Securing sheets to the structure and addressing tears on the frame
Façade scaffolding must remain stable in all circumstances. The standard anchoring plan must be recalculated or densified as soon as the structure receives textile cladding on its external faces, in accordance with recognised rules of safety technology. The scaffolder ensures that each outer frame transmits the load directly without tube deformation or fabric flapping.
- Positioning and alignment of the sheetUnroll the roll horizontally along the working level, applying the netting to the outside of the tubular frame standards without leaving folds or dangling excess lengths.
- Lashing to the top guardrail and standardsFasten the netting along the upper protective guardrail and to each vertical standard using UV-resistant self-locking plastic cable ties or braided nylon cord.
- Joining and overlapping lengthsProvide an overlap of at least 15 centimetres between two consecutive rolls, then close the joint with continuous stitching or closely spaced fasteners every 30 centimetres.
- Securing the bottom edgeFirmly secure the base of the netting to the toeboard or bottom ledger to prevent any rolling objects from passing through onto the metal decking.
During regular inspection rounds, netting torn by a scaffolding corner, perforated by debris, or degraded by mechanical friction must be recorded and replaced without delay. A slit in the fabric eliminates rubble containment and concentrates wind forces on neighbouring eyelets, leading to the progressive tearing away of the entire drop. The scaffolder cuts away the damaged section back to sound standards and laces a new sheet securely lashed to the frame, maintaining uniform tension throughout.
Aerodynamic behaviour and risk of mesh clogging
The permeability of scaffolding netting directly governs the stability of the structure against climatic surcharges. Contrary to a persistent misconception on construction sites, a micro-perforated sheet does not retain its initial drag coefficient indefinitely. During intensive work phases generating airborne particulate matter — such as concrete scabbling, masonry sandblasting or spray-applied mineral rendering —, the textile mesh traps a significant fraction of microparticles.
This progressive clogging transforms a theoretically ventilated screen into a virtually airtight surface. Under the combined effect of a downpour and hydraulic binder dust, fines agglomerate within the polyethylene monofilament weave, forming a rigid crust. The scaffolder will then find that the structure's effective wind-exposed surface area has sharply approached that of a solid tarpaulin.
| Sheet configuration | Residual air permeability | Direct consequence on the structure | Action required by the erection team |
|---|---|---|---|
| Standard new netting (approx. 50 g/m²) | High (unimpeded airflow) | Thrust force complies with standard erection plan | Visual check of ties to standards |
| Netting saturated with dust or render | Low (surface mesh clogged) | Multiplication of tensile forces on ties | Tightening of the anchoring grid or sheet replacement |
| Frozen netting with ice bridging | Zero to residual (formation of an impermeable barrier) | Total screen effect similar to solid sheeting | Temporary removal of elements or reinforcement of ties |
The Construction Work Ordinance highlights the need to protect workstations and access routes against falling objects, but this technical measure must under no circumstances compromise the overall equilibrium of the tubular steel framework. In the event of a weather warning or violent bise episode, monitoring deformations on the outer frames constitutes an absolute priority for the scaffolder.
Operating method for removal and repair of damaged components
The presence of a tear in netting creates two distinct problems: the breach of the physical barrier against projections towards the public domain and violent flapping generated under wind action. A flapping edge exerts jerky pull-out forces on adjacent plastic ties or textile bindings, risking spreading the tear across the entire bay.
To remedy such degradation without disrupting the overall operation of the construction site by finishing trades, the erection team must proceed systematically. Any improvised patching using adhesive tape or sharp metal ties is prohibited, as these solutions deteriorate the perimeter mesh under cyclic loading.
- Delineation and securing of the work areaTemporarily prohibit access to working levels located directly in line with the damaged bay. If the scaffolding faces the public highway, set up an exclusion perimeter or post a banksman on the ground for the duration of the work.
- Controlled cutting of defective fixingsUsing an electrician's diagonal cutters or a safety workshop knife, cut the cable ties in the damaged area. Hold the loose section using locking pliers or temporary straps to prevent it from catching the wind during a thermal gust.
- Installation of the repair patch or new dropUnroll a new sheet across the full width of the bay or position a reinforcement patch with the regulatory overlap. Securely tie both layers together along the standards and guardrails using UV-resistant self-locking polyamide cable ties.
- Mechanical tensioning and inspection of nearby anchoragesTension the sheet uniformly from bottom to top to eliminate air pockets. Take advantage of the intervention to verify the secure hold of the scaffolding eyebolts screwed into the façade wall plugs on adjacent bays.
In accordance with art. 17 OTConst, measures must be taken at workstations and passageways so that workers are not endangered by falling materials. The integrity of the netting constitutes the direct guarantor of this collective fall protection. Furthermore, when structural work conditions generate debris hazards above platforms, art. 6 OTConst mandates the wearing of safety helmets to guard against residual risks.
Incident management: tearing, clogging and securing
On a construction site in French-speaking Switzerland, the sudden failure of a sheet or a violent Föhn blast immediately tests the integrity of the temporary works. When netting tears, flaps against frames or begins tearing away under the effect of gusts funnelled in urban areas, the scaffolder must act systematically. The first action consists in eliminating the hazard at the foot of the scaffolding: cordon off a safety perimeter on the ground to safeguard public property or worker transit routes.
At workstations and passageways, measures must be taken so that workers are not endangered according to art. 17 OTConst. The chargehand ascends the structure only if it remains stable, equipped with a fall arrest harness anchored to structural anchor points and not to temporary guardrails. If the hanging sheet threatens to rip out the standards through an unexpected sail effect, it must be cut away or temporarily bound against the vertical standards using textile lashings or reinforced ties, without attempting to retension damaged mesh in the middle of a storm.
As soon as calm is restored, checking the wall plugs and base jacks is essential before any return to service. If the contractor finds that an extraordinary event compromises safety or necessitates unforeseen heavy repairs, they immediately inform the site management in accordance with the duty of diligence under the contract for work pursuant to the Code of Obligations (CO). Replacing torn netting is always carried out bay by bay, from top to bottom, reinstalling new ties every metre along the vertical standards.
Frequently asked questions
Can scaffolding netting replace a waterproof tarpaulin to protect a painted façade from rain?
No. Scaffolding netting is designed with an openness factor intended to break wind speed and stop projections of tools or debris. Rainwater passes freely through it by runoff and fine misting. Attempting to use it as moisture protection is a technical error: only a heat-welded or reinforced tarpaulin guarantees watertightness, but it requires a complete redesign of the anchoring plan to absorb significantly higher tensile loads.
What should be done if a trade cuts netting to remove materials without authorisation?
The scaffolder must record the alteration in writing and alert the site management. Slitting a sheet creates a tear line that, under wind action, destabilises the entire bay and eliminates debris containment. The scaffolder closes access to the affected platform, strips the damaged sheet and lashes a new netting panel to the perimeter frames, at the expense of the contractor responsible for the unauthorised modification.
How should one respond to a weather warning forecasting exceptional gusts on sheeted scaffolding?
The chargehand primarily inspects the façade ties and the condition of the frame-to-netting connections. If the initial stability calculations under standard SIA 261 did not anticipate winds of such intensity with netting in place, the precautionary measure consists in opening or rolling back the netting sheets and tying them tight against the standards to reduce the windage area and relieve the ties.
What ties should be used to fix netting and prevent it from flapping in the wind?
UV-resistant polyamide cable ties or annealed tie wire applied with end cutting nippers should be used. Fasteners must directly wrap around vertical tubes and horizontal rails every 50 to 100 centimetres. Leaving a free edge or using adhesive tape inevitably results in the netting flapping, premature wear from friction against the steel, and tearing during the first wind gust.
Texts and standards cited
- OTConst art. 17protection against collapse of construction elements or falling objects and materials: at workstations and passageways, measures must be taken so that workers are not endangered