Key takeaways
- The safety and health protection plan records interruption criteria prior to any assembly.
- The official meteorological reference must be defined in agreement between the scaffolder and the site management.
- The site foreman or lead scaffolder holds the sole authority to order the immediate evacuation of the platform.
- Suva directives require securing decks and tarpaulins as soon as thresholds are reached.
Setting shutdown criteria and the reference station in the safety plan
Anticipating wind risk begins well before the first gusts appear on the facade. On a building construction site, the behaviour of scaffolding depends heavily on its equipment: bare frames, decking with debris netting, or fully sheeted structures. The windage of these surfaces greatly multiplies the loads on ties and compromises the balance of the scaffolder handling large framework components, such as guardrails or aluminium decks.
According to art. 4 OTConst, before work begins, the employer ensures that there is a plan detailing the necessary measures for the work carried out on the construction site. This safety and health protection plan must not be limited to statements of intent. It explicitly records the actions to be taken according to wind force, the conditions for temporary removal of netting or tarpaulins, as well as operational monitoring arrangements.
Wind data reported by uncertified consumer platforms do not constitute an enforceable technical basis. The site agreement must specify the MeteoSwiss station most representative of local topography, taking into account funnel effects, valley thermal winds, or down-draughts created by neighbouring structures. On high-rise or particularly exposed construction sites in French-speaking Switzerland (lakeshores, Pre-Alpine ridges), using a calibrated handheld anemometer at the highest working platform level remains the benchmark for observing the actual gusts experienced by the team.
| Wind force / Gusts | Scaffolding configuration | Mandatory measure on the decking |
|---|---|---|
| From 45 km/h to 50 km/h | Assembly of bare components, laying decks | Interruption of handling components with high windage (sheeting, cantilever brackets, top frames). |
| From 60 km/h | Scaffolding with netting or light tarpaulins | Stop assembly, secure loose decks, fold back or open screening devices. |
| From 70 km/h to 80 km/h | Any facade scaffolding configuration | Immediate evacuation of the structure, blocking access with barriers, checking ground anchorages. |
Designating the competent person to order evacuation and recording the procedure
Once limit values are written into safety documents, responsibility for triggering protective measures rests on a clear chain of command. According to art. 5 OTConst, the employer designates on each construction site a competent person responsible for occupational safety and health protection, able to give directives to workers. This person has the required authority to enforce the immediate cessation of lifting or assembly operations as soon as scaffolder safety is no longer guaranteed.
- Continuous weather monitoringThe chargehand or site foreman consults MeteoSwiss warning bulletins in the morning and at midday. They measure the wind at the top of the structure if gusts strengthen noticeably.
- Halting handling tasksAs soon as the first threshold is exceeded, the person in charge halts lifting frames and decks with a crane or site hoist. Scaffolders complete the locking of components already in position.
- Securing the structureWorking decks that are not clipped down are secured, hop-up brackets are checked, and tarpaulins are rolled up or laced in accordance with manufacturer instructions to limit wind thrust on anchor plugs.
- Evacuation and blocking accessThe lead scaffolder has personnel descend, removes access ladders from the lowest levels, or installs prohibition barriers along with the sign indicating that the scaffolding is out of service.
The scaffolder must under no circumstances negotiate a site shutdown under pressure from finishing trades. The Suva directive on scaffolding points out that the overall stability of the structure and the physical integrity of personnel take precedence over scheduling demands. When the site foreman makes the decision to evacuate, the order applies to their own workers but also entails the immediate closure of working platforms for other trades working on the facade.
Operational withdrawal protocols and securing movable components
As soon as the weather warning exceeds forecast thresholds or the site anemometer signals that the critical zone is approaching, the assembly team interrupts vertical handling. The evacuation decision must not be improvised at the last moment under gusts: it requires an orderly sequence to stabilise unlocked components before the decking becomes unusable. Under LAA, to prevent occupational accidents and diseases, the employer must take all measures shown by experience to be necessary, applicable according to the state of the art, and adapted to the given conditions; workers assist them. On scaffolding, this duty translates into immediately securing exposed workstations.
| Scaffolding component | Immediate aerodynamic risk | Action required from the team | Locking method |
|---|---|---|---|
| Loose floor decks | Uplift caused by negative pressure | Locking onto transoms | Anti-uplift wedges or screw clamps |
| Frames and standards being erected | Overturning out of the facade plane | Connecting to lower frames | Safety pins inserted and locked |
| Cantilever brackets and overhangs | Torsion under gust forces | Installing a temporary diagonal | Right-angle couplers tightened with a torque wrench |
| Tarpaulins and protective netting | Sail effect tearing anchorages away | Tight rolling against standards | Ratchet lashing straps every two metres |
| Access trapdoors and ladders | Flapping and hinge breakage | Closing and locking the hatch | Mechanical locking of the deck catch |
- Stopping lifting and lowering loadsImmediately cease using wire-rope hoists, lifting jibs, and materials hoists. Lower any suspended load to the ground and cut the electrical supply to the control panel to prevent any inadvertent operation.
- Securing working decks and accessoriesCheck that each deck on the last assembled level has its anti-uplift lock. Gather hand tools, 19/22 mm ratchet spanners, bolts, and couplers into closed metal boxes, securely lashed to the inner standards on the wall side.
- Managing sheet permeabilityIf the structure includes micro-perforated netting or impermeable sheeting not yet fully stiffened by the final tie pattern, roll up and lash these sheets to restore the structure's air permeability.
- Orderly evacuation via stair flightsHave scaffolders descend via the site stair access towers. Strictly prohibit the use of internal service ladders during destabilising gusts.
- Physical closure of ground-level accessClose access barriers at ground level, install a rigid barrier rail, and display the red prohibition notice strictly barring access to the scaffolding during the storm.
Checking ties and post-wind return to service
After a storm or a violent wind front has passed, the scaffolding cannot be returned to the trades without a formal check of its structural integrity. The ordinance on construction work requires ensuring that workstations and passageways present no risk of collapse or falling objects. Under art. 5 OTConst, the employer designates on each construction site a competent person responsible for occupational safety and health protection, able to give directives to workers. It falls to this technical supervisor, generally the site foreman scaffolder, to conduct the rigorous inspection before any site reopening.
- Visual check of standards verticality (checking out-of-plumb induced by dynamic wind loads).
- Examination of mechanical anchors or eyebolts: detection of any partial pull-out, cracking of the substrate concrete, or slippage in masonry.
- Checking the tightness of anchor couplers connecting the fixed tie rod to vertical standards (compliant tightening torque of 50 Nm).
- Inspection of ground base packing: absence of scouring by runoff water beneath sole plates.
- Checking decking levelness: verifying that no access hatch has unhooked from tubular transoms.
- Review of edge protections: top guardrails, intermediate guardrails, and 15 cm toeboards securely replaced in accordance with the ordinance on construction work.
When site checks reveal loosening or a broken anchor, the section must be isolated with barrier tape and a prohibition sign. Replacing defective ties is carried out advancing from a stable area, equipped with a fall-arrest harness attached to a certified anchorage point. Once rectification work is completed, the site foreman draws up a post-severe-weather inspection report entered in the site daily log, lifts the access restriction, and transmits the authorisation to resume work to the site management.
Crisis and failure management under strong winds
When gusts exceed local MeteoSwiss forecasts or the wind rises suddenly during operations, the emergency protocol applies immediately. The absolute priority remains the evacuation of decking and the withdrawal of personnel to sheltered areas at ground level. If unsecured components, such as access decks, aluminium platforms, or debris netting, begin to vibrate dangerously or threaten to blow away, scaffolders must under no circumstances attempt to climb up to secure them in the middle of the storm.
The employer prepares the necessary arrangements in advance within their safety and health protection plan, in accordance with art. 4 OTConst, to strictly regulate these emergency situations. As soon as a lull is confirmed by official readings, the site foreman performs a full inspection before any operations resume: condition of anchor plugs, potential deformation of tubular standards, integrity of diagonals, and tarpaulin tension. If a tie has pulled out from the masonry, new drilling with the installation of an expansion anchor or suitable chemical anchoring must be executed and proof-tested before assembly teams re-enter the bay concerned.
Frequently asked questions
Which weather station is authoritative when deciding to stop assembly?
The official reference is the MeteoSwiss station closest to the construction site, supplemented by a cup anemometer read directly at the level of the highest platform. Smartphone consumer apps have no contractual or legal validity in the event of a dispute. The exact source must be explicitly designated in the safety plan drawn up before work begins.
At what wind speed must scaffolding assembly be stopped?
Suva directives recommend stopping the handling of loads and assembly as soon as there are sustained winds or strong gusts. In Swiss practice, handling decks and tarpaulins becomes impracticable from 45 km/h. A formal threshold between 50 and 60 km/h is generally set in writing in the safety plan to enforce a total shutdown and immediate withdrawal.
Who on the construction site has the authority to order an evacuation?
The decision rests with the competent person designated by the scaffolding contractor, generally the site foreman or chargehand, who holds authority over personnel. The site management may demand a shutdown if conditions threaten overall safety, but the scaffolder remains responsible for their workers' safety and may exercise their right to stop work as soon as the threshold is reached.
What should be done with tarpaulins and netting if a storm is forecast in advance?
Before gusts arrive, the team must roll up or remove sheeting and debris nets to eliminate the sail effect that would overload facade ties. Access openings must be locked and loose material on the ground strapped down. Bare scaffolding offers lower wind resistance, thus protecting the entire structure against accidental pull-out.
Texts and standards cited
- OTConst art. 4safety and health protection plan: before work begins, the employer ensures that there is a plan detailing the necessary measures for the work carried out on the construction site, including the organisation of first aid; this plan is drawn up in writing or in a form allowing proof by text.
- OTConst art. 5organisation of occupational safety and health protection: the employer designates on each construction site a competent person responsible for occupational safety and health protection, able to give directives to workers (para. 1); any person who, through their behaviour or state, exposes themselves or endangers other persons must be dismissed from the construction site (para. 2).